William B. Newton v. Duke Energy Florida, LLC

895 F.3d 1270
CourtCourt of Appeals for the Eleventh Circuit
DecidedJuly 11, 2018
Docket17-10080
StatusPublished
Cited by131 cases

This text of 895 F.3d 1270 (William B. Newton v. Duke Energy Florida, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
William B. Newton v. Duke Energy Florida, LLC, 895 F.3d 1270 (11th Cir. 2018).

Opinion

TJOFLAT, Circuit Judge:

In 2006, the Florida Legislature enacted the Florida Renewable Energy Technologies and Energy Efficiency Act 1 (the "Act"). The Act authorized the Florida Public Service Commission ("PSC") to create a plan to incentivize energy utilities to invest in nuclear power plant construction. Fla. Stat. § 366.93 (2). Acting on this authority, the PSC promulgated a regulation creating the Nuclear Cost Recovery System ("NCRS"). 2 If a utility chooses to participate in the NCRS and receives PSC approval of its plant construction project, it may preemptively charge its customers *1273 through an electricity rate increase for "costs incurred in the siting, design, licensing, and construction" of the project through its completion. Id. Under the NCRS, the utility retains the funds generated by the rate increase even if the project is never completed.

This is a putative class action. The plaintiffs' class representatives, William Newton and Noreen Allison ("Plaintiffs"), claim that two provisions of the Act which authorize the NCRS, Florida Statutes §§ 366.93 and 403.519(4), are invalid under the Dormant Commerce Clause ("DCC"), which precludes a state from "regulat[ing] Commerce ... among the several States," U.S. Const. art. I, § 8, cl. 3, and "directly limits the power of the States to discriminate against interstate commerce." New Energy Co. of Ind. v. Limbach , 486 U.S. 269 , 273, 108 S.Ct. 1803 , 1807, 100 L.Ed.2d 302 (1988). Plaintiffs also claim that the two provisions of the Act are preempted by the Atomic Energy Act of 1954, 3 42 U.S.C. § 2011 et seq. , and the Energy Policy Act of 2005, Pub. L. No. 109-58, 119 Stat. 594 . 4

Plaintiffs did not bring these claims against the State of Florida, the PSC (which is charged with implementing and administering the Act), or its members. Instead, they seek the Act's invalidation solely by suing two electric utilities, Duke Energy Florida and Florida Power & Light ("Utilities"), who have been collecting rate increases from them and their class members for nuclear plant construction that has been discontinued.

Utilities separately moved the District Court to dismiss Plaintiffs' claims pursuant to Federal Rule of Civil Procedure 12(b)(6) on numerous grounds. As to the DCC claim, Utilities argued that if a cause of action lies under the DCC, it belongs to the States that may have been injured due to Florida's regulation of interstate commerce and not to Plaintiffs, who are Florida utility customers. Utilities also argued that they are private parties, not state actors, and, as such, could not have violated the DCC. As to the preemption claims, Utilities argued that they failed for numerous reasons, including that preemption is a defense , not a claim for relief. 5 Utilities *1274 also argued that the preemption claims failed on the merits.

The District Court dismissed Plaintiffs' DCC claim for lack of "prudential standing" because Plaintiffs were not in the "zone of interests" protected by the Clause. 6 See Harris v. Evans , 20 F.3d 1118 , 1121 (11th Cir. 1994). It dismissed Plaintiffs' preemption claims based on the Atomic Energy Act and the Energy Policy Act on the ground that neither act created a cause of action, express or implied. 7 The Court dismissed Plaintiffs' claims without granting leave to amend.

Plaintiffs moved the District Court for reconsideration pursuant to Federal Rule of Civil Procedure 60(b). The motion focused on the Court's dismissal of their claims without leave to amend. Citing Federal Rule of Civil Procedure 15(a)(2), which states that "[t]he court should freely give leave [to amend] when justice so requires," Plaintiffs argued that they could cure the deficiencies in their complaint if given leave to join the State of Florida as a defendant and to prosecute their claims against Utilities under 42 U.S.C. § 1983 on the ground that, in increasing their rates under the NCRS, Utilities acted under color of state law.

The District Court denied the Rule 60(b) motion. Its reading of the motion was that Plaintiffs were seeking to bolster their claims against Utilities by joining the State as a defendant. This would be futile. "Simply joining the State as a party," the Court explained, "would not suddenly empower Plaintiffs to bring constitutional claims against private entities, such as [Utilities]." Dist. Ct. Ord. Denying Mot. for Reconsideration at 4. The Court did not expressly respond to Plaintiffs' request to bring their DCC claim against Utilities under § 1983, but it implicitly rejected the request in stating that Utilities were not acting under color of state law in participating in the NCRS.

Plaintiffs appeal the District Court's judgment, arguing that the allegations of their complaint were sufficient to make out their DCC claim and their preemption claim under the Atomic Energy Act. 8

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
895 F.3d 1270, Counsel Stack Legal Research, https://law.counselstack.com/opinion/william-b-newton-v-duke-energy-florida-llc-ca11-2018.