Whatcom Builders Supply Co. v. H. D. Fowler, Inc.

463 P.2d 232, 1 Wash. App. 665, 1969 Wash. App. LEXIS 387
CourtCourt of Appeals of Washington
DecidedDecember 31, 1969
Docket18-40058-1
StatusPublished
Cited by12 cases

This text of 463 P.2d 232 (Whatcom Builders Supply Co. v. H. D. Fowler, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whatcom Builders Supply Co. v. H. D. Fowler, Inc., 463 P.2d 232, 1 Wash. App. 665, 1969 Wash. App. LEXIS 387 (Wash. Ct. App. 1969).

Opinion

Horowitz, A. C. J.

Plaintiff, H. D. Fowler, Inc. (Fowler) sued defendant, Whatcom Builders Supply Company (Whatcom) to recover the purchase price of a pump and to recover for certain work performed on the purrip. That action was consolidated for trial with an interpleader action commenced by Whatcom against Fowler and the City of Blaine (City). In that action Whatcom paid into court the sum of $2,932 less a claimed offset of $343.76 as due from Fowler. The court entered judgment in favor of Fowler against Whatcom for the purchase price less the offset and awarded the interpleaded funds to Fowler to be applied on its judgment against Whatcom. 1 The City appeals, claiming it is entitled to the interpleaded funds.

The court found in substance that in September, 1963, Whatcom and the City entered into a contract for the installation of a sewage treatment plant (Whatcom-City contract) which provided for the installation of certain pumps (to be manufactured); that Whatcom then contracted with Fowler (Fowler-Whatcom contract, evidenced by exhibits 1, 2, 3) for the purchase from it of pump No. 1 for a price of $2,932; that no contract was entered into between the City and Fowler; that in June 1964, Fowler supplied What- *667 com with pump No. 1, the pump complying with all the specifications of Whatcom’s order; that immediately after installation the pump was tested; that the City found the pump unsatisfactory as not complying with certain performance specifications set out in the Whatcom-City contract; that in July 1964 the bubbler control mechanism of the pump, which was not supplied by Fowler, failed to function, with resulting performance deficiencies, none of which was the responsibility of Fowler; that the repairs following prevented the pump from thereafter attaining its maximum performance; that in September, 1964, the City “made a formal completion and acceptance” of the What-com-City contract “and signified this completion and acceptance to the federal government so that federal matching funds could be paid on the project”; that thereafter the City paid Whitcom in full for the Whatcom-City contract; that Whatcom did not pay Fowler the agreed purchase price for the pump; that a fourth test of the pump on April 13, 1965, indicated substantial performance in accordance with the Fowler-Whatcom contract and the engineer for the City recommended acceptance; that subsequent to the installation of the pump in 1964 the City retained and utilized the pump for over two years; that at no time up to and including the time of trial did either the City or Whatcom tender a return of the pump to Fowler. Additional reference to the findings and evidence will be hereinafter made. From these findings the court concluded that Fowler was entitled to the judgment from which this appeal is taken.

The City has assigned error to certain findings and conclusions which basically raise the question whether the City rather than Fowler is entitled to the interpleaded funds. The City contends that it is entitled to these funds on two grounds: (1) by virtue of the provisions of the Uniform Sales Act (RCW 63.04) in effect at the time of the 1963 contracts (now RCW Title 62A, Article 2), and (2) by virtue of the resulting trust doctrine. We are of the opinion that neither of the grounds is applicable under the express and necessarily implied findings of the court, negative or *668 affirmative, consistent with the findings entered. 53 Am. Jur. 2d Trial § 1143 (1945). See Graham v. Roderick, 32 Wn.2d 427, 202 P.2d 253, 6 A.L.R.2d 1237 (1949); Sainsbury v. Wapato Fruit & Cold Storage Co., 132 Wash. 455, 232 P. 331 (1925).

The Uniform Sales Act is applicable to the FowlerWhatcom contract as a contract to sell future goods; i.e., pumps to be manufactured. RCW 63.04.060. Accordingly, when the pump after manufacture “complied with all the specifications of the order” and was appropriated by Fowler to the Fowler-Whatcom contract and then delivered to and accepted by Whatcom, title to the pump passed to Whatcom. RCW 63.04.060, 63.04.420, 63.04.490, 63.04.190, 63.04.200, Rule 4(1). The City, however, purports to make no claim under the Fowler-Whatcom contract either as assignee, subrogee, third party beneficiary or otherwise; and the court found that no contract existed between the City and Fowler—a finding supported by substantial evidence. The City’s rights, therefore, must arise under the What-com-City contract, a contract for work, labor and materials, to which the Uniform Sales Act is not applicable but to which general principles of contract law are applicable. Crystal Recreation, Inc. v. Seattle Ass’n of Credit Men, 34 Wn.2d 553, 209 P.2d 358 (1949).

Even if the Uniform Sales Act were applicable to the Whatcom-City contract, the evidence does not support the City’s claim that it is entitled to the interpleaded funds. Basically, the City contends that compliance with the performance specifications set forth in the Whatcom-City contract is a condition precedent to the passage of title of the pump to the city (RCW 63.04.120); that compliance never having been had, title to pump No. 1 never passed to the City and that, accordingly, it is entitled to reject the pump and without tendering it back, recover the purchase price paid. This remedy does not involve invoking the remedy of rescission (RCW 63.04.700(1) (c)). If, however, the performance specifications have not been assumed by Fowler *669 (American Pipe & Constr. Co. v. Harbor Constr. Co., 51 Wn.2d 258, 317 P.2d 521 (1957)), or if compliance with the performance specifications is a matter of warranty rather than a matter of condition, then if the City wishes to recover the purchase price of the pump it must rescind the sale in conformity with the conditions set forth in RCW 63.04.700, 1(c), (3), (4). 2 There is substantial evidence that compliance with performance specifications by Fowler was never a condition as contended for by the City. The evidence showed that the City’s project engineer by letter dated August 26, 1964, addressed to the City Council of the City of Blaine stated: “We have inspected the project and find that the work has been completed in accordance with the plans and specifications as amended. . . . We are very satisfied with their work [Whatcom’s] and feel that they should be commended for doing a fine job.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tacoma Athletic Club, Inc. v. Indoor Comfort Systems, Inc.
902 P.2d 175 (Court of Appeals of Washington, 1995)
BHP Petroleum Co., Inc. v. Okie
836 P.2d 873 (Wyoming Supreme Court, 1992)
Arango Construction Co. v. Success Roofing, Inc.
730 P.2d 720 (Court of Appeals of Washington, 1986)
Lincor Contractors, Ltd. v. Hyskell
692 P.2d 903 (Court of Appeals of Washington, 1984)
McCollough v. Cashmere School District No. 222
551 P.2d 1046 (Court of Appeals of Washington, 1976)
Grandy v. Luther
530 P.2d 679 (Court of Appeals of Washington, 1975)
State v. Swain
520 P.2d 950 (Court of Appeals of Washington, 1974)
Collins v. Boeing Co.
483 P.2d 1282 (Court of Appeals of Washington, 1971)
Davey v. Brownson
478 P.2d 258 (Court of Appeals of Washington, 1970)
Radosevich v. County Commissioners
476 P.2d 705 (Court of Appeals of Washington, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
463 P.2d 232, 1 Wash. App. 665, 1969 Wash. App. LEXIS 387, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whatcom-builders-supply-co-v-h-d-fowler-inc-washctapp-1969.