Bethesda Lutheran Church v. Twin City Construction Co.

356 N.W.2d 344, 1984 Minn. App. LEXIS 3642
CourtCourt of Appeals of Minnesota
DecidedOctober 9, 1984
DocketC4-84-320, C4-84-334
StatusPublished
Cited by28 cases

This text of 356 N.W.2d 344 (Bethesda Lutheran Church v. Twin City Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bethesda Lutheran Church v. Twin City Construction Co., 356 N.W.2d 344, 1984 Minn. App. LEXIS 3642 (Mich. Ct. App. 1984).

Opinion

OPINION

LESLIE, Judge.

Plaintiff Bethesda Lutheran Church filed this action against Twin City Construction Company which in turn filed a complaint against third-party defendant Building Specialties. After trial the jury delivered a verdict finding both defendant and third-party defendant negligent and assessing damages. The trial court made additional findings of fact with its conclusions of law and order for judgment. Defendant and third-party defendant brought motions for judgment NOV or, alternatively, for a new trial which the trial court denied. The appeals of both defendant and third-party defendant are consolidated.

We affirm.

FACTS

In 1968 plaintiff Bethesda Lutheran Church (Bethesda) of Moorhead, Minnesota began planning a new church and contracted with an architectural firm, Adkins Associates, to design the church. Adkins prepared architectural plans and drawings for the church which Bethesda let for bids in 1971. In February 1971 Bethesda and defendant Twin City Construction Company (Twin City) entered a construction agreement for the church.

The roof design provided for unique peaks and slopes. Some of those features *347 had to be built up from the roof deck by layering plies of paper and felt coated with tar. Twin City constructed the roof deck and shingled those areas which did not need to be built up. It subcontracted with third-party defendant Building Specialties for construction of the built up areas. Construction on the church began in April 1971 and continued until January 1972 when representatives of Bethesda, Adkins, and the contractors inspected the completed building.

The Bethesda congregation began using the new church building in February 1972. By April 1972 members of Betheda noticed water leakage through the church ceiling. Bethesda’s pastor, Rev. Anttila, contacted both Twin City and Building Specialties about the problem. Twin City agreed to attempt to fix the roof and gave Bethesda a two-year guarantee on the roof for workmanship and materials. Building Specialties apparently informed Anttila that it would not repair the roof.

Twin City made numerous attempts to stop the leaks beginning in the spring of 1972 until 1977. Nonetheless the roof leaked chronically, causing damage to the church interior. The evidence suggested several reasons for the leaks. Anttila testified he frequently saw pools of water on the roof which did not drain off after rains. The roof architect, Roger Sjobeck testified that the water pooled because the roof deck was improperly constructed to slope where it should have been flat. This defect caused at least one drain to be higher than some areas of the roof.

Anttila testified that a Twin City employee came to the church in June 1977 to handle a complaint that the roof was leaking again. The employee went up on top of the roof and discovered that a drain was not draining even though water ponded on top of it. He took the grate off and used a long pole to force out material blocking the drain. The pastor caught the material at the other end of the drain. Anttila described it as a glob of tar covered insulation material with rock and stone piled on top of it.

Testimony also showed that blisters formed on parts of the roof. Moisture in the roof insulation below the roof surface heats up in the sun and bubbles causing blisters. When the blisters eventually crack, they can cause leaks. The blisters occur when wet insulation material is used or asphalt is improperly mopped on to the roofing materials.

Finally, plaintiff presented evidence that nails used to secure the flashing strips on the roof were hammered in too close to the roof, allowing water to soak through the roof when it had ponded on the roof. No testimony, however, showed that the nail holes actually leaked water.

In August or September of 1978, Twin City informed Bethesda it would no longer repair the roof. Bethesda decided to replace the roof in the fall of 1978. The new roof contained more layers of felt and tar than the original and more insulation. Not including the price of adding insulation, the roof cost $18,300.00. It was installed on the same deck Twin City had built. The new roof has not leaked.

Bethesda commenced this lawsuit in September 1978 against Twin City. Twin City brought its third-party action against Building Specialties for contribution or indemnity in January 1979. The jury found Building Specialties 50% negligent, Twin City 30% negligent, and Adkins Associates 20% negligent. It determined the reasonable cost of replacing the roof was $18,-000.00.

ISSUES

1. Does the evidence support the jury’s verdict that Twin City and Building Specialties were causally negligent in constructing plaintiffs roof?

2. Does the evidence support the jury’s determination that the reasonable cost of constructing a new roof was $18,000.00?

3. Did the trial court err by instructing the jury that defendant’s failure to notify plaintiff or the architect of design defects constitutes negligence if defendants knew or should have known the defects existed?

*348 4. Is Twin City estopped, by its promises to repair the roof, from asserting the statute of limitations as a defense to plaintiff's action for negligent construction of the roof?

5. Does the statute of limitations on plaintiffs negligence claim prevent Twin City from bringing a third-party action against Building Associates for contribution or indemnity?

ANALYSIS

I. Sufficiency of Evidence on Negligence

Twin City and Building Specialties claim the evidence does not support the jury’s allocation of negligence. 1 They point to substantial evidence in the record showing a defective roof design caused the leakage. They claim the roof design placed a drain higher than other parts of the roof. Their evidence includes expert testimony that design defects caused the leaks. They argue that any evidence of construction defects did not show the defects caused the leakage.

On appeal from a denial of a motion for judgment NOV, the evidence must be viewed in the light most favorable to the verdict. The verdict should stand unless manifestly and palpably contrary to the evidence. Stuempges v. Parke, Davis & Co., 297 N.W.2d 252, 256 (Minn.1980). Circumstantial evidence may alone establish negligence as long as the evidence does not equally sustain any other theory. E.H. Renner & Sons, Inc. v. Primus, 295 Minn. 240, 243, 203 N.W.2d 832, 835 (1973).

The evidence at trial showed several roof problems that allegedly caused the leaks: improper construction of the roof deck support joists, use of wet insulation or roofing materials, incorrect nailing of the flashing strips, and the plugged drain. While Bethesda did not unequivocally establish which one of these problems actually caused the leaks, Bethesda did not need to.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gfroerer v. Menard, Inc.
D. Minnesota, 2021
Robert Martin v. A�BULAE, LLC
Court of Appeals of Minnesota, 2016
Negassi H. Ghebrehiwet v. Khaled Ghneim
Court of Appeals of Minnesota, 2016
Weston v. McWilliams & Associates, Inc.
694 N.W.2d 558 (Court of Appeals of Minnesota, 2005)
Guinness Import Co. v. Mark VII Distributors, Inc.
971 F. Supp. 401 (D. Minnesota, 1997)
Church of Nativity of Our Lord v. Watpro, Inc.
474 N.W.2d 605 (Court of Appeals of Minnesota, 1991)
In re the Amended Administrative Penalty Order to Westling Manufacturing, Inc.
442 N.W.2d 328 (Court of Appeals of Minnesota, 1989)
Matter of Westling Mfg., Inc.
442 N.W.2d 328 (Court of Appeals of Minnesota, 1989)
Hydra-Mac, Inc. v. Onan Corp.
430 N.W.2d 846 (Court of Appeals of Minnesota, 1989)
Bahl v. Country Club Market, Inc.
410 N.W.2d 916 (Court of Appeals of Minnesota, 1987)
Greenbrier Village Condominium Two Ass'n v. Keller Investment, Inc.
409 N.W.2d 519 (Court of Appeals of Minnesota, 1987)
GREENBRIER VILL. CONDO. 2 v. Keller Inv.
409 N.W.2d 519 (Court of Appeals of Minnesota, 1987)
Bulau v. Hector Plumbing and Heating Co.
402 N.W.2d 528 (Supreme Court of Minnesota, 1987)
Axia, Inc. v. I. C. Harbour Construction Co.
501 N.E.2d 1339 (Appellate Court of Illinois, 1986)
Bulau v. Hector Plumbing and Heating Co.
387 N.W.2d 659 (Court of Appeals of Minnesota, 1986)
Agristor Leasing v. Kramer
640 F. Supp. 187 (D. Minnesota, 1986)
Rosenberg v. Townsend, Rosenberg & Young, Inc.
376 N.W.2d 434 (Court of Appeals of Minnesota, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
356 N.W.2d 344, 1984 Minn. App. LEXIS 3642, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bethesda-lutheran-church-v-twin-city-construction-co-minnctapp-1984.