Weston v. McWilliams & Associates, Inc.

694 N.W.2d 558, 2005 Minn. App. LEXIS 395, 2005 WL 832066
CourtCourt of Appeals of Minnesota
DecidedApril 12, 2005
DocketA04-1251
StatusPublished
Cited by3 cases

This text of 694 N.W.2d 558 (Weston v. McWilliams & Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weston v. McWilliams & Associates, Inc., 694 N.W.2d 558, 2005 Minn. App. LEXIS 395, 2005 WL 832066 (Mich. Ct. App. 2005).

Opinion

OPINION

CRIPPEN, Judge. *

This appeal requires judicial interpretation of the statute of repose for claims premised on defective and unsafe real estate improvements. Appellant contends the ten-year statute (running from the date when construction is completed), because it limits when an action can “accrue,” permits suits within the normal two-year limitation period in the eleventh or twelfth year after construction is completed, even though its claim accrued in fact after the ten-year anniversary. Determining that a proper interpretation of the statute requires this result, we reverse the summary judgment dismissing appellant’s contribution and indemnity claims and remand the proceedings to the district court.

FACTS

In 1993, plaintiffs Weston and Schwalbe contracted with appellant Top Value Homes to build a home in Eagan. Top Value subcontracted with respondents Tappe Construction (framing), Panelcraft of Minnesota (siding), and Windsor Window Company (manufacturing windows). A certificate of occupancy was completed for the home on July 20,1993.

In 2002, an inspector of the home found significant amounts of mold and believed the cause was water intrusion. This followed the deteriorating health of plaintiffs and their children. In May 2003, two months before the tenth anniversary of completion of the home construction, plaintiffs brought an action for damages against appellant Top Value. Appellant initiated contribution and indemnity action against respondents in March and April 2004, in the eleventh year after construction was completed. The contribution and indemnity claim had not ripened before the tenth year following construction. 1 Following motions premised on the statute of repose in Minn.Stat. § 541.051, subd. 1(a) (2002), the district court granted summary judgment to respondents.

ISSUE

Did the district court correctly determine that Minn.Stat. § 541.051, subd. 1(a) (2002), bars initiation of a contribution and indemnity suit in the eleventh year after completion of construction?

ANALYSIS

When reviewing the district court’s summary judgment, we must determine *560 whether the court erred in its application of the law. Larson v. Babcock & Wilcox, 525 N.W.2d 589, 591 (Minn.App.1994) (announcing standards for review of decision on the facts and on the law).

Minn.Stat. § 541.051, subd. 1(a), limits actions and accrual of actions for injuries “arising out of the defective and unsafe condition of an improvement to real property,” and for contribution and indemnity for damages sustained on account of these injuries. Id. Subject to conditions not relevant to this case, paragraph (a) prohibits an action more than two years after the injury is discovered “or, in the case of an action for contribution or indemnity, [after] accrual of the cause of action.” Id. A subsequent clause of the paragraph states the period of repose: “[N]or, in any event shall such a cause of action accrue more than ten years after substantial completion of the construction.” Id. (emphasis added).

In the case of contribution and indemnity claims, the limitation period begins upon “accrual” of the cause of action. Id. Minn.Stat. § 541.051, subd. 1(b), 2 declares that “a cause of action accrues” under paragraph (a), in the case of an action for contribution and indemnity, upon “payment” on a claim arising out of the unsafe condition. Id. 3 An injury claim “accrues upon discovery of the injury,” the time stated in paragraph (a) for the beginning of the limitation period on these claims. Id.

We must determine the meaning of the subsequent clause of paragraph (a), stating that an action shall not “accrue” more than ten years after substantial completion of the construction.

The parties have not produced and we have not found legislative history relevant to the use of the “accrue” concept in the 1980 amendment of Minn.Stat. § 541.051. The original version of the limitations and repose provisions now found in Minn.Stat. § 541.051, subd. 1(a), was enacted in 1965, and this version was subsequently found to be unconstitutional for reasons not relevant to this case. See Pac. Indem. Co. v. Thompson-Yaeger, Inc., 260 N.W.2d 548, 555 (Minn.1977). The first version of the statute provided that no action “shall be brought” more than ten years after completion of construction. See Calder v. City of Crystal, 318 N.W.2d 838, 842-43 (Minn.1982) (reviewing history of enactment and alteration of provision). The “accrue” concept for the repose clause first appeared in Minn.Stat. § 541.051, subd. 1 (1980). Calder, 318 N.W.2d at 843.

We also are unassisted in our interpretation of this repose statute by any precedents addressing the issue in this case. We observe but find no authority in mixed signals from appellate court dicta on this statute of repose. Thus, for example, we *561 note the observation of the supreme court that the repose provision of Minn.Stat. § 541.051, subd. 1(a), “specifies a limitation period barring suit more than 10 years after substantial completion of a real property improvement;” the court had no occasion when making this observation either to note the accrual concept or to determine the time when the statute operated to stop the period for suit. Olmanson v. LeSueur County, 693 N.W.2d 876, 880, n. 2 (Minn.2005) (reviewing scope of claims subject to statute of repose); 4 cf. Concordia Coll. Corp. v. W.R. Grace & Co., 999 F.2d 326, 328 (8th Cir.1993) (when confirming lawful application of repose statute 20 years after construction, correctly paraphrasing statute as one on “accrual” of a cause and declaring that the cause “will be deemed accrued” under the statute “no later than” ten years after construction). 5

Without explanation, the district court determined that becausé the “commencement by Top Value of its claim for third-party contribution” occurred more than ten years after completion of construction, “the clock had run on the period of repose” and its claims were “extinguished.”

At' least two things' are evident upon initially examining the statute at issue in this case. First, it is a statute of repose added to the statute of limitation, declaring an ultimate repose of an injury action or a contribution or indemnity action, regardless of when the cause of action arises. See Sartori v. Harnischfeger Corp., 432 N.W.2d 448

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weston v. McWilliams & Associates, Inc.
716 N.W.2d 634 (Supreme Court of Minnesota, 2006)
Brink v. Smith Companies Construction, Inc.
703 N.W.2d 871 (Court of Appeals of Minnesota, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
694 N.W.2d 558, 2005 Minn. App. LEXIS 395, 2005 WL 832066, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weston-v-mcwilliams-associates-inc-minnctapp-2005.