Hannah v. Steinman

112 P. 1094, 159 Cal. 142, 1911 Cal. LEXIS 303
CourtCalifornia Supreme Court
DecidedJanuary 4, 1911
DocketS.F. No. 5327.
StatusPublished
Cited by38 cases

This text of 112 P. 1094 (Hannah v. Steinman) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hannah v. Steinman, 112 P. 1094, 159 Cal. 142, 1911 Cal. LEXIS 303 (Cal. 1911).

Opinion

ANGELLOTTI, J.

Plaintiff appeals from a judgment denying him any relief and from an order denying his motion *144 for a new trial in an action brought by him to obtain a decree that a contract of lease has been rescinded.

Defendant is the owner of an unimproved lot of land in San Francisco, with a frontage of ninety feet on the northerly line of Geary Street between Larkin and Hyde streets. On July 7, 1906, a contract of lease was executed by the parties, whereby defendant let to plaintiff and plaintiff hired from defendant said lot for a term of three years commencing August 7, 1906, for the sum of nine thousand dollars, payable in monthly installments of two hundred and fifty dollars, and the privilege was thereby given to plaintiff to extend the lease for a further term of two years at a monthly rental of three hundred dollars. It was recited therein that as the lessee contemplated erecting buildings on the premises he would hold the owner free of any claim of lien on account thereof, that all buildings or other improvements placed thereon by plaintiff should be plaintiff’s property at the termination of the lease, that he would pay all taxes thereon and that he should have ten days free of rent at the termination of the lease in which to remove them. Up to the fifth day of July, 1906, the ordinances of the city and county of San Francisco were such that a permit could be obtained for the construction of a wooden building on this property, but on July 5, 1906, an ordinance was enacted that rendered it unlawful to erect or construct wooden buildings within certain limits prescribed therein, which included this lot. Neither plaintiff nor defendant knew of this change in the laws of the city and county at the time of the execution of the lease, each supposing that he knew and understood the law relative to such matters and each apprehending the law to be that the erection of a temporary wooden building on said lot would be lawful. Plaintiff and defendant never met personally until long after the execution of the lease, all negotiations between them having been conducted through a firm of real estate brokers who acted purely as middlemen and who were not the agents or representatives of the defendant. The finding on this question of agency is fully sustained by the evidence. About two weeks after the execution of the lease, plaintiff, having already paid two hundred and fifty dollars rent, applied to the board of public works of the city and county for a permit to erect a wooden building on said property, and he then discovered

*145 that the law relative to fire limits had been changed and that no permit could be obtained. There was no attempt to question the positive evidence introduced by plaintiff to the effect that without the right to erect a wooden building upon this lot, the lease for three years only with the privilege of two years more at the prescribed rental was absolutely without value to a tenant, and that plaintiff never would have entered into the contract had he supposed that he could not erect such a building thereon. It was impossible to use the lot to advantage without a building, and the cost of such a building as could be constructed in view of the building ordinances applicable would be so great as to render the lease in question valueless. The evidence compels the conclusion that it was within the contemplation of both parties that the lessee could use the lot to advantage only by constructing a wooden building thereon and that he was taking it for such use. Upon learning that a wooden building could not be constructed plaintiff so informed the real estate agents, said the lot was of no value to him unless he was given a longer term and protested against paying the rent for the second month. He subsequently paid rent for two additional months to Mr. Israel of the Union Trust Company for defendant, protesting at each payment against the same. He was informed by Mr. Israel that defendant was East but would shortly return and he allowed the matter to remain in abeyance until defendant’s return. The evidence indicated that defendant was advised of plaintiff’s dissatisfaction with the lease and that he (plaintiff) was disposed not to go on with it. Immediately upon his return (January 26, 1907) negotiations were commenced between the parties looking to a longer term, but they came to nothing. In his written proposition of February 24, 1907, regarding the terms of a new lease for twenty years, plaintiff asked defendant, if not satisfied with the proposition, to consider releasing him, saying that he had already paid dearly for his experience. As soon as it had developed that no satisfactory arrangement could be made plaintiff consulted an attorney, and was informed that he had a right to rescind the contract of lease. This was on March 1, 1907. He had full knowledge of the facts which entitled him to rescind two weeks after the agreement was entered into, but did not know that an agreement could be rescinded on account of such a mistake until *146 so advised by Ms attorney. On March 5, 1907, he served a notice of rescission on defendant, specifying mistake and failure of consideration as the grounds, offering therein to restore possession of the land, authorizing defendant to enter upon and hold the same, offering to execute such release of the lease as defendant might desire and to do all acts necessary in order to fully restore to defendant any and all things of value received by him as fully and completely as if said lease had not been made, “on condition that you restore to me all moneys and things of value received as consideration for said lease.” Defendant refused to agree to a rescission and this action was at once commenced.

The trial court found as facts “that the use of said real property described in said lease by the erection of a building or buildings which could be removed, was not the only valuable consideration for the obligation of plaintiff under said contract,” and that plaintiff “did not use due diligence in rescinding said agreement.” Both of these findings are attacked as not being sustained by the evidence. In its purported conclusions of law was one that plaintiff "did not rescind said contract promptly upon discovering the facts which entitled him to rescind the same and when he was aware of his right to rescind,” and this, treated by plaintiff as a finding of fact, is also attacked as being unsupported by the evidence.

A party to a contract may rescind the same if his consent thereto was given by mistake either of law or fact. (Civ. Code, sec. 1689, subd. 1.) We deem it unimportant whether the alleged mistake in this case be held to be a mistake of fact or one of law. The mistake was the belief of both parties that the lot was not within the limits fixed by .ordinance wherein it was unlawful under the ordinances of the city and county of San Francisco to construct a wooden building—ignorance of the fact that an ordinance had just been adopted placing-such lot within such limits. Unconscious ignorance of a fact material to the contract or belief in the present existence of a thing material to the contract constitutes a mistake of fact (Civ. Code, sec. 1577), and a misapprehension of the law by all parties, all supposing that they know and understand it, and all making substantially the same mistake as to the law, constitutes a mistake of law. (Civ. Code, see. 1578.) Upon *147

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Super.Ct. (Sanchez)
223 Cal. App. 4th 567 (California Court of Appeal, 2014)
Briercrest Development v. City of La Mesa CA4/1
California Court of Appeal, 2013
Harris v. Rudin, Richman & Appel
116 Cal. Rptr. 2d 552 (California Court of Appeal, 2002)
Gartner v. Eikill
319 N.W.2d 397 (Supreme Court of Minnesota, 1982)
Pauley Petroleum Inc. v. United States
591 F.2d 1308 (Court of Claims, 1979)
Guthrie v. Times-Mirror Co.
51 Cal. App. 3d 879 (California Court of Appeal, 1975)
The DOVER POOL & RACQUET CLUB, INC. v. Brooking
322 N.E.2d 168 (Massachusetts Supreme Judicial Court, 1975)
Williams v. Puccinelli
236 Cal. App. 2d 512 (California Court of Appeal, 1965)
Golem v. Fahey
191 Cal. App. 2d 474 (California Court of Appeal, 1961)
Bellwood Discount Corp. v. Empire Steel Buildings Co.
346 P.2d 467 (California Court of Appeal, 1959)
Vickerson v. Frey
224 P.2d 126 (California Court of Appeal, 1950)
Stock v. Meek
221 P.2d 15 (California Supreme Court, 1950)
Butler v. Newcomb
214 P.2d 857 (California Court of Appeal, 1950)
Sackett v. Starr
212 P.2d 535 (California Court of Appeal, 1949)
Brown v. Volz
204 P.2d 110 (California Court of Appeal, 1949)
Adams v. Heinsch
200 P.2d 796 (California Court of Appeal, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
112 P. 1094, 159 Cal. 142, 1911 Cal. LEXIS 303, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hannah-v-steinman-cal-1911.