Whittington v. Westport Hotel Operating Co.

33 S.W.2d 963, 326 Mo. 1117, 1930 Mo. LEXIS 761
CourtSupreme Court of Missouri
DecidedDecember 20, 1930
StatusPublished
Cited by8 cases

This text of 33 S.W.2d 963 (Whittington v. Westport Hotel Operating Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whittington v. Westport Hotel Operating Co., 33 S.W.2d 963, 326 Mo. 1117, 1930 Mo. LEXIS 761 (Mo. 1930).

Opinions

* NOTE: Opinion filed October 13, 1930; motion for rehearing filed; motion overruled December 20, 1930. This is an action for damages for personal injuries alleged to have been suffered by plaintiff on August 12, 1925, while working as a carpenter's helper in the construction of the President Hotel in Kansas City. The jury returned a verdict for $20,000 against both defendants, and defendants appealed from the judgment entered thereon.

Hereinafter we speak of the Westport Hotel Operating Company as Westport Company and the George H. Siedhoff Construction Company as Siedhoff Company. Both plaintiff and defendants introduced evidence.

The evidence in behalf of plaintiff warrants the finding that plaintiff, then aged twenty-three years, on August 12, 1925, about three o'clock in the afternoon, while working as a carpenter's helper on the President Hotel, was injured as the result of a board, laid across an opening from beam to beam, tilting and causing him to fall from the ninth floor, a height of ten or twelve feet, to the concrete comprising the eighth floor of the building. The hotel as planned was twelve stories in height. It was being constructed of structural steel incased in concrete and with concrete floors. The vertical pillars throughout the structure and on each floor were spaced about fourteen feet apart in each direction. Plaintiff was working on the ninth floor with and as the helper of carpenter Gatlin. The concrete comprising the eighth floor had been completed, as had the ninth floor, except a strip or open space extending the length of the building from north to south, fourteen feet in width, the distance between the second and third row of pillars or columns from the west side of the building, there being completed the concrete on the east of the opening and also an area of concrete fourteen feet wide on the west side of the opening. The *Page 1122 concrete floors rested on steel beams. In order to bridge this opening, the erector of the building placed a plank, eight inches wide, eighteen feet in length and two inches thick, running diagonally across the opening. Plaintiff was walking on this plank over the opening when he fell to the eighth floor.

On the day in question, Gatlin, on the ninth floor, was constructing wooden forms on the east side of the opening, to inclose the steel and into which to pour concrete. Plaintiff was working under Gatlin's orders as a helper, and at the time in question he was supplying Gatlin with lumber for the forms. Plaintiff had crossed from the east to the west and returned before attempting to walk the board at the time of injury. The ends of the board rested at each end on the completed concrete of the ninth floor. The center of the board hung two inches immediately above an I-beam connecting the pillars. The board was not fastened at either end, nor were railings provided. When walking over the board, it sprang down and rested on I-beam. Plaintiff, on going and returning across the board empty-handed, noticed that it was springy and wobbly, and told Gatlin, his boss, that he did not think it was very safe. Gatlin ordered him to carry a wooden trestle or sawhorse, weighing forty to fifty pounds, over the board, telling him to hurry up, that he was needing the material, saying, "The board is all right; go ahead." Plaintiff did not pay particular attention to the board or make an inspection. The purpose in taking the sawhorse from one side of the opening to the other was to break or saw the material for the forms into lesser parts, as the lumber in its condition was too heavy or cumbersome to traverse the board safely with it. As plaintiff was in the act of carrying the sawhorse over the opening, walking the board, the board tilted when he was about three steps or six feet on it, and he fell, striking the concrete floor below with his left foot and suffering injuries. On crossing over and back prior to his fall, he noticed the board spring down to the beam and did not consider it very safe, but he had no difficulty or trouble in crossing on it and believed he could use it safely by being careful. Plaintiff said, "I did not think the board was very safe, but I thought if I was extremely careful I could get across there." He testified that it was light and he could see the situation before him, and that in crossing when he fell, he was extremely careful, more careful than ordinarily, because of the narrow board. Upon being asked the universal custom and practice in regard to boards of that width in a place like that, plaintiff answered, "The usual practice on construction jobs is to build a wide, thick platform with a railing across it, so there is no danger of a man getting overbalanced and falling." Plaintiff examined the board subsequent to his fall, and observed that it was cupped, *Page 1123 but he failed to observe it on crossing over and back before he fell. He did not notice the board tilt on first crossing over, or any decided tilty effect, but he noticed the springy effect. Plaintiff's deposition was taken. He admitted he said then: "Mr. Gatlin, that plank is pretty shaky. I almost fell off there a while ago. I said it was loose." On the trial plaintiff testified: "I would not say I came very near falling. I told him (Gatlin) something like that, maybe." He said he told them that, "so that he would realize the condition of the board." Plaintiff said the board was shaky and insecure. "It seemed insecure. I did not think it was very safe."

After he fell, plaintiff attempted to work. Finding that he was in pain, he went to the office, reported the matter to Sefton, the bookkeeper, and was taken by Sefton in a taxicab to the office of Dr. Lawrence T. Jones for treatment.

Defendants' evidence tends to show that the board was ten or twelve inches in width. Defendants' witnesses Gatlin and Sefton testified that plaintiff told them that his fall was caused by the sawhorse in some manner striking the pillar as he started to cross the plank, causing him to lose his balance. Gatlin said plaintiff made no complaint about the board or its safety. Gatlin said that plaintiff was his helper, that he was subject to his orders, and obeyed his instructions. Aegerter, the superintendent, testified that Gatlin was plaintiff's boss. Gatlin said that he instructed plaintiff to carry the sawhorse over the board across the opening, and that plaintiff was obeying instructions in so carrying it. On the trial Gatlin testified that he did not give it (the safety of the board) a thought, but admitted that the board was not fastened at either end, and that it was ten inches in width, although he denied he thought it was unsafe. His deposition was previously taken and shows that he (Gatlin) had crossed over on the board several times and that it was loose and tilty, and that if the lumber, in its then condition, was carried across, there was a chance of getting overbalanced. Gatlin stated in his deposition that plaintiff might have said to him, just after the fall, that the board tilted.

Defendants' witness Vandiver testified on cross-examination, without objection, that it was customary in that kind of building work to have platforms constructed of two or three boards, twelve inches in width, to provide space to prevent an employee from losing his balance and falling. Other facts, pertinent to the issues discussed, will be adverted to in the opinion.

I. Before proceeding to a discussion of defendants' contention that plaintiff failed to make a submissible case, we think it apropos first to dispose of questions relating to the admissibility of evidence, *Page 1124 as the making of a submissible case, to some extent, depends upon the force of that evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Elms v. Kansas City Public Service Co.
335 S.W.2d 26 (Supreme Court of Missouri, 1960)
Russell v. Johnson
160 S.W.2d 701 (Supreme Court of Missouri, 1941)
Stoutimore v. Atchison, Topeka & Santa Fe Railway Co.
92 S.W.2d 658 (Supreme Court of Missouri, 1936)
Rouchene v. Gamble Construction Co.
89 S.W.2d 58 (Supreme Court of Missouri, 1935)
Goodwin v. Missouri Pacific Railroad
72 S.W.2d 988 (Supreme Court of Missouri, 1934)
Huselton v. Commerce Trust Co.
64 S.W.2d 757 (Missouri Court of Appeals, 1933)
Gray v. Doe Run Lead Co.
53 S.W.2d 877 (Supreme Court of Missouri, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
33 S.W.2d 963, 326 Mo. 1117, 1930 Mo. LEXIS 761, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whittington-v-westport-hotel-operating-co-mo-1930.