Whitbeck v. United States

77 Ct. Cl. 309, 1933 U.S. Ct. Cl. LEXIS 301, 1933 U.S. Tax Cas. (CCH) 9380, 1933 WL 1805
CourtUnited States Court of Claims
DecidedApril 10, 1933
DocketNo. F-32
StatusPublished
Cited by9 cases

This text of 77 Ct. Cl. 309 (Whitbeck v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whitbeck v. United States, 77 Ct. Cl. 309, 1933 U.S. Ct. Cl. LEXIS 301, 1933 U.S. Tax Cas. (CCH) 9380, 1933 WL 1805 (cc 1933).

Opinion

LittletoN, Judge,

delivered the opinion of the court:

The broad question in this case is whether the plaintiff is entitled to recover any amount under either or both of the contracts, no. 555 with the Army, and no. 57340 with the Navy, for the construction of airplanes. If recovery can be had the questions arise as to the items on which he is entitled to recover under each of the contracts.

Plaintiff contends with reference to Army contract no. 555 that the defendant breached the same by failing and refusing to make all the biweekly payments of $2,000 each absolutely provided to be made under art. Y (2) thereof; that it also breached the contract by capriciously changing the basis of the progress reports after such basis had been approved and payments made thereunder over a long period and in failing to make accrued payments for direct labor expended by plaintiff contrary to the spirit of the contract; and, finally, that the defendant breached this contract by canceling it on May 12, 1924, on the ground that the plaintiff had breached the same by failing to complete the work called for thereby within the time specified when, in fact, the defendant itself was then, and had been for some time, in default.

On the other hand the defendant contends that the plaintiff breached this contract on March 15, 1923, and that such breach continued until the contract was canceled by the defendant on May 12, 1924, because of continued default of the plaintiff; that section 3648 of the Revised Statutes U.S.C.A. tit. 31, sec. 529, prohibited the defendant from paying any amount in excess of the percentage of the'progress of work under the contract, which, it is contended, represented the value of services performed; that because of the failure of plaintiff to complete the contract and deliver the completed articles called for therein, the defendant received nothing for the $62,951.82 paid and judgment should, therefore, be rendered in its favor on its counterclaim for this and two other amounts of $910.30 for testing and $545 for certain equipment for the airplanes furnished by the defendant, as mentioned in the findings, totaling $64,407.12, from which should be deducted $13,688.03, being the amount [333]*333of the voucher issued in favor of plaintiff on Navy contract no. 57340, hereinafter mentioned, leaving a balance of $50,719.09. Although credit is not given plaintiff in- the counterclaim for the amount of $5,000 offered by the defendant in connection with one of the changes ordered, defendant’s counsel states that probably the plaintiff should receive credit for this item, and if the counterclaim should be sustained there would be a balance due the defendant of $45,719.09.

We cannot sustain the contention of the defendant that the plaintiff breached this contract on March 15, 1923, the date on which the finance officer wrote him that the sum of $51,727.61 already paid was 35 percent of $148,000, the contract price, exclusive of the profit of $22,000, and that the progress which the plaintiff had made on the contract up to that time was but 27 percent. In the first place the progress which the plaintiff had made on the work to March 15, 1923, under the approved method of computation was in excess of 35 percent, and the finance officer was not correct in finding that only 27 percent progress had been made. Further than this, the failure to keep the percentage of completion of the contract at all times in excess of the payments provided for therein was not necessarily a breach of the contract and would give the defendant no right to cancel the same on that ground alone unless some provision of the contract so provided. At most, the inability of the plaintiff to make progress equal to the percentage of the total payments called for on any date within the period allowed for delivery of the articles would only give the defendant the right to postpone the installment payments called for in the contract until the value of the work performed equaled the percentage of payments made computed on the basis of the entire contract price rather than upon only a portion thereof. Although the contract provided in art. VIII that the Government might terminate it at any time by written notice from the contracting officer, in which event the plaintiff would be entitled to compensation as provided in paragraph 2 of said article, as set forth in finding 5, the defendant did not terminate the contract under this provision, but canceled [334]*334it on the ground that the plaintiff had breached the same, and demanding at the same time the return of the amount paid thereunder. It is our opinion from the facts with reference to this contract that the defendant breached the same in refusing to make payment to the plaintiff of the amounts called for by the contract after the payments to May 1923. This contract was wholly experimental, and it was recognized and stated therein that the consideration named was not, in and of itself, commensurate with the work called for. At the time the last payment for direct labor was made, the entire contract was about 42 percent completed. The progress of the work was necessarily delayed from June 16 to about October 1, 1923, while consideration was being given by defendant’s officials to the question whether a greater number or more powerful engines should be installed in the airplane. This delay was not caused by plaintiff. During this period the plaintiff’s expenses for labor and overhead were going on and as soon as this matter was disposed of plaintiff proceeded with the work and made further progress toward completion. When he resumed work about October 1, 1923, he found that the defendant’s officials in the meantime had changed the percentages theretofore approved and used in computing the percent of progress on the work and had prescribed different factors to be used for this purpose which very materially reduced the percentage of progress toward completion of work called for by the contract.

The facts establish that under the terms of this contract and by reason of its nature, the first method of determining progress of the work was correct and that the second method prescribed by the defendant was erroneous. When the plaintiff on February 4, 1924, was compelled to discontinue operations because of lack of funds, this contract was more than 60 percent complete. The evidence justifies the conclusion that if the defendant had paid to the plaintiff the installment payments called for by this contract, as were justified by the correct percentage of completion, and had also paid to the plaintiff the amount due under Navy contract no. 57340 for the first airplane, plaintiff would not [335]*335have been compelled to close his plant and would have been able to complete the articles called for by both contracts.

In view of the foregoing we are of opinion that the defendant breached contract no. 555 at least as early as June 16, 1923, at which time the percentage of progress toward completion of the contract was about 42 percent and this breach continued until February 4, 1924, when plaintiff ceased work. Overstreet v. United States, 55 C.Cls. 154. Plaintiff was justified in discontinuing work under the contract. He is therefore entitled to retain the amounts paid and to recover, in addition thereto, as damages, his actual expenditures for direct labor in excess of the amount paid, the cost of materials purchased for and used on the contract, which materials and the uncompleted airplanes became the property of the defendant, and also the profit provided in the contract. Overstreet v. United States, supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A. Ernest Fitzgerald v. Elmer B. Staats
578 F.2d 435 (D.C. Circuit, 1978)
Fitzgerald v. Staats
429 F. Supp. 933 (District of Columbia, 1977)
Northern Helex Co. v. United States
455 F.2d 546 (Court of Claims, 1972)
Barnes v. United States
92 Ct. Cl. 32 (Court of Claims, 1940)
Aluminum Co. of America v. United States
87 Ct. Cl. 96 (Court of Claims, 1938)
Edwards v. United States
84 Ct. Cl. 615 (Court of Claims, 1937)
R. J. Reynolds Tobacco Co. v. United States
13 F. Supp. 425 (Court of Claims, 1936)
American Potash Co. v. United States
8 F. Supp. 717 (Court of Claims, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
77 Ct. Cl. 309, 1933 U.S. Ct. Cl. LEXIS 301, 1933 U.S. Tax Cas. (CCH) 9380, 1933 WL 1805, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whitbeck-v-united-states-cc-1933.