Westport v. Connecticut Siting Council

47 Conn. Super. Ct. 382
CourtConnecticut Superior Court
DecidedJune 27, 2001
DocketNo. File Nos. CV00-0501129S CV00-0500547S.
StatusPublished
Cited by3 cases

This text of 47 Conn. Super. Ct. 382 (Westport v. Connecticut Siting Council) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westport v. Connecticut Siting Council, 47 Conn. Super. Ct. 382 (Colo. Ct. App. 2001).

Opinion

* Affirmed. Westport v. Connecticut Siting Council, 260 Conn. 266,796 A.2d 510 (2002). These are consolidated appeals. In Docket No. CV00-0501129S, the plaintiff, the town of Westport (town), appeals from a December 17, 1998 decision of the named defendant, the Connecticut siting council (council), approving an application for a certificate of environmental compatibility and public need for the construction and operation of a telecommunications tower facility proposed by Cellco Partnership, doing *Page 384 business as Bell Atlantic Mobile. In Docket No. CV00-0500547S, the plaintiff, Cellco Partnership (Cellco), appeals from a July 27, 1999 decision of the named defendant, the zoning board of appeals of the town of Westport (board), upholding its zoning enforcement officer's refusal to approve Cellco's zoning application to construct the tower facility. The first appeal is brought pursuant to General Statutes § 16-50q and §4-183, of the Uniform Administrative Procedure Act (UAPA). The second appeal is brought pursuant to General Statutes §§ 8-8 and 8-10. The court decides for the council on the town's appeal, Docket No. CV00-0501129S, and for Cellco on its appeal, Docket No. CV00-0500547S, for the reasons stated subsequently in this opinion.

The council, in its final decision of December 17, 1998, made findings of fact that may be summarized as follows.

1. Cellco applied to the council on June 24, 1998, pursuant to General Statutes §§ 16-50g through 16-50aa, for a certificate of environmental compatibility and public need for construction, operation and maintenance of a cellular telecommunications facility in the town. A "prime site" on 2 Sunny Lane and an alternate site near the intersection of Clinton Avenue and the Merritt Parkway were identified. The purpose of the proposed facility was to provide cellular coverage for existing coverage gaps in the area and to meet demand beyond the capacity of existing facilities.

2. Notice was given and hearings were held pursuant to General Statutes § 16-50m. The council and its staff made inspections of the proposed prime and alternative sites. During the field inspection, Cellco flew a balloon at each of the proposed sites to simulate the heights of the towers proposed at the two locations.

3. Springwich Cellular Limited Partnership (Springwich), the Southern New England Telephone cellular affiliate, Sprint Spectrum (Sprint), a personal *Page 385 communications service provider (pcs provider), Omni-point Communications, Inc., (Omnipoint), a pcs provider, and Nextel Communications of the Mid-Atlantic, Inc., doing business as Nextel Communications (Nextel), an enhanced specialized mobile radio service provider, sought to share the proposed tower, equipment building, generator and associated fuel tank at both of the proposed sites.

4. Cellco has offered to provide space on the proposed tower to the town's public safety entities.

5. Existing Cellco facilities in the towns of Westport, Fairfield and Norwalk do not provide adequate service for coverage gaps in the northern Westport area. The primary purpose of the proposed site is to provide coverage to these gaps and additional traffic handling capacity along Routes 33, 53, 57, 136 and 15.

6. Springwich also has gaps under existing coverage. Omnipoint has limited coverage in the northern portion of the town and coverage gaps in excess of five miles along Route 15.

7. Sprint experiences a coverage gap of approximately 3.5 miles along Route 15 and lesser distances on other routes.

8. Nextel experiences a coverage gap of approximately 4.5 miles along Route 15 and lesser distances on other routes.

9. Other suggested sites were investigated, but did not prove feasible. The sites were rejected for such reasons as an unwillingness of the property owner to lease land, system performance problems, less favorable channel deployment and insufficient coverage. One site suggested by the town was the department of transportation (department) commuter parking lot off of exit 41 of the Merritt Parkway. *Page 386

10. Cellco met with town officials in August, 1997, and, in June, 1998, participated in a public hearing.

11. The town does not support the placement of a telecommunications facility at either of the proposed sites. The town has stated that the proposed facilities are commercial in nature, are not appropriate in residentially zoned areas and are inconsistent with the town's plan of development.

12. The town made recommendations to the council, should it approve the prime site, to protect water resources at or near the site, including Poplar Plains Brook. It made similar environmental recommendations for the alternative site.

13. The town suggested, as an alternative to either site, expanding the current 180 Bayberry Lane facility by devoting more town land to the site.

14. The proposed prime site is a 1.63 acre parcel located at 2 Sunny Lane in Westport and is owned by Cellco. It is in a town residence AAA district for single-family homes. According to town zoning regulations, communication towers are allowed with a special permit and site plan approval on ten acre parcels.

15. The proposed prime site is a developed parcel consisting of a single-family building, an approximately twelve foot wide driveway, maintained lawn and landscaped trees and shrubs. The existing single-family building is the only structure within 160 feet of the base of the proposed tower.

16. The proposed prime site is traversed by the Poplar Plains Brook and contains inland wetlands and a 100 year flood zone located adjacent to the brook. The proposed prime site tower compound would be located no closer than approximately 75, 110 and 55 feet from the areas designated as a watercourse, inland wetland and 100 year flood zone, respectively. *Page 387

17. Cellco proposed to construct a 160 foot monopole tower, enclosed by an eight foot tall security fence with a gate, on an approximately forty foot compound at the proposed prime site. There would be a variety of antennas placed on the tower by the shared users.

18. Vehicular access would be from Sunny Lane along the existing driveway. Utility service would extend from the existing service along Sunny Lane underground for a distance of approximately 170 feet to the building.

19. All the electrical equipment and a 200 kilowatt emergency generator, sized to accommodate five tower users, would be installed within the existing single-family structure on the proposed site.

20. The proposed prime site is surrounded by existing residential development and the Merritt Parkway. There are approximately twenty-two residences within 1000 feet of the proposed site.

21. The proposed site is located approximately fifty feet south of the Merritt Parkway right of way, near the commuter parking area located adjacent to interchange 41 off the Merritt Parkway.

22. The proposed prime site would require the removal of three trees of less than four inches in diameter, but five trees with diameters of twenty-four inches or greater would be spared.

23. The cost of construction of the prime site was placed at $1,404,000.

24.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brouillard v. Connecticut Siting Council
39 A.3d 1241 (Connecticut Superior Court, 2010)
Sprint Spectrum v. Town of Madison, No. Cv 00-0445411 S (X20) (Aug. 1, 2002)
2002 Conn. Super. Ct. 9900 (Connecticut Superior Court, 2002)
Town of Westport v. Connecticut Siting Council
796 A.2d 510 (Supreme Court of Connecticut, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
47 Conn. Super. Ct. 382, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westport-v-connecticut-siting-council-connsuperct-2001.