This text of 856 F.2d 1026 (McMichael v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McMichael v. United States, 856 F.2d 1026 (8th Cir. 1988).

Opinion

JOHN R. GIBSON, Circuit Judge.

The United States Department of Defense contracted with Celesco Industries, Inc., an independent contractor, to produce explosive photo-flash cartridges. On March 8, 1976, an explosion occurred at the Celesco plant in East Camden, Arkansas, killing seven employees, seriously injuring five, and causing minor injuries to numerous others. Consolidated cases were filed against the United States under the Federal Tort Claims Act (FTCA), 28 U.S.C.A. §§ 1346, 2671-2680 (1982) and Highland Resources, Inc. under state law, the owner and lessor of the building where the explosion occurred. The government appeals from the district court’s1 award of damages to the injured or killed employees, arguing that the court erred in ruling that the claims were not barred by the discretionary function exception to the FTCA and in holding that the government was negligent in failing to enforce safety standards at the plant. The employees cross-appeal, contending that the district court erred in ruling that Highland Resources was not liable under Arkansas products or strict liability statutes, or common law principles of negligence. For the reasons set forth below, we affirm.

This case is before us for the third time. The factual background is outlined in our first opinion, Madison v. United States, 679 F.2d 736, 737-38 (8th Cir.1982), and the procedural and appellate history is set forth in our second opinion, McMichael v. United States, 751 F.2d 303, 304-05 (8th Cir.1985).2 After a bench trial in January [1029]*10291986 the district court made factual findings, which we recite below.'

On June 20, 1975, the United States awarded Celesco a contract to produce highly explosive photo-flash cartridges. Before submitting the bid, the government required Celesco to secure a manufacturing facility. Celesco leased a former naval ammunition plant in East Camden, Arkansas from Highland Resources, a commercial lessor. Celesco, an experienced munitions manufacturer, had leased other buildings for similar purposes and had special knowledge of the construction requirements for buildings to be used in the production of munitions. Highland, on the other hand, did not possess such special knowledge.

Before awarding the contract to Celesco, the Defense Department required the Safety Manager of the Defense Contract Administrative Services Region (DSCAR) to review Celeseo’s safety procedures, processes, facility and personnel to determine whether Celesco could comply with the Department of Defense safety requirements. The survey concluded that Celesco and the facility complied with the department guidelines. It developed at trial, however, that the Safety Manager did not conduct an on-site evaluation of the plant at the time of the survey.

The contract between Celesco and the government required Celesco to promulgate safety provisions and comply with safety standards established by the Department of Defense Contractor’s Safety Manual for Ammunition, Explosives and Related Dangerous Materials (DOD Manual) and the provisions of the Armed Services Procurement Regulations. See 32 C.F.R. § 7.104-79 (1984). These requirements and standards were incorporated into the contract. The contract delegated primary responsibility for safety to Celesco, and Cel-esco hired a full-time safety staff, headed by a safety engineer. Pursuant to the contract terms, the government provided Celesco with three on-site quality assurance representatives, or inspectors. One inspector was placed in Building M-35, the building where the explosion occurred, on a full-time basis. Although the primary responsibility of the inspector was to oversee Celesco’s compliance with the quality requirements of the contract, safety review was also an integral part of his assigned tasks. The inspectors’ regular procedures included a fifty-one step procedures review checklist for safety compliance. The Armed Services Procurement Regulations and the Celesco contract gave the inspectors the authority to require on-the-spot corrective action, and the contracting officer was authorized to cease production by withdrawing government inspectors until the safety violations were corrected.3

[1030]*1030The district court found a number of conditions at the Celesco plant did not comply with the safety requirements of the contract. For example, the lightning protection system was inadequate and there was . no humidity control in Bay 4 of Building M-35, where the explosion occurred. Water was present in an area where detonation was likely to occur. (Moisture, in the form of water or humidity, is an initiating force for the photo-flash). Despite a sign directing that the steel blast doors to Bay 4 remain shut at all times, the doors were constantly left open. The open doors allowed the blast to spread down a hallway, where all but one of the killed or injured employees were at the time of the explosion. In addition, although there was conflicting testimony concerning the precise amount of the photo-flash in Bay 4, by any account the amount exceeded the limit approved by the government.4 Shortly before the explosion, the Building M-35 government inspector informed Celesco’s line supervisor that Bay 4 was overloaded. There was also testimony that defective loaded components, or “rejects,” were stored in Bay 4, contrary to the safety requirements of the contract. Finally, the Department of Defense manual required evacuation of personnel in the event of an electrical storm, and the district court found that although on the morning of March 8, 1976, there was rain, thunder and lightning in the East Camden area, no evacuation of the plant was ordered. An explosion occurred in Building M-35, killing and injuring numerous employees.

The district court found that the government was negligent in failing to enforce the safety standards incorporated in its contract with Celesco. Specifically, the court ruled that the government inspectors were negligent in failing to order an evacuation until the storm passed and that this was the proximate cause of the employees’ injuries. The court also concluded that the lessor of the Celesco Plant, Highland Resources, Inc. was not liable on any of the theories advanced by the employees and dismissed the counts against them.

I.

The government first argues that the action is barred by the discretionary function exception to the FTCA, 28 U.S.C. 2680(a) (1982), and that the district court erred in refusing to consider whether the exception applied. For purposes of the government’s motion for summary judgment, the parties entered into a stipulation of fact, which was before, and substantially relied upon by, this court in our earlier decisions. See McMichael, 751 F.2d at 305; Madison, 679 F.2d at 738 n. 3. The essence of the stipulation was that the contract imposed numerous mandatory safety standards on Celesco, but that the government, despite its “three onsite assurance inspectors,” failed to enforce Celeseo’s compliance with those standards and thereby caused plaintiffs’ injuries.5 The govern[1031]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tookes v. United States
811 F. Supp. 2d 322 (District of Columbia, 2011)
Davis v. United States
244 F. Supp. 2d 878 (N.D. Illinois, 2002)
Foderberg v. United States
157 F. Supp. 2d 1077 (S.D. Iowa, 2001)
Berry v. LAND AND LAKE TOURS, INC.
169 F. Supp. 2d 973 (W.D. Arkansas, 2001)
Fleming v. United States
69 F. Supp. 2d 837 (W.D. Virginia, 1999)
Appley Brothers v. United States
164 F.3d 1164 (Eighth Circuit, 1999)
Irving v. United States
First Circuit, 1998
Lowry v. United States
958 F. Supp. 704 (D. Massachusetts, 1997)
Stokes v. U.S. Postal Service
937 F. Supp. 11 (District of Columbia, 1996)
Appley Bros. v. United States
924 F. Supp. 944 (D. South Dakota, 1996)
Irving v. USA
D. New Hampshire, 1996
Estate of Bernaldes v. United States
877 F. Supp. 301 (W.D. Virginia, 1995)
Vincent William Michels v. United States
31 F.3d 686 (Eighth Circuit, 1994)
C.R.S. ex rel. D.B.S. v. United States
11 F.3d 791 (Eighth Circuit, 1993)
Kirchmann v. United States
8 F.3d 1273 (Eighth Circuit, 1993)
FGS Constructors, Inc. v. Carlow
823 F. Supp. 1508 (D. South Dakota, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
856 F.2d 1026, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcmichael-v-united-states-ca8-1988.