Westlands Water District v. Firebaugh Canal

10 F.3d 667
Court of Appeals for the Ninth Circuit·Decided November 30, 1993·No. No. 93-15295·Published·Cited by 19 cases

Opinion

REAVLEY, Circuit Judge:

Westlands Water District (Westlands) and San Benito County Water District (San Benito) appeal a district court order dismissing their claims against the Department of Interior’s Bureau of Reclamation (Bureau), arising out of water allocations made by the Bureau during the 1992 California drought. While we do not find ourselves in complete agreement with all of the district court’s analysis, we affirm the judgment.

BACKGROUND

The Central Valley Project (CVP) is a massive water reclamation project authorized by various acts of Congress, and serving the needs of central California. Prior to the construction of the Friant Dam across the San Joaquin River, an early CVP project, the Bureau entered into contracts with holders of downstream water rights. The first such contract, known as the Exchange Contract, was signed in 1939. The currently effective second amended Exchange Contract was executed in 1968, by the Bureau and four Exchange contractors,1 all of whom are parties or successors in interest to the original Exchange Contract. Under the terms of the Exchange Contract, the Exchange contractors gave up their rights to San Joaquin waters in exchange for the agreement of the Bureau to provide “substitute water.” Article 5 of the Exchange Contract “anticipated that most if not all of the substitute water provided the [Exchange contractors] will be, delivered to them via the [ ] Delta-Mendota Canal.” The Delta-Mendota canal carries water from the Sacramento-San Joaquin River Delta (the Delta). Article 4 of the Exchange Contract obliged the Bureau to release water from Millerton Lake, the lake created behind Friant Dam, in the event of temporary or permanent interruptions in the delivery of substitute water to the Exchange contractors.

The CVP is divided into a number of units. The San Luis Unit was authorized by the San Luis Act of 1960, Pub.L. No. 86-488, 74 Stat. 156 (1960) (the Act). The San Luis Unit consists of the San Luis Dam and the San Luis Reservoir (the Reservoir), together with a number of smaller facilities. The Reservoir stores surplus water from the Delta, which is pumped into the Reservoir from the Delta-Mendota Canal. The Reservoir was constructed to provide irrigation water for Merced, Fresno and Kings Counties. Id. at § 1(a). The Act further contemplated additional construction projects to provide CVP water to Santa Clara, San Benito, Santa Cruz and Monterey Counties. Id. at § 6. The San Felipe Division of the CVP was later created to serve these counties. To implement the Act, the Bureau entered into contracts with water service providers, including appellants Westlands and San Benito (collectively the San Luis Contractors). The West-lands contract was executed in 1963, and the San Benito contract was executed in 1978.

On February 14, 1992, after several years of serious drought, the Bureau issued a declaration of available CVP water supplies for water year 1992. The declaration stated the Bureau’s intent to provide no CVP water to [670]*670certain agricultural contractors, including the San Luis Contractors, while the Exchange contractors were to receive 75 percent of their normal supply of water. The declaration was revised to allow for 15 and then 25 percent of normal allocations to the San Luis Contractors. The Bureau planned to divert Reservoir water to meet its contractual obligations to the Exchange contractors.

On March 20, 1992, the San Luis Contractors, believing that they are entitled to preferential access to water from the San Luis Reservoir, sued the Bureau and its regional director. The San Luis Contractors alleged in their complaint that the Bureau’s intended diversion of Reservoir water to serve the needs of the Exchange contractors was contrary to the obligation in the Exchange Contract to release water from Millerton Lake in the event of an inability to provide substitute water. They further alleged that the intended diversion of Reservoir water to the Exchange contractors violated the Act and the Westlands and San Benito contracts. Relief was sought under the Administrative Procedure Act (APA), 5 U.S.C. §§ 701-706, and federal reclamation law. The San Luis Contractors prayed for an injunction “prohibiting the Bureau from rediverting water stored in San Luis Reservoir to satisfy its contractual obligations to the Exchange contractors,” and “a declaration that Plaintiffs have prior rights to the water stored in the San Luis Reservoir pursuant to the terms of the San Luis Act-and contracts entered into thereunder and that the Bureau may not satisfy its obligations to the Exchange contractors through rediversion of project water from storage in San Luis Reservoir.”

The Exchange contractors and several users of water from Millerton Lake intervened in support of the Bureau. The Bureau filed a motion to dismiss under Fed.R.Civ.P. 12(b)(6). The intervenors moved for judgment on the pleadings under Fed.R.Civ.P. 12(c). The district court considered the motions together, granted them, and dismissed the suit without leave to amend. Westlands Water Dist. v. Dept. of Interior, 805 F.Supp. 1503 (E.D.Cal.1992).

DISCUSSION

We review de novo rulings on Rule 12(b) motions to dismiss for failure to state a claim and Rule 12(c) motions for judgment on the pleadings. Assiniboine and Sioux Tribes v. Bd. of Oil and Gas Conservation, 792 F.2d 782, 794 (9th Cir.1986) (motion to dismiss); 3550 Stevens Creek Assoc. v. Barclays Bank, 915 F.2d 1355, 1357 (9th Cir.1990), cert. denied, — U.S. -, 111 S.Ct. 2014, 114 L.Ed.2d 101 (1991) (motion for judgment on the pleadings). In deciding a motion to dismiss, the district court must accept as true all material allegations in the complaint and construe them in the light most favorable to the plaintiff. NL Indus., Inc. v. Kaplan, 792 F.2d 896, 898 (9th Cir.1986). Similarly, a judgment on the pleadings is appropriate when, even if all allegations in the complaint are true, the moving party is entitled to judgment as a matter of law. Hal Roach Studios v. Richard Feiner & Co., 896 F.2d 1542, 1550 (9th Cir.1990).

A. Statutory Claims

The APA provides a remedy for agency action found to be “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law,” or found to be “in excess of statutory jurisdiction, authority, or limitations, or short of statutory right....” 5 U.S.C. § 706. The San Luis Contractors contend that diverting Reservón’ water to serve the needs of the Exchange contractors is remediable under the APA since such action violates the San Luis Act. Specifically, they claim that such action would violate § 1(a) of the Act, which provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Westlands Water District v. Firebaugh Canal, 10 F.3d 667 (9th Cir. 1993).

10 F.3d 667 (Westlands Water District v. Firebaugh Canal) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Untitled Case
E.D. California, 2026
(PC)Valencia v. Medina
E.D. California, 2025
Brown v. Kijakazi
N.D. California, 2025
Freeze v. Gallagher
W.D. Washington, 2024
Ponce v. Kijakazi
E.D. Washington, 2022
Edler v. Kijakazi
E.D. Washington, 2021
(PC) Quair v. Collier
E.D. California, 2021
Schmorde v. Saul
E.D. Washington, 2021
Westlands Water District v. Patterson
900 F. Supp. 1304 (E.D. California, 1995)