In re the Receivership of D. Ross & Son, Inc.

95 A. 311, 10 Del. Ch. 434, 1915 Del. Ch. LEXIS 22
Court of Chancery of Delaware·Decided May 4, 1915·Published·Cited by 11 cases

Opinion

The Chancellor.

The exceptions to the claim of the McCall Company relate to these facts: The Ross Company agreed to buy from the McCall Company a certain quantity of patterns during a term of five years, which would expire on December 12, 1918. It was provided that if either should [436] “intentionally” break any of the terms and refuse or fail after two weeks’ notice in writing promptly to perform, then the other may be released from all further performance and may recover as estimated and agreed damages a sum of money equal to one-third of the agreed charge of all goods agreed to be delivered during the time the contract would have to run after such notice be given. It was also provided that the goods would be paid for within a fixed period of time after shipment, and if not so paid for, then after two weeks’ notice in writing the seller had a right to consider such failure to pay as a breach of the contract.

The Ross Company failed to pay on August 4, 1914, for the goods shipped theretofore, and on August 7, 1914, the McCall Company sent a letter to the Ross Company, received August 8, 1914, stating that owing to the failure of the Ross Company to perform their contract and pay for the goods furnished, the McCall Company gave two weeks’ notice to the buyer to pay for the goods, and that in the event of a failure to do so it would claim release of further performance and would seek payment of the liquidated damages according to the method fixed in the contract. The time for which this notice ran expired on August 22d, according to the solicitor for the McCall Company, and the receiver respectively, and the receiver of the Ross Company was appointed on August 21, 1914.

The claim for damages as filed is for $1,267.27. This is ascertained by calculating the number of issues of patterns, etc., which the Ross Company agreed to take between the time of the expiration of the two weeks’ notice, August 22, 1914, and the expiration of the contract, December 12, 1918, and by dividing that number -by three, as provided in the contract. The exceptions taken by the receiver are that by the appointment of the receiver before the two weeks’ notice had expired, the control, management and possession of all the property of the Ross Company was taken from the company and vested in the receiver, and the company was prevented from paying the debt then due, there being no intentional breach of the contract. It is also a question whether the basis [437] of calculating the damages is permissible, as being a penalty instead of liquidated damages. The exceptions were argued upon the statement of the claim and the exceptions, there being no disputes as to questions of fact.

From the above it appears, then, that the question raised by the exception is whether the seller can claim liquidated damages where the only breach claimed is a failure to pay for an installment of patterns delivered, and where before the two weeks allowed by the contract for notice to the buyer a receiver was appointed for the company on the ground of its insolvency.

First, then, as to the right of the McCall Company to damages. According to the contract the buyer having failed to pay for an installment of goods, and the seller having by giving notice elected to treat such failure as a breach of the contract, the buyer still had two weeks of grace after such default within which to pay and avoid the consequences of the breach, viz., a rescission of the contract and a recovery of damages for the breach. But within that period of two weeks, and before it expired, the receiver was appointed. By the appointment of the receiver and the taking possession of all the assets of the buyer, its corporate activity was paralyzed, and it was, therefore, prevented by the court from performing its obligation to pay for the goods within the period of grace.

In the case of Du Pont v. Standard Arms Co., 9 Del. Ch. 315, 81 Atl. 1089, in considering the claim of James J. Hartley, it was decided in this court that a contract for personal services to be rendered to a corporation was terminated by the appointment of a receiver for the corporation, and that the servant could not recover damages, though under the employment he was entitled to three months’ notice of the termination of the employment. In the opinion filed this was based clearly and expressly on the similarity between the consequences resulting from the death of an individual employer and the appointment of a receiver of an insolvent corporate employer. When a receiver elects to terminate executory contracts of personal service the situation is the same as that produced by the death of an individual employer. It was there said that no [438] opinion was expressed concerning the right of creditors with claims other than for personal services.

In deciding the validity of the claim of the McCall Company the question is squarely raised, whether the appointment of a receiver for an insolvent corporation prevents the enforcement of a right to damages for the breach of an executory contract made by the insolvent company. In this case it is certain that there is not sufficient assets to pay in full the debts of the insolvent company, and there is therefore no possibility that any benefit will result to the shareholders of the company.

Free access — add to your briefcase to read the full text and ask questions with AI

In re the Receivership of D. Ross & Son, Inc., 95 A. 311, 10 Del. Ch. 434, 1915 Del. Ch. LEXIS 22 (Del. Ct. App. 1915).

95 A. 311 (In re the Receivership of D. Ross & Son, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lyons Insurance Agency, Inc. v. Kelly Wark
Court of Chancery of Delaware, 2020
Donegal Mutual Insurance v. Tri-Plex Security Alarm Systems
622 A.2d 1086 (Superior Court of Delaware, 1992)
Wilmington Housing Authority v. Pan Builders, Inc.
665 F. Supp. 351 (D. Delaware, 1987)
Gilbane Building Co. v. Nemours Foundation
666 F. Supp. 649 (D. Delaware, 1985)
Lee Builders v. Wells
103 A.2d 918 (Court of Chancery of Delaware, 1954)
Lee Builders, Inc. v. Wells
103 A.2d 918 (Court of Chancery of Delaware, 1954)
In re the Receivership of International Re-Insurance Corp.
48 A.2d 529 (Court of Chancery of Delaware, 1946)
Pusey & Jones Co. v. Hanssen
261 U.S. 491 (Supreme Court, 1923)
Napier v. Peoples Stores Co.
120 A. 295 (Supreme Court of Connecticut, 1923)
Pusey & Jones Co. v. Hanssen
279 F. 488 (Third Circuit, 1922)