Wisconsin Bridge & Iron Co. v. United States

97 Ct. Cl. 165, 1942 U.S. Ct. Cl. LEXIS 55, 1942 WL 4469
CourtUnited States Court of Claims
DecidedOctober 5, 1942
DocketNo. 44322
StatusPublished
Cited by3 cases

This text of 97 Ct. Cl. 165 (Wisconsin Bridge & Iron Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wisconsin Bridge & Iron Co. v. United States, 97 Ct. Cl. 165, 1942 U.S. Ct. Cl. LEXIS 55, 1942 WL 4469 (cc 1942).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

The plaintiff sues the defendant for $61,280.99. The amount of $8,800 thereof is for liquidated damages deducted by the defendant for 88 days’ delay in completing the contract hereafter described. The balance of $52,480.99 is the cost of doing alleged extra work and damages due to the delay said to have been incident to the doing of this alleged extra work.

The main controveráy is over whether or not the plaintiff was required to do work not called for by the contract.

[177]*177This the plaintiff claims was the building of certain cofferdams to á height above low water greater than it had originally planned to build them.

The contract required the plaintiff, among other things, to strengthen both main piers for the St. Georges Bridge and the north pier of the Summit Bridge. Contract drawing No. 4 set forth the work to be done in strengthening the main piers for the St. Georges Bridge, and contract drawing No. 5 showed the work to be done in strengthening the main pier at the Summit Bridge. As a part of these drawings there was indicated by dotted lines temporary cofferdams inclosing the work to be done. No details, dimensions nor'design were given for these cofferdams, but plaintiff says that since the drawings were drawn to scale, it was possible to ascertain their height above mean low water by scaling them. By doing so, it ascertained the height at the St. Georges piers to be 6 feet 2 inches, and the height at the Summit pier to be 3 feet 3 inches.

When the plaintiff submitted working drawings for these cofferdams, as it was required to do by section 6 (c) of the specifications, it showed a cofferdam for the north pier at the St. Georges Bridge which extended 4 feet above mean low water mark, and one which extended 6 feet 2 inches above mean low water for the south pier at the St. Georges Bridge, and one which extended 5 feet 3 inches above mean low water at the Summit Bridge.

The contracting officer sent these plans to his consulting engineer for comment. The consulting engineer advised the contracting officer that in the last three years there had been six tides a year in the Canal which exceeded 8 feet in height, and one or two a year which had been over 9 feet; therefore, he advised that the cofferdams should be built high enough to protect against a tide of 8]/2 -feet. This increased height he said would require the strengthening of the wales and struts in the cofferdams. Upon receipt of this letter the contracting officer wrote the plaintiff requesting it to revise its drawings by increasing the height of the cofferdams to 10 feet above sea level. In response thereto the plaintiff submitted revised drawings for the three cofferdams increasing the height of all of them to 9% feet above [178]*178sea level. This increased the height of the cofferdams at both piers of the St. Georges Bridge to 8 feet 10 inches above mean low water, and at the Summit Bridge to 8 feet above mean low water.

The plaintiff says that this request for increased height of the cofferdams was extra work, for which it should be compensated. In support of its position it relies upon two things: (1) the provisions of article 7 of the specifications, which provides: “The mean range of tide in the canal is 5.2 feet at the Delaware River end and 2.3 feet at Chesapeake City”; and (2) the height of the cofferdams as' indicated on the contract drawings.

Plaintiff’s original position seems to have been that the quoted provision of the specifications was a misrepresentation of actual conditions, but this clearly is not true. The testimony sIioavs without controversy that the mean range of-tide was exactly that stated in the specifications. This was not a representation as to the maximum tide to be expected, but only as to the mean range of tide. The use of the words “mean range” carries a necessary implication that sometimes tides ranged above the mean range, because the mean range is the range midway between the low range and the high range, or the average range determined by adding together all the ranges and dividing by the number added together. This, of course, indicates that sometimes the tide ranged above the “mean” or the average range, and sometimes lower. What is meant by “mean range” is clearly explained in the pamphlet of the Uñited States Coast and Geodetic Survey, “Instructions for Tide Observations.” At page 2 this publication says:

The “range of tide” is the difference in height between a high water and a preceding or following low water.
The “mean range” is the average difference in the heights of high and low water at a given place.
The range of the tide at any given place varies from day to day. Variations in the range may at times be caused by varying meteorological conditions, but the principal variations - are brought about by astronomic causes — variations in the relative positions of moon, sun, and earth. At the times of new and full moon the sun and moon are in line relative to the earth, and their [179]*179tidal forces are then in concert, causing tbe tides to rise bigber and fall lower than usual, so that tbe range at this time is greater than the average. These tides are known as “spring tides” and the range the “spring range.”

This provision of the specifications clearly was not a representation as to the maximum tide that might be expected.

The plaintiff further says that the defendant knew what was tbe maximum height to be expected, and that it was its duty-to furnish plaintiff this information. In the first place, as pointed out above, the representation made in the specifications as to the tides put plaintiff on notice that it-might expect higher tides than the mean high tide. This imposed upon plaintiff the duty to make inquiry as to the height of the tide that might be expected, if it thought this information was necessary.

It is not true, as plaintiff says, that the defendant warranted that its specifications and drawings -would give plaintiff all the information that was necessary for it to have in order to bid.

The cases cited by plaintiff do not so hold. Hollerbach v. United States, 233 U. S. 165, and Christie v. United States, 237 U. S. 234, hold merely that the contractor should be relieved if misled by erroneous statements in the specifications. There were no erroneous statements in these specifications.

In United States v. Spearin, 248 U. S. 132, the contractor had been directed to build a certain sewer at a certain place and according to certain specifications. He built it as specified, but it proved inadequate to carry off the water and the site of the work was flooded. His contract was cancelled because he insisted the defendant should bear the cost of remedying the defect. The court held he was entitled to recover damages therefor. This was plainly correct because the damage resulted from an inadequate structure built according to specifications prepared by the defendant.

Steel Products Eng. Co. v. United States, 71 C. Cls. 457, goes no further than the Spearin case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Len Company and Associates v. The United States
385 F.2d 438 (Court of Claims, 1967)
Alamo Construction Co. v. United States
86 F. Supp. 845 (Court of Claims, 1949)
Globe Indemnity Co. v. United States
102 Ct. Cl. 21 (Court of Claims, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
97 Ct. Cl. 165, 1942 U.S. Ct. Cl. LEXIS 55, 1942 WL 4469, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wisconsin-bridge-iron-co-v-united-states-cc-1942.