American Pipe & Construction Co. v. Harbor Construction Co.

317 P.2d 521, 51 Wash. 2d 258, 1957 Wash. LEXIS 517
CourtWashington Supreme Court
DecidedNovember 7, 1957
Docket34188
StatusPublished
Cited by24 cases

This text of 317 P.2d 521 (American Pipe & Construction Co. v. Harbor Construction Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Pipe & Construction Co. v. Harbor Construction Co., 317 P.2d 521, 51 Wash. 2d 258, 1957 Wash. LEXIS 517 (Wash. 1957).

Opinion

Rosellini, J.

On January 17, 1955, the city of Anacortes advertised for bids for the purchase of pipe and other supplies for the city’s proposed new water supply system. According to the specifications, delivery was to begin on March 7th and to be completed by May 7th, and bidders were also advised that delivery was of utmost importance because, under a contract between the city and Shell Oil Company, the city was obliged to deliver water to the latter’s new refinery, which was scheduled to open on June 1, 1955. American Pipe and Construction Company, hereafter referred to as the pipe supplier, was the successful bidder and was awarded the contract on or about the first of February. The contract provided that the pipe was to be delivered in sequence to trench side, so that it could be installed in sequence, and provided a penalty to be paid to the city for delays in delivery, due to the fault of the supplier, beyond the time fixed for delivery on the bid sheet or the time which might subsequently be agreed upon.

On February 15th, bids for the installation of the pipe were invited. Harbor Construction Company, hereafter *260 referred to as the installation contractor, was the successful bidder and was awarded the contract on or about the first of March, 1955. The pipe supplier’s guaranteed delivery date appeared on the specifications for this bid, and the installation contractor was required to complete the installation job in ninety-five days. Among the provisions of this contract was the following:

“Article 47. Claims for Damages and Extensions of Time. The Contractor shall not be entitled to any claim for damages on account of hindrances or delays and he shall not be charged with liquidated damages because of any delays in the completion of the work due to unforeseeable causes beyond his control and without his fault or negligence, including, but not restricted to, acts of God, or of the public enemy, acts of the Owner, acts of another contractor in the performance of a contract with the Owner, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe’ weather or delays of Subcontractors due to such causes, provided that the Contractor shall give notice in writing of the causes of any such act, hindrance or delay within ten (10) days after its occurrence.”

This contract also contained a provision for liquidated damages for delay in completion of the work. It further provided that the installation contractor must acquaint himself with any other contracts awarded by the owner and perform his contract in the light of such contracts. It was further provided:

“Standard lengths of pipe will be delivered to the job as manufactured. The Contractor shall acquaint himself with the manufacturer’s shipping schedule and so arrange his pipe laying operations. . . .
“In no case shall the Owner be liable for any claims made by the Contractor for failure of the Owner’s manufacturer to deliver as scheduled or promised.”

Prior to submitting its bid, the installation contractor obtained and accepted a bid from the pipe supplier for certain “specials” which were not to be furnished by the city.

Although the installation was scheduled to begin on March 7th, pipe was not on hand at that time, and the installation contractor did not move his equipment onto *261 the job site until March 14th, when pipe was available. The work was completed on or about June 2, 1955. No penalties for delays were assessed. This was due to the fact that the construction of the Shell refinery had not proceeded as rapidly as had been expected, and pressure on the city and its subcontractors was relaxed.

The project was accepted by the city in December, 1955, after other installations not covered by these contracts were completed, and within thirty days thereafter the pipe supplier filed a claim with the city for $9,700.91 which it alleged the installation contractor owed on its contract with the pipe supplier. The city held a sum in excess of that amount, which was due the installation contractor, which it withheld pending settlement of the dispute between the installation contractor and the pipe supplier.

On April 30,1956, the pipe supplier filed this suit, naming the city, the installation contractor and the surety on the latter’s bond as defendants. The surety answered that the city had in its possession funds sufficient to pay the claim and asked to be dismissed from the action, and the city tendered the amount of $11,700.91, which it had withheld from the installation contractor, into the registry of the court. The installation contractor denied that any sum was due the pipe supplier, claiming that certain items had not been delivered or were defective and cross-complaining for expenses on account of delays in delivery of pipe under its contract with the city. Liability of the city for these delays was also alleged.

The trial court found that the installation contractor had been put to expense because of the pipe supplier’s failure to deliver certain items according to specifications, and that on one occasion the installation contractor had requested and had received assurance that certain pipe would be delivered at specified times; that the pipe had not been delivered as promised; and that the installation contractor was entitled to an offset for the expense which this delay involved. The remaining offsets were denied. Judgment was entered for the pipe supplier in the sum of $7,574.93 *262 with interest, attorney’s fees and costs. Recovery against the city on the cross-complaint was also denied.

The questions on appeal are whether the installation: contractor is entitled to recover from the city for delays incurred by the former by reason of the failure of the latter to deliver the pipe which it agreed to furnish on or-before the original “guaranteed delivery date,” and whether the pipe supplier is liable for these delays.

The answer to the first of these questions is that the city, in its contract, disclaimed all liability for delays occasioned by its own act or acts of other contractors in the performance of their contracts with the city. Where a contract expressly precludes the recovery of damages for delays caused by such defaults, that provision will be given effect. Ericksen v. Edmonds School Dist., 13 Wn. (2d) 398, 125 P. (2d) 275, and cases cited therein. See, also, Annotations, 10 A. L. R. (2d) 801.

In regard to the second question, the trial court did not find it necessary to decide whether the pipe supplier’s contract with the city was enforcible by the installation contractor but based its decision upon findings that the pipe was delivered at a steady rate, as contemplated by the contract, and that any loss sustained by the installation contractor was due to its failure to inform itself of the pipe supplier’s shipping schedule and arrange its work accordingly.

The installation contractor points out that these findings overlook the fact that the delivery of the pipe was not completed by May 7, 1955, the guaranteed delivery date, and the further fact that it was not shown that by familiarizing itself with the pipe supplier’s delivery schedule, it could have secured delivery of all of the pipe by that date.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cedar River Water & Sewer District v. King County
315 P.3d 1065 (Washington Supreme Court, 2013)
Kim v. Moffett
156 Wash. App. 689 (Court of Appeals of Washington, 2010)
Hamlin v. Transcon Lines
697 P.2d 606 (Wyoming Supreme Court, 1985)
Lonsdale v. Chesterfield
662 P.2d 385 (Washington Supreme Court, 1983)
Simons v. Tri-State Construction Co.
655 P.2d 703 (Court of Appeals of Washington, 1982)
Burke & Thomas, Inc. v. International Organization of Masters
600 P.2d 1282 (Washington Supreme Court, 1979)
Coast Trading Co. v. Parmac, Inc.
587 P.2d 1071 (Court of Appeals of Washington, 1978)
Burke & Thomas, Inc. v. International Organization of Masters
585 P.2d 152 (Court of Appeals of Washington, 1978)
City of Seattle v. Dyad Construction, Inc.
565 P.2d 423 (Court of Appeals of Washington, 1977)
S. L. Rowland Construction Co. v. Beall Pipe
540 P.2d 912 (Court of Appeals of Washington, 1975)
Turner v. Wexler
538 P.2d 877 (Court of Appeals of Washington, 1975)
Wolfe v. Morgan
524 P.2d 927 (Court of Appeals of Washington, 1974)
Quadrant Corporation v. Spake
504 P.2d 1162 (Court of Appeals of Washington, 1973)
McDonald Construction Co. v. Murray
485 P.2d 626 (Court of Appeals of Washington, 1971)
Bellevue Square Managers v. Granberg
469 P.2d 969 (Court of Appeals of Washington, 1970)
Whatcom Builders Supply Co. v. H. D. Fowler, Inc.
463 P.2d 232 (Court of Appeals of Washington, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
317 P.2d 521, 51 Wash. 2d 258, 1957 Wash. LEXIS 517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-pipe-construction-co-v-harbor-construction-co-wash-1957.