Willie Mae Toole, Deceased, and Clyde Toole, Administrator of Estate, and Clyde Toole, in His Own Right v. United States

588 F.2d 403, 1978 U.S. App. LEXIS 7314
CourtCourt of Appeals for the Third Circuit
DecidedDecember 4, 1978
Docket78-1168
StatusPublished
Cited by33 cases

This text of 588 F.2d 403 (Willie Mae Toole, Deceased, and Clyde Toole, Administrator of Estate, and Clyde Toole, in His Own Right v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Willie Mae Toole, Deceased, and Clyde Toole, Administrator of Estate, and Clyde Toole, in His Own Right v. United States, 588 F.2d 403, 1978 U.S. App. LEXIS 7314 (3d Cir. 1978).

Opinion

OPINION OF THE COURT

ROSENN, Circuit Judge.

This appeal presents a difficult question concerning the liability of the United States under the Federal Tort Claims Act, 28 U.S.C. §§ 1346(b), 2671-80 (1976), for the death of an employee of an independent contractor engaged in the manufacture of antitank explosives for the United States Army.

I.

Willie Mae Toole worked at the Philadelphia munitions plant of Action Manufacturing Company (“Action” or “Company”). She was engaged in the manufacture of the “fuze rocket,” an antitank explosive that Action made for the United States Army. Specifically, her job was to “stake” together a primer and detonator, both of which contained explosive material. Sitting behind a plexiglass shield at a plywood table, Mrs. Toole would reach around the shield, hold a detonator in her left hand and a primer in her right, insert the primer into the detonator, and put that assembly onto a staking device 1 in the center of the table. She would then withdraw her hands behind the shield, press levers with each hand in order to operate the staking device, and finally remove the assembled product. Mrs. Toole might have had as many as 50 detonators and 350 primers at her table while she was performing this operation.

The staking device pressed together components that contained highly explosive material. As the contract between Action and the United States noted, a “fire and explosion hazard prevails throughout the entire [manufacturing] process . . . .”

On August 5, 1974, Mrs. Toole was staking a primer and a detonator. The parts that she was assembling, seven other detonators, and all of the primers at her table exploded, throwing her three or four feet from the bench. She died from the injuries. In his own right and as administrator of his wife’s estate, Toole sued the United States in the United States District Court for the Eastern District of Pennsylvania for damages under the Federal Tort Claims Act, supra, asserting claims under the Pennsylvania Survival Statute, 20 Pa.C.S.A. § 3371 (1975), and the Pennsylvania Wrongful Death Statute, 12 P.S.A. §§ 1601-4 (1953). After a bifurcated nonjury trial on the issue of liability alone, the district court, in a thoughtful opinion, rendered judgment for the United States. Toole appealed. We are compelled to reverse.

An important background to the accident and suit is found in the contract between Action and the United States and in the efforts taken to enforce compliance with the contractual provisions. The contract under which Action manufactured the fuze rocket incorporated by reference Armed Services Procurement Regulation 7-104.79, *405 32 C.P.R. § 7-104.79 (1975). According to that regulation, Action had to comply with the Department of Defense Contractors Safety Manual for Ammunition, Explosives and Related Dangerous Materials (DOD Manual 4145.26M). If a contracting officer in the Department of Defense discovered a violation of the manual and notified the contractor, the contractor was obligated to take immediate corrective action. Should the contractor fail to correct the violation, the contracting officer could postpone production until the contractor complied, or the contracting officer could even terminate the contract. Armed Services Procurement Regulation 7-104.79(b), 32 C.F.R. § 7-104.-79(b) (1975). Despite the requirement that a contractor abide by the manual, the regulation provided:

Neither the requirements of this clause nor any act or failure to act by the Government shall affect or relieve the Contractor of his responsibility for the safety of his personnel ... or impose or add to any liability of the Government for such safety.

Id. at § 7 — 104.79(d).

Among the requirements in the manual was a provision concerning safety shields. The provision required the contractor to install shields protecting employees from hazardous operations, and these shields had to be designed “in such a manner as to protect against the effects of not less than a 25 percent overload above the expected maximum charge [from an accidental explosion].” DOD Manual 4145.26M, § 603(f)(1) & (2). Under another section, rules were to be established governing the quantity of explosives to be kept in any one place, such as a work station. Id. at § 603(b)(1) & (2).

In order to discover whether the contractor was complying with the contract and obeying the manual, the Department of Defense, through an arm of the Defense Supply Agency, established an inspection system. On one occasion before the contract was awarded and at quarterly intervals after the award was made, inspectors from the Department of Defense surveyed Action’s plant to ascertain whether the Company was in compliance. The inspectors reported to E. J. Slade, an Administrative Contracting Officer. When Slade learned that a contractor was not following the recommendation of an inspector, Slade would write to the contractor, requesting compliance within a specified time. If the contractor still failed to comply, Slade would investigate the reasons for the failure. Slade’s last resort was to bring the violation to the attention of a Procurement Contracting Officer, who had the sole power to postpone work or terminate the contract.

On July 16, 1973, an inspector visited Action’s plant. The inspector recommended that Action install a more effective shield around the staking operation. 2 Noting that Action had permitted as many as 50 detonators and 350 primers at the staking operation station at one time, the inspector also recommended reducing these numbers. In a subsequent letter to Action, Slade repeated the inspector’s recommendations. Although Action’s Contracts Manager, Joseph C. Brenner, promised compliance, the Company never fully corrected the hazardous conditions. An inspection in October again resulted in a letter from Slade and a promise by Brenner. After a third inspection, Slade wrote that “the proposed design [of the shields] should be tested with at least 25 percent overload before its use is permitted in operations.” In reply, Brenner wrote that Action had tested a shield in an explosion of 25 detonators, and the shield had held fast. Since the manual required, as Slade had indicated, a shield able to withstand a 25 percent overload, rather than an explosion of 25 detonators, Action had not conducted the test with nearly enough explosives. A proper test would have involved the explosion of 500 units (each primer or detonator being a unit) — 25 percent more than the 400 units that Action *406 was permitting at the staking operation. It is undisputed that Slade did not notify Action of its error.

At approximately the same time that Brenner wrote to Slade, the plant manager told an inspector, Leo Everett, about the test. Although Everett knew that Action had seriously misinterpreted the manual, the district court found as a fact that Everett did not alert the plant manager to the misinterpretation. Instead, he simply transmitted to Slade what the plant manager hád told him. Everett also conducted the next inspection of the plant, and his report did not mention the faulty test.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BALESTRIERI v. United States
E.D. Pennsylvania, 2021
Millbrook v. United States
8 F. Supp. 3d 601 (M.D. Pennsylvania, 2014)
Carcaise v. Cemex, Inc.
200 F. App'x 116 (Third Circuit, 2006)
Drummond v. Delaware Transit Corp.
365 F. Supp. 2d 581 (D. Delaware, 2005)
Sebroski v. United States
111 F. Supp. 2d 681 (D. Maryland, 1999)
Monk v. Virgin Islands Water & Power Authority
53 F.3d 1381 (Third Circuit, 1994)
Ferguson v. United States
793 F. Supp. 107 (E.D. Pennsylvania, 1992)
Markovich v. Bell Helicopter Textron, Inc.
805 F. Supp. 1231 (E.D. Pennsylvania, 1992)
Tarantino v. P.H. Glatfelter Co.
2 Pa. D. & C.4th 198 (York County Court of Common Pleas, 1989)
Carl McMichael Administrator of the Estate of Emma McMichael Deceased v. United States of America, Insurance Company of North America (Intervenor Below). Mrs. Lamar Bartlett Winfred Lowe, Administrator of the Estate of Thelma Lowe Mrs. Edna Rogers Mrs. Flora Weaver and Mrs. Georgia Ray v. United States of America, Insurance Company of North America (Intervenor Below). Leonard Madison, Administrator of the Estate of Lula Mae Madison, Deceased v. United States of America, Insurance Company of North America (Intervenor Below). Gertie B. Mitchell, Administratrix in Succession of the Estate of Eliza Walker, Deceased v. United States of America, Insurance Company of North America (Intervenor Below). Billy Dwayne Moody, Administrator of the Estate of Geraldine Moody, Deceased v. United States of America, Insurance Company of North America (Intervenor Below). Willie D. Kelly, Administrator of the Estate of Shirley J. Kelly, Deceased v. United States of America, Insurance Company of North America (Intervenor Below). Billy Harrison, Administrator of the Estate of Elsie Marie Harrison, Deceased v. United States of America, James Stancile, Administrator of the Estate of Lula Mae Madison, Deceased, Gertie B. Mitchell, Administratrix in Succession of the Estate of Eliza Walker, Deceased, Willia H. Moody, Administrator of the Estate of Geraldine Moody, Deceased, Willie D. Kelly, Administrator of the Estate of Shirley J. Kelly, Deceased v. United States of America, Highland Resources, Inc.
856 F.2d 1026 (Eighth Circuit, 1988)
McMichael v. United States
856 F.2d 1026 (Eighth Circuit, 1988)
Rocci v. United States
688 F. Supp. 971 (D. Delaware, 1988)
Dellinger v. United States
676 F. Supp. 567 (D. Delaware, 1987)
Hess v. United States
666 F. Supp. 666 (D. Delaware, 1987)
Cole v. United States
651 F. Supp. 221 (N.D. Florida, 1986)
White Ex Rel. White v. United States, Department of Interior
656 F. Supp. 25 (M.D. Pennsylvania, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
588 F.2d 403, 1978 U.S. App. LEXIS 7314, Counsel Stack Legal Research, https://law.counselstack.com/opinion/willie-mae-toole-deceased-and-clyde-toole-administrator-of-estate-and-ca3-1978.