Wilmington Housing Authority v. Pan Builders, Inc.

665 F. Supp. 351, 1987 U.S. Dist. LEXIS 6545
CourtDistrict Court, D. Delaware
DecidedJuly 10, 1987
DocketCiv. A. 86-112-JLL
StatusPublished
Cited by25 cases

This text of 665 F. Supp. 351 (Wilmington Housing Authority v. Pan Builders, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilmington Housing Authority v. Pan Builders, Inc., 665 F. Supp. 351, 1987 U.S. Dist. LEXIS 6545 (D. Del. 1987).

Opinion

MEMORANDUM OPINION

LATCHUM, Senior District Judge.

Plaintiff Wilmington Housing Authority (“WHA”) instituted this diversity action against defendant Pan Builders, Inc. (“Pan”), and Pan’s surety defendant Pennsylvania National Mutual Casualty Company (“PNMC”) to recover $72,000 in liquidated damages for Pan’s failure to timely perform two heating installation contracts for WHA. (Docket Item [“D.I.”] 1.) At issue in this Memorandum Opinion is Pan’s and PNMC’s motion for summary judgment requesting that this Court find the stipulated damages provision in Pan’s contracts with WHA to be an unenforceable penalty and thus limit WHA’s recovery to the actual damages, if any, WHA sustained due to Pan’s delay in performance. (D.I. 52.) For the reasons stated below, the -Court will deny Pan’s and PNMC’s motion.

FACTUAL BACKGROUND

In early July of 1984, WHA placed an advertisement in area newspapers to solicit bids from contractors for the installation of gas firéd furnaces and hot water heaters in 638 occupied family rental units. (D.I. 53A at A-23 to A-24.) WHA divided the work into eight projécts and solicited bids on each project separately. (Id.) Bidding opened on all projects on July 31, 1984. (Id.)

Pan was the low bidder on two of the projects and was consequently awarded the contracts for those projects. (D.I. 55B at A-112 to A-115, A-116 to A-119.) Contract 066-1-4A-16 (“066”) was for the installation of gas fired furnaces and hot water heaters in 74 WHA units at a contract price of $334,000. (D.I. 53A at A-2.) Contract 068-1-5A-16 (“068”) was for the same work in 52 units at a contract price of $265,000. (Id. at A-12.) 1

*353 After some initial delay, the reasons for which the parties dispute, a pre-construction meeting was held between WHA and Pan on September 26, 1984. The parties executed contracts 066 and 068 at this meeting and WHA issued Pan notices to proceed on both contracts. (D.I. 53A at A-2, A-4, A-12, A-14.) The notices to proceed required that both contracts be substantially complete by October 13,1984. (Id. at A-4, A-14.) The completion date on contract 066 was subsequently extended to November 20, 1984, by agreement of both parties. (D.I. 53 at 8; 55 at 3.) The completion date on contract 068 was never extended.

The parties disagree as to the exact date of substantial completion. Pan contends that both contracts were substantially complete no later than November 20, 1984. (D.I. 53 at 8.) WHA insists that neither contract was substantially complete until December 7, 1984, the date the heaters passed a required city inspection. (D.I. 55 at 3.)

THE CONTRACT

Contracts 066 and 068 both contained a provision requiring Pan to pay $1,000 a day in stipulated damages for each day the work remained unfinished after the completion date. (D.I. 53A at A-40.) The clause read in full:

1.3 Liquidated Damages
As actual damages for any delay in completion are impossible of determination, the contractor and his sureties shall be liable for and shall pay to Wilmington Housing Authority the sum of $1000.00 as fixed, agreed and liquidated damages for each calendar day of delay until the work is completed and accepted.

(D.I. 53A at A-40.)

WHA routinely includes such clauses, ranging in amount from $100 to $1,000 a day, in its construction contracts. WHA's Director of Technical Assistance, Mary Anne Russ (“Russ”), had the responsibility for setting the stipulated amounts in contracts 066 and 068. (D.I. 45 at 19.) Russ claims the $1,000 a day figure was a forecast of the potential damages WHA could have faced if the projects were not completed on time. (Id. at 20.) Foremost among those damages was the possibility that WHA would be exposed to personal injury and property damage liability if one or more of the old furnaces malfunctioned and injured WHA tenants or their property. (Id.) Secondarily, Russ considered the possibility of rent loss should the units be unoccupied for an extended period of time. m

ANALYSIS

Pan and PNMC have moved for summary judgment on their position that the stipulated damages provision contained in contracts 066 and 068 is an unenforceable penalty. (D.I. 52.) Pan and PNMC must overcome a formidable burden if they are to prevail on their motion. A party moving for summary judgment bears the burden of convincing the Court that no genuine issue of material fact exists with regard to the motion and that he is entitled to judgment as a matter of law. Fed.R.Civ.P. 56(c) (1986). Further, a court deciding a summary judgment motion must view all facts, and any reasonable inference from those facts, in the light most favorable to the party opposing summary judgment. Adickes v. Kress Co., 398 U.S. 144, 157, 90 S.Ct. 1598, 1608, 26 L.Ed.2d 142 (1970). As will become apparent, the Court believes that there is an unresolved genuine issue of fact with regard to Pan’s and PNMC’s motion, and summary judgment is thus inappropriate.

It is generally accepted that parties to a contract may agree on a fixed sum to be paid as liquidated damages to compensate the non-breaching party in the event of breach. Wise v. United States, 249 U.S. 361, 365, 39 S.Ct. 303, 304, 63 L.Ed. 647 (1919); Davy v. Crawford, 147 F.2d 574, 575 (D.C.Cir.1945); Lee Builders Inc. v. Wells, 34 Del.Ch. 307, 103 A.2d 918, 919 (1954); In Re Ross & Sons, Inc., 10 Del.Ch. 434, 95 A. 311, 315 (1915). But if the purpose of such a provision is not to compensate the non-breaching party and is instead to punish the breaching party or en *354 sure his performance, the provision is void as a penalty. Davy, 147 F.2d at 575; A. Corbin, Corbin on Contracts, § 1057 (1964); 22 Am.Jr.2d Damages § 213 (1965).

In order to determine if a provision is a valid liquidated damages provision or an unenforceable penalty, Delaware courts apply the following test. Where (1) the damages that would result from a breach are uncertain or incapable of accurate calculation by any accepted rule of law, and (2) the amount fixed is a reasonable forecast of such damages, the provision is one for liquidated damages and will be enforced like any other. Conversely, if the provision fails to meet one of these criteria, the damages stemming from a breach being easily ascertainable or the amount fixed excessive, the provision is void as a penalty. Gilbane Building Co. v. Nemours Foundation, 666 F.Supp. 649, 652 (D.Del.1985) (Stapleton, C.J.); Lee Builders Inc., 34 Del.Ch. 307, 103 A.2d at 919; In re Boss, 10 Del.Ch. 434, 95 A. at 315.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Avesair, Inc. v. Inphonic, Inc.
2007 NCBC 32 (North Carolina Business Court, 2007)
Delaware Bay Surgical Services, P.A. v. Swier
900 A.2d 646 (Supreme Court of Delaware, 2006)
In Re Hayes Lemmerz International, Inc.
340 B.R. 461 (D. Delaware, 2006)
Brazen v. Bell Atlantic Corp.
695 A.2d 43 (Supreme Court of Delaware, 1997)
Kysor Industrial Corp. v. Margaux, Inc.
674 A.2d 889 (Superior Court of Delaware, 1996)
Donegal Mutual Insurance v. Tri-Plex Security Alarm Systems
622 A.2d 1086 (Superior Court of Delaware, 1992)
David B. Lilly Co., Inc. v. Fisher
800 F. Supp. 1203 (D. Delaware, 1992)
United States v. One Parcel of Property
786 F. Supp. 400 (D. Delaware, 1992)
Diltz v. United States
771 F. Supp. 95 (D. Delaware, 1991)
United States v. Delaware
755 F. Supp. 119 (D. Delaware, 1991)
Terra Nova Ins. Co., Inc. v. Nanticoke Pines, Ltd.
743 F. Supp. 293 (D. Delaware, 1990)
Sears, Roebuck & Co. v. Sears Plc
744 F. Supp. 1297 (D. Delaware, 1990)
Games v. Cavazos
737 F. Supp. 1368 (D. Delaware, 1990)
Ward v. United States
738 F. Supp. 129 (D. Delaware, 1990)
Cruz v. Chesapeake Shipping Inc.
738 F. Supp. 809 (D. Delaware, 1990)
Fitzpatrick v. United States
726 F. Supp. 975 (D. Delaware, 1989)
Bristol-Myers Co. v. Erbamont Inc.
723 F. Supp. 1038 (D. Delaware, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
665 F. Supp. 351, 1987 U.S. Dist. LEXIS 6545, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilmington-housing-authority-v-pan-builders-inc-ded-1987.