Crystal Recreation, Inc. v. Seattle Ass'n of Credit Men

209 P.2d 358, 34 Wash. 2d 553, 1949 Wash. LEXIS 554
CourtWashington Supreme Court
DecidedAugust 17, 1949
DocketNo. 30725.
StatusPublished
Cited by24 cases

This text of 209 P.2d 358 (Crystal Recreation, Inc. v. Seattle Ass'n of Credit Men) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crystal Recreation, Inc. v. Seattle Ass'n of Credit Men, 209 P.2d 358, 34 Wash. 2d 553, 1949 Wash. LEXIS 554 (Wash. 1949).

Opinion

*555 Schwellenbach, J.

This is an appeal from a judgment in a replevin action rendered in favor of the plaintiff.

We shall refer to Crystal Recreation, Inc., as “Crystal”; to Modern Store and Restaurant Equipment Corporation, as “Modern”; and to Seattle Association of Credit Men, as “Association.”

In October, 1946, Crystal had a location in the basement of a building at 423 Pike, in Seattle. It intended to establish there a general restaurant business, cigar store, card room, and tavern. It employed an architect to prepare plans for fixtures, which had to be specially made because of the shape of the room. There was a call for bids, and on November 27, 1946, it entered into a written contract with Modern for the construction of the fixtures at an agreed price of $21,878. It agreed to make payments on or about the 5th day of each month of 85% of the value of labor and materials incorporated in the work, as estimated by the architect. Article 21 provided:

“Art. 21. The Owner’s Right to Do Work. — If the Contractor should neglect to prosecute the work properly or fail to perform any provision of this contract, the Owner, after three days’ written notice to the Contractor may, without prejudice to any other remedy he may have, make good such deficiencies and may deduct the cost thereof from the payment then or thereafter due the Contractor, provided, however, that the Architect shall approve both such action and the amount charged to the Contractor.”

Article 22 provided:

“Art. 22. Owner’s Right to Terminate Contract. If the Contractor should be adjudged a bankrupt, or if he should make a general assignment for the benefit of his creditors, or if a receiver should be appointed on account of his insolvency, . . . then the Owner, upon the certificate of the Architect that sufficient cause exists to justify such action, may, without prejudice to any other right or remedy and after giving the Contractor seven days’ written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method he may deem expedient.”

*556 Article 33 provided:

“Art. 33. Assignment. — Neither party to the Contract shall assign the Contract or sublet it as a whole without the written consent of the other, nor shall the Contractor assign any moneys due or to become due to him hereunder, without the previous written consent of the Owner.”

The work was being done at Modern’s plant at 1616 Eighth avenue, Seattle. The following payments were made on the contract:

December 18, 1946.................... $2,084.22
January 10, 1947.....................1 9,703.04
February 10, 1947..................... 5,240.25
$17,027.51

Prior to the payment of February 10th, Modern executed to Crystal a bill of sale dated February 10, 1947, in consideration of the sum of $21,233, covering the following described personal property located at 1616 Eighth avenue, Seattle: “all fixtures shown on blue prints by Waldo B. Christenson for Crystal, Inc., dated October 18, 1946, and described in specifications as work included in fixture contract.”

The certificate of the architect for the Feb. 10th payment showed:

“Amount of Contract.............. $21,878.00
Eliminate Booth Table Tops........ $645.00
Net Amount this Date.............. 21,233.00
Total Work Done This Period...... $6,165.00
Less 15% Retained................ 924.75
Amount Due This Certificate....... 5,240.25
Amount Previously Certified....... 11,787.26
Total Certified to Date............. 17,027.51
Balance ..................... $4,205.49
“Remarks: A bill of sale to Crystal, Inc. in the full amount of the contract price has been issued by the Contractor as a condition precedent to payment of the amount herein certified.”

The bill of sale was never recorded. Prior to March 12th, four lunch counters and the oval bar had been delivered to Crystal. The balance of the fixtures remained at the Mod *557 ern plant. None of the fixtures, whether delivered or not, was completed.

On March 12, 1947, Modern executed to the Association a common-law assignment for the benefit of creditors. It stated:

“Assignor does assign, transfer, and deliver unto said assignee, all that certain stock of goods, wares and merchandise, consisting principally of stock and restaurant equipment, and now located at 1616 Eighth Avenue, Seattle.”

For at least four months prior to the assignment, Modern had been insolvent. Immediately upon the giving of the assignment, John B. Morris, an employee of the Association, took possession of the property, placed a padlock on the door, and prepared to take inventory. Mr. Replogle, manager of Modern, told Morris that the fixtures involved in this action were being constructed for Crystal, and belonged to Crystal. Crystal called on the telephone and demanded the property, which was refused.

Before an inventory could be taken, this action was commenced, a bond furnished, and the fixtures removed to Crystal’s place of business. It cost Crystal approximately ten thousand dollars to complete and install the fixtures.

The trial court found that plaintiff entered into a written contract with Modern whereby the latter agreed to construct and install fixtures and equipment for a restaurant to be operated by plaintiff; that the fixtures were to be specially constructed, according to plans and specifications, and were to be designed and adapted to the particular location according to its measurements and contour; that Modern did not carry the fixtures upon any of its books of account as an asset; that it considered and regarded said fixtures as belonging to and being owned by plaintiff at the time of making the common-law assignment, and so advised the common-law assignee; that the fixtures, when replevied by plaintiff on March 14th, and when conveyed to plaintiff by bill of sale, had been appropriated to the original contract; that the Association acquired no title or interest in the fixtures by virtue of the common-law assignment; that *558 plaintiff, on the date of the assignment and on the date of the replevin, owned all of the fixtures and was entitled to the possession thereof.

The plaintiff in a replevin action must prove its title and right to possession in order to be successful in the action. The plaintiff can only succeed on the strength of its own title and right to possession, irrespective of the title or right to possession of the defendant. Colby v. Nelson, 131 Wash.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

OEG Inc v. Korum
W.D. Washington, 2025
Russell H. Bensch, et ux v. Don C. Dixon
Court of Appeals of Washington, 2013
Graham v. Notti
196 P.3d 1070 (Court of Appeals of Washington, 2008)
Tacoma Athletic Club, Inc. v. Indoor Comfort Systems, Inc.
902 P.2d 175 (Court of Appeals of Washington, 1995)
State v. Pelkey
794 P.2d 1286 (Court of Appeals of Washington, 1990)
Arango Construction Co. v. Success Roofing, Inc.
730 P.2d 720 (Court of Appeals of Washington, 1986)
Nitrin, Inc. v. Bethlehem Steel Corp.
342 N.E.2d 65 (Appellate Court of Illinois, 1976)
Whatcom Builders Supply Co. v. H. D. Fowler, Inc.
463 P.2d 232 (Court of Appeals of Washington, 1969)
Northwest Collectors, Inc. v. Enders
446 P.2d 200 (Washington Supreme Court, 1968)
Billman v. Ace Restaurant Supply Co.
423 P.2d 132 (Court of Appeals of Arizona, 1967)
Epstein v. Giannattasio
197 A.2d 342 (Connecticut Superior Court, 1963)
Epstein v. Giannattasio
25 Conn. Supp. 109 (Pennsylvania Court of Common Pleas, 1963)
Wm. H. Wise & Co. v. Rand McNally & Company
195 F. Supp. 621 (S.D. New York, 1961)
Aced v. Hobbs-Sesack Plumbing Co.
360 P.2d 897 (California Supreme Court, 1961)
Authorized Supply Co. of Arizona v. Swift & Co.
277 F.2d 710 (Ninth Circuit, 1960)
Clements v. Olsen
282 P.2d 266 (Washington Supreme Court, 1955)
Perlmutter v. Beth David Hospital
123 N.E.2d 792 (New York Court of Appeals, 1954)
Foley Corp. v. Dove
101 A.2d 841 (District of Columbia Court of Appeals, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
209 P.2d 358, 34 Wash. 2d 553, 1949 Wash. LEXIS 554, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crystal-recreation-inc-v-seattle-assn-of-credit-men-wash-1949.