Citizens' Utility Board v. Public Service Commission

565 N.W.2d 554, 211 Wis. 2d 537, 1997 Wisc. App. LEXIS 461
CourtCourt of Appeals of Wisconsin
DecidedMay 1, 1997
Docket96-0867
StatusPublished
Cited by19 cases

This text of 565 N.W.2d 554 (Citizens' Utility Board v. Public Service Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Citizens' Utility Board v. Public Service Commission, 565 N.W.2d 554, 211 Wis. 2d 537, 1997 Wisc. App. LEXIS 461 (Wis. Ct. App. 1997).

Opinion

DEININGER, J.

The Public Service Commission and Wisconsin Electric Power Company appeal an order vacating and remanding the Public Service Commission's decision and order authorizing Wisconsin Electric Power Company to construct an *540 independent spent fuel storage installation at its Point Beach Nuclear Power Plant. The trial court concluded that the Public Service Commission had erred in determining that the Environmental Impact Statement for the proposed project was adequate. Because we conclude that the Public Service Commission's determination regarding the adequacy of the Environmental Impact Statement should be accorded great weight deference and that it had a rational basis, we reverse the circuit court's order.

BACKGROUND

Wisconsin Electric Power Company (WEPCO) applied to the Public Service Commission (PSC) for authority to construct and operate an independent spent fuel storage installation (ISFSI) at its Point Beach Nuclear Power Plant. The ISFSI would consist of concrete pads on which a series of "dry storage" casks are placed to house the spent nuclear fuel assemblies from Point Beach's two reactors. Spent fuel assemblies continue to generate heat and are highly radioactive. They must therefore be properly and securely stored for many years following removal from the reactors. Currently, spent fuel assemblies at Point Beach are stored in the facility's spent fuel pool, where they are cooled by circulating water. The pool however, is almost full of fuel assemblies and cannot be modified to house additional assemblies. If an additional storage facility of some type is not constructed, the pools will be full in 1998, and the nuclear generating plant would likely be required to cease operation at that time, even though its two units are federally licensed to operate until 2010 and 2013. Even at present, there is not enough room in the pool to allow for the complete *541 unloading of both reactors, which would occur during decommissioning of Point Beach.

The accumulation of spent fuel assemblies at Point Beach, and at nuclear generating plants throughout the United States, results from the U.S. Department of Energy's (DOE) present inability to accept high level radioactive waste. Owners of the waste, like WEPCO, are required to store the material until DOE takes title to it. 1 Even though WEPCO has a contract with DOE for the removal of spent fuel from Point Beach to begin in 1998, DOE does not expect that any federal disposal facility will be operational before 2010. The PSC found that "[w]hen or whether DOE will begin taking spent nuclear fuel is a matter of speculation," and that complete removal of all spent fuel from Point Beach will take from 23 to 32 years once removal begins, if removal proceeds according to DOE's current removal schedule. The proposed ISFSI would utilize a type of air-cooled "dry cask," constructed of concrete and steel, which has been approved by the Nuclear Regulatory Commission (NRC) for temporary storage of spent fuel assemblies. The PSC's order authorized the construction and operation of only twelve such casks, although the concrete pads to be constructed would allow for the eventual use of forty-eight casks. 2

*542 Although an Environmental Impact Statement (EIS) is not usually required for applications of the type under consideration, the PSC determined that an EIS was warranted for WEPCO's application to construct an ISFSI. 3 The final EIS, prepared by PSC staff with assistance from the Radiation Protection Unit in the Department of Health and Social Services, encompasses 163 pages plus numerous appendices. Public hearings were conducted October 11 to 14 and 17 to 21, 1994, in Manitowoc, and on October 26 to 28, 1994, in Madison. In its Findings of Fact, Conclusions of Law, Certificate, Order and Interim Order, issued February 9, 1995, the PSC determined that "[t]he EIS adequately describes the environmental effects of the proposed facility and its reasonable alternatives, including effects on public health and safety" and further that:

[T]he ISFSI as proposed does not constitute a significant risk to public health and that the facility will not create major or significant effects on wild life or plant life. The facility will not create an *543 unreasonable risk to the quality of the water in Lake Michigan.

The PSC's order of February 9, 1995, authorized WEPCO to construct the ISFSI with twelve casks and two concrete pads, but directed the utility to file a new application "before constructing any additional casks or making any other additions to the Facility that would increase its capacity beyond that of-the 12 casks authorized herein." The petitioners-respondents (collectively, CUB) petitioned the circuit court for review under § 227.53, STATS. The trial court concluded that "there is no rational basis for the Commission's ultimate determination that the EIS was adequate" because the EIS did not adequately address "reasonably foreseeable future impacts" and "reasonably related alternatives to the ISFSI." The trial court vacated the PSC order and remanded to the agency with directions to supplement the EIS in the areas deemed deficient. From this portion of the circuit court's order, the PSC and WEPCO appeal. 4 Additional facts will be presented in the analysis which follows.

ANALYSIS

a. Standard of Review

All parties concur that our review is directed to the determination of EIS adequacy in the PSC order, not to the EIS itself. There is no dispute that we review the PSC decision and order directly, applying the same standard of review as the trial court but owing no *544 deference to the trial court's conclusions. See Barnes v. DNR, 178 Wis. 2d 290, 302, 506 N.W.2d 155, 160 (Ct. App. 1993), aff'd, 184 Wis. 2d 645, 516 N.W.2d 730 (1994). There is also agreement among the parties that § 227.57, Stats., governing the scope of review of agency decisions, applies to this appeal. Finally, all parties point to the discussion in Wisconsin's Environmental Decade, Inc. v. PSC, 98 Wis. 2d 682, 689-97, 298 N.W.2d 205, 207-11 (Ct. App. 1980) (WED IV), as controlling authority on the issue of the proper standard of review to be applied in this case.

There, agreement ceases, however. WEPCO claims the trial court applied the wrong standard of review. It argues that the adequacy of the EIS is a factual matter, and therefore, the PSC's finding must be sustained if there is any "substantial evidence" to support it. See § 227.57(6), STATS. 5 The appellants maintain that WED IV

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tetra Tech EC, Inc. v. Wisconsin Department of Revenue
2017 WI App 4 (Court of Appeals of Wisconsin, 2016)
J & E Investments LLC v. Division of Hearings & Appeals
2013 WI App 90 (Court of Appeals of Wisconsin, 2013)
Wisconsin Electric Power Co. v. United States
90 Fed. Cl. 714 (Federal Claims, 2009)
Xerox Corp. v. Wisconsin Department of Revenue
2009 WI App 113 (Court of Appeals of Wisconsin, 2009)
Clean Wisconsin, Inc. v. Public Service Commission
2005 WI 93 (Wisconsin Supreme Court, 2005)
Clean Wisconsin, Inc. v. Public Service Commission of Wisconsin
2005 WI 93 (Wisconsin Supreme Court, 2005)
WISCONSIN DEP'T OF REVENUE v. A. Gagliano Co., Inc.
2005 WI App 170 (Court of Appeals of Wisconsin, 2005)
Wisconsin Bell, Inc. v. Public Service Commission
2004 WI App 8 (Court of Appeals of Wisconsin, 2003)
League of Wisconsin Municipalities v. Wisconsin Department of Commerce
2002 WI App 137 (Court of Appeals of Wisconsin, 2002)
Heritage Credit Union v. Office of Credit Unions
2001 WI App 213 (Court of Appeals of Wisconsin, 2001)
Department of Revenue v. Johnson Welding & Manufacturing Co.
2000 WI App 179 (Court of Appeals of Wisconsin, 2000)
State Ex Rel. Bliss v. Wisconsin Retirement Board
576 N.W.2d 76 (Court of Appeals of Wisconsin, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
565 N.W.2d 554, 211 Wis. 2d 537, 1997 Wisc. App. LEXIS 461, Counsel Stack Legal Research, https://law.counselstack.com/opinion/citizens-utility-board-v-public-service-commission-wisctapp-1997.