Wisconsin Power & Light Co. v. Public Service Commission

437 N.W.2d 888, 148 Wis. 2d 881, 1989 Wisc. App. LEXIS 101
CourtCourt of Appeals of Wisconsin
DecidedJanuary 26, 1989
Docket88-1320
StatusPublished
Cited by7 cases

This text of 437 N.W.2d 888 (Wisconsin Power & Light Co. v. Public Service Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wisconsin Power & Light Co. v. Public Service Commission, 437 N.W.2d 888, 148 Wis. 2d 881, 1989 Wisc. App. LEXIS 101 (Wis. Ct. App. 1989).

Opinion

EICH, J.

Wisconsin Power and Light Company (WPL) appeals from that portion of an order affirming the Public Service Commission's (PSC) denial of the company's application to install a "phase-shifting transformer" as part of its electrical generation and distribution system. The issues are: (1) whether the term "public" in sec. 196.49(3)(b), Stats., which requires the PSC to certify the "public convenience and necessity" of proposed utility projects, may be read to include persons other than the customers of the particular utility applying for the permit; (2) if so, whether the commission's findings of fact are adequate to support its order; and (3) whether the PSC acted arbitrarily and capriciously by denying WPL's petition for rehearing based on the company's attempt to comply with the commission's request that it negotiate with other utilities to seek compensation for the transmission losses the phase shifter was intended to prevent.

*884 We believe that the “public” envisioned by the statute comprises all Wisconsin consumers of utility services, not just the ratepayers of the applying utility. We also conclude that the commission’s findings are adequate to support its order and we see nothing arbitrary or capricious in the procedures followed in this case.

WPL is a public utility providing wholesale and retail electric service to customers in southern and central Wisconsin. In 1986, WPL applied to the commission for a permit — a certificate of public convenience and necessity — to establish a new interconnection with an adjoining utility, Dairyland Power Cooperative. WPL and Dairyland are members of regional “pools” of interconnected electric utilities, the Mid-Continent Area Power Pool (MAPP) and the Mid-America Interconnected Network (MAIN). The primary utilities in the two pools are the Commonwealth Edison Company in Illinois and the Northern States Power Company in Minnesota. From time to time power is shifted between the pools in order to meet the needs of customers in the various regions served by pool members — from Northern States to Commonwealth Edison, for example. In such cases, the power often travels from Northern States to Commonwealth over lines owned by Dairyland and WPL.

Whenever electricity travels through transmission lines it meets resistance in the wires, and this results in the loss of some of the power as heat — much as heat is lost in water pipes as the water travels from the basement water heater to the upstairs faucet. These “transmission losses” are unavoidable, and, all else being equal, the more power a line carries, the more losses will result. And these losses increase the utility’s overall cost of production and transmission because, to *885 meet its customers’ needs, the utility must compensate for the losses by generating more electricity than would otherwise be necessary.

In cases where WPL is part of the power transfer transaction — as when it purchases power from Northern States and then resells it to Commonwealth Edison — it can recover compensation for the transmission losses in the price it charges Commonwealth. But electricity also travels through WPL lines in interre-gional power transfers through the MAIN and MAPP grids in cases where WPL is not a party to the transaction. This is so because electricity will always seek the path of least resistance. Thus, when a utility to the west of WPL’s service area sells electricity to one south of it, and the path of least resistance is through WPL lines, the electricity will travel through those lines. When this happens, WPL’s system power losses — and therefore its operating costs — increase.

A phase shifter is a device which can, in effect, alter the resistance on a company’s lines so that only so much power will flow through those lines as the shifter permits. With the device in place, WPL would be able to “stop” power which would otherwise enter and flow through its lines on the way from the western seller to the ultimate southern purchaser. The power, meeting the increased resistance created by the phase shifter, will seek out a freer path through the lines of another utility. By “rerouting” or diverting these interregional transfers onto the lines of other utilities, WPL will be able to eliminate losses it otherwise would incur by “shifting” those losses to neighboring utilities.

The commission, finding that “[t]he primary proposed purpose, for the phase shifter was to minimize total electrical losses for the combined WPL and [Dairyland] transmission systems by shifting these *886 losses to other transmission systems,” determined that the project would neither improve WPL’s system efficiency or reliability, nor reduce or eliminate overall system losses. Then, finding that installation of the shifter “would add to the cost of electric service for all ratepayers without proportionately increasing the value of service” and was not necessary to meet the public’s needs for an adequate supply of electricity, the commission denied WPL’s application. WPL sought review in the circuit court and the court affirmed the commission’s order.

“PUBLIC” CONVENIENCE AND NECESSITY HH

WPL’s application was filed under sec. 196.49(3)(b), Stats., which provides as follows:

[N]o project may proceed until the commission has certified that public convenience and necessity require the project. The commission may refuse to certify a project if it appears that the completion of the project will do any of the following:
1. Substantially impair the efficiency of the service of the public utility.
2. Provide facilities unreasonably in excess of the probable future requirements.
3. When placed in operation, add to the cost of service without proportionately increasing the value or available quantity of service unless the public utility waives consideration by the commission, in the fixation of rates, of such consequent increase of cost of service.

As indicated, the PSC found as an “ultimate fact” that construction of the phase shifter was not necessary to satisfy the reasonable needs of the public for an adequate supply of electric energy. It also found that the shifter would add to the cost of service for “all *887 ratepayers” without proportionately increasing the value of the service. These determinations were based on other commission findings that the primary purpose of WPL’s proposed installation of the phase shifter was to minimize the losses incurred by its participation in interregional transfers by “shifting” those losses to other utilities’ transmission systems. WPL has not challenged any of the commission’s findings of fact.

WPL argues first that because it is undisputed in the record that its ratepayers will benefit from the phase shifter due to that device’s ability to reduce the losses and resulting costs incurred by the utility when interregional transfers of electricity flow through its lines, the commission must have interpreted the word “public” in the statutory phrase “public convenience and necessity” as extending beyond those members of the public who are WPL customers — to the entire “consuming public” of the state. This, WPL contends, is an erroneous interpretation of the statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wisconsin Electric Power Co. v. United States
90 Fed. Cl. 714 (Federal Claims, 2009)
Citizens' Utility Board v. Public Service Commission
565 N.W.2d 554 (Court of Appeals of Wisconsin, 1997)
Interstate Telephone Cooperative, Inc. v. Public Utilities Commission
518 N.W.2d 749 (South Dakota Supreme Court, 1994)
Central West Virginia Refuse, Inc. v. Public Service Commission
438 S.E.2d 596 (West Virginia Supreme Court, 1993)
Nelson Bros. Furniture Corp. v. Wisconsin Department of Revenue
449 N.W.2d 328 (Court of Appeals of Wisconsin, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
437 N.W.2d 888, 148 Wis. 2d 881, 1989 Wisc. App. LEXIS 101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wisconsin-power-light-co-v-public-service-commission-wisctapp-1989.