Central West Virginia Refuse, Inc. v. Public Service Commission

438 S.E.2d 596, 190 W. Va. 416, 1993 W. Va. LEXIS 226
CourtWest Virginia Supreme Court
DecidedDecember 13, 1993
Docket21750
StatusPublished
Cited by53 cases

This text of 438 S.E.2d 596 (Central West Virginia Refuse, Inc. v. Public Service Commission) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central West Virginia Refuse, Inc. v. Public Service Commission, 438 S.E.2d 596, 190 W. Va. 416, 1993 W. Va. LEXIS 226 (W. Va. 1993).

Opinion

MILLER, Justice:

Central West Virginia Refuse, Inc., (Central), appeals a final order of the Public Service Commission (PSC), dated March 10, 1993, that reduced the base tariff rate Central could charge its customers from $27.45 to $21.58 per ton. On appeal, Central alleges two errors: (1) the PSC exceeded its statutory authority when it refused to follow its earlier decision in the original tariff case involving Central, and (2) the evidence was inadequate to support several of the PSC’s findings. We have reviewed the record and find no error; accordingly, we affirm the final order of the PSC.

I.

Central owns and operates a solid waste disposal facility in Braxton County. In 1989, the PSC was given jurisdiction over the establishment and enforcement of rates and fees charged by commercial solid waste facilities. 1

In July of 1989, Central was required to file an original tariff request with the PSC. The application filed by Central, which was assigned Case No. 89-405-SWF-T, requested a rate of $32.00 per ton. This amount included a base rate of $29.25 per ton, a State assessment fee of $1.25, a county assessment fee of $0.50 per ton, and a solid waste interim fee of $1.00 per ton, for a total assessment of $2.75. This rate was accepted by the PSC on an interim basis without an *418 audit or review, and, subject to refund, became effective on or after July 1, 1989.

Because staff had not yet conducted its audit, on May 9, 1991, the Administrative Law Judge (ALJ) issued a recommended decision that Case No. 89-405-SWF-T be dismissed from the docket. The PSC did not adopt the ALJ’s recommended decision and instead remanded the case for a hearing. After hearings were held, the ALJ recommended that the $29.25 base rate be approved for use on a permanent basis, thus making a refund unnecessary. The PSC fully reviewed the recommended decision and, in its order dated March 18, 1992, reduced the base rate Central could charge to $27.45 per ton or $30.20 per ton including assessments.

On June 6, 1991, Central filed an application to increase its rates at the Braxton County landfill to $50.00 per ton, including all assessments. 2 This application was assigned Case No. 91-400-SWF-42A. In a decision dated April 9,1992, the ALJ determined that the rate established in Case No. 89-405-SWF-T should be used as a floor upon which cost increases should be added because he found the same test year was used in establishing the proper rate in both proceedings. He recommended that the rate per ton be increased to $37.64. Both the staff and Central filed exceptions to this recommended order. Once again, the PSC refused to adopt the ALJ’s decision and, instead, ordered Central to charge a base rate of $21.58 per ton plus assessments. Central appeals this order pursuant to W.Va.Code, 24A-8-1. 3

II.

Over a decade ago, in Monongahela Power Co. v. Public Service Commission, 166 W.Va. 423, 276 S.E.2d 179 (1981), we discussed at great length the standard of review this Court will apply in an appeal of an order of the PSC. We adopted a comprehensive standard from a test established by the United States Supreme Court in Permian Basin Area Rate Cases, 390 U.S. 747, 88 S.Ct. 1344, 20 L.Ed.2d 312 (1968). We incorporated this standard into Syllabus Point 2 of Monongahela Power:

“In reviewing a Public Service Commission order, we will first determine whether the Commission’s order, viewed in light of the relevant facts and of the Commission’s broad regulatory duties, abused or exceeded its authority. We will examine the manner in which the Commission has employed the methods of regulation which it has itself selected, and must decide whether each of the order’s essential elements is supported by substantial evidence. Finally, we will determine whether the order may reasonably be expected to maintain financial integrity, attract necessary capital, and fairly compensate investors for the risks they have assumed, and yet provide appropriate protection to the relevant public interests, both existing and foreseeable. The court’s responsibility is not to supplant the Commission’s balance of these interests with one more nearly to its liking, but instead to assure itself that the Commission has given reasoned consideration to each of the pertinent factors.”

See, e.g., Chesapeake & Potomac Tel. Co. v. Public Serv. Comm’n, 171 W.Va. 494, 300 S.E.2d 607 (1982).

In Chesapeake & Potomac Telephone Co. v. Public Service Commission, 171 W.Va. at 498, 300 S.E.2d at 611, we summarized the detailed standard for our review of an order of the PSC contained in Syllabus Point 2 of Monongahela Power Co. v. Public Service Commission, supra:

“(1) [Wjhether the Commission exceeded its statutory jurisdiction and powers; (2) whether there is adequate evidence to support the Commission’s findings; and, (3) whether the substantive result of the Commission’s order is proper.”

*419 III.

Central is not arguing that, as a result of the PSC’s actions, it cannot maintain its financial integrity, .attract necessary capital, or fairly compensate its investors for the risks they have assumed. Rather, it argues that the PSC abused its statutory power when it failed to follow its earlier decision and that there was insufficient evidence to support several of the PSC’s findings.

Central’s main argument is that because the staff .used the same test year, field information, and audit information in both Case No. 89-405-SWF-T and Case No. 91-400-SWF-42A, the ALJ did not err when he used the rate established in Case No. 89-405-SWF-T as a floor upon which an upward adjustment should be made in Case No. 91-400-SWF-42A. Specifically, Central contends that because no one appealed the order in Case No. 89-405-SWF-T, it was a final order that the PSC had already determined was reasonable; thus, the findings in the first case are entitled to a preclusive effect.

The PSC responds that although the test year used by staff in Case No. 89-405-SWF-T was a starting point in reaching a proper rate in this ease, staff did conduct additional financial investigations and filed a separate report. Furthermore, the PSC argues that because the rates established in both proceedings must be reached independently of each other, it is not bound by findings of facts in earlier proceedings. Finally, the ■ PSC maintains that the doctrine of stare decisis does not apply to administrative proceedings.

A.

In essence, Central is contending that the PSC abused or exceeded its legitimate authority under W.Va.Code 24-2-1, et seq., by not adhering to its earlier ruling in Case No. 89^05-SWF-T.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Industrial Energy Consumer Group v. Public Utilities Commission
2024 ME 60 (Supreme Judicial Court of Maine, 2024)
Sierra Club v. Public Service Commission of West Virginia
827 S.E.2d 224 (West Virginia Supreme Court, 2019)
Delby B. Pool v. Greater Harrison County Public Service District
821 S.E.2d 14 (West Virginia Supreme Court, 2018)
In Re: A.M.
West Virginia Supreme Court, 2017
David C. Tabb v. Jefferson County Commission
West Virginia Supreme Court, 2015

Cite This Page — Counsel Stack

Bluebook (online)
438 S.E.2d 596, 190 W. Va. 416, 1993 W. Va. LEXIS 226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-west-virginia-refuse-inc-v-public-service-commission-wva-1993.