Western Sun Contractors Co. v. Superior Court

766 P.2d 96, 159 Ariz. 223, 24 Ariz. Adv. Rep. 20, 1988 Ariz. App. LEXIS 376
CourtCourt of Appeals of Arizona
DecidedDecember 29, 1988
Docket1 CA-SA 88-168
StatusPublished
Cited by11 cases

This text of 766 P.2d 96 (Western Sun Contractors Co. v. Superior Court) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Sun Contractors Co. v. Superior Court, 766 P.2d 96, 159 Ariz. 223, 24 Ariz. Adv. Rep. 20, 1988 Ariz. App. LEXIS 376 (Ark. Ct. App. 1988).

Opinion

OPINION

JACOBSON, Judge.

This special action arises out of the City of Peoria’s (City) award of a construction contract for a sewer project to Pipe Tech, Inc., after the City determined that Pipe Tech was the lowest bidder and was entitled to the statutory preference allowed by A.R.S. § 34-241(A). The superior court denied the special action relief requested by the second-lowest bidder, Western Sun Contractors Co., after the City rejected Western Sun’s bid protest. Western Sun filed this special action from the trial court’s order upholding the contract award and dismissing Western Sun’s complaint.

In the superior court special action, Western Sun contended that Pipe Tech was not entitled to the contractor’s five percent preference established in A.R.S. § 34-241(A), and thus the contract should have been awarded to it. Because we find that the trial court erred in determining that Pipe Tech’s payment under an equipment rental contract of a renter’s pro rata share of the lessor’s property tax met the tax requirement of A.R.S. § 34-241(A), (C)(1), (3), we need not address the remaining issues raised in superior court. 1

Factual Background

The City invited bids for construction of the Peoria Pivotal Sewer Project, in accordance with the competitive bidding process required by A.R.S. §§ 34-201 et seq. On Friday afternoon, July 15, 1988, the City opened the bid proposals. The two lowest bids were by Pipe Tech, for $667,858, and by Western Sun, for $665,915. The difference between the bids was .3%.

On Monday, July 18, 1988, Western Sun hand-delivered to the Peoria City Engineer a letter advising that a review of the Mari-copa County Assessor’s records indicated that Pipe Tech had not paid any taxes during the preceding two year period, as required by A.R.S. § 34-241(A) 2 to be entitled to the five percent preference. Western Sun contended that it had met the statutory requirements for the preference and concluded:

Inasmuch as it appears that Pipe-Tech, Inc. does not meet the requirements of A.R.S. Section 34-241, we respectfully request that the Peoria Pivotal Sewer Improvement Project be awarded to Western Sun Contractors.

On Thursday, July 21, 1988, the Peoria City Engineer responded by letter to Western Sun:

Staff has made a preliminary determination that the bid bond submitted by Pipe Tech, Inc., the apparent low bidder, did not comply with project specifications. Therefore, we are recommending that City Council reject Pipe Tech’s bid and authorize the City Manager to assign the contract to Western Sun Contractors. We have also requested that Pipe Tech, Inc. provide evidence that they qualify as a preferred contractor according to A.R.S. 34-241.
We have scheduled a meeting for Tuesday, July 26, 1988, ... at City Hall and we request that you or a representative from your company attend and be able to *226 provide evidence that Western Sun Contractors qualifies as a preferred contractor.

On Tuesday, July 26, 1988, at 5:30 p.m., the Peoria City Attorney held a hearing to determine, prior to the City Council meeting to be held at 7:00 p.m., whether the two lowest bidders were entitled to the five percent statutory bid preference. Both contractors appeared and presented evidence, and the City Attorney concluded both were entitled to the preference. Based upon the City Attorney’s advice the City Council awarded the contract to Pipe Tech by a vote of 5-0.

On Friday, July 29, 1988, Western Sun’s attorney contacted Pipe Tech’s attorney, and was advised that the signed construction contract would be delivered to the City on Monday, August 1, 1988. At oral argument in this court, Western Sun’s attorney avowed that on Friday, July 29, 1988, he also contacted the City Attorney and provided case law and statutory authority with a request for reconsideration of the bid protest. On Monday, August 1, 1988, the City Attorney denied the request for reconsideration, and the City issued a notice to proceed to Pipe Tech. The following day, on Tuesday, August 2, 1988, Western Sun filed its complaint for special action in superior court, seeking to enjoin the City from proceeding with its contract with Pipe Tech and directing the City to award the contract to Western Sun.

On Tuesday, August 2, 1988, the trial court issued an interlocutory stay, enjoining the City from proceeding with the construction contract. Based upon an expedited procedure, on Monday, August 8, 1988, the trial court held a hearing on the complaint, and issued its ruling, stating in part:

THE COURT DETERMINES that the City Council of Peoria did not act illegally or arbitrarily in accepting the recommendation of its attorney ... that the invoice from Empire Machinery reflected Pipe Tech’s pro rata share of Property Tax attributable to the value of the equipment rented by it from Empire Machinery thereby satisfying the two year consecutive payment of state or county taxes in an amount of at least $200.00 to be a preferred contractor under A.R.S. § 34-241.

On Wednesday, August 10, 1988, the trial court issued its formal order affirming its decision regarding the tax requirement, rejecting the other issues raised by Western Sun, and dismissing the complaint. Western Sun filed a special action in this court on Thursday, August 11, 1988. We issued an interlocutory stay on Friday, August 12, 1988, and ordered accelerated briefing so that this matter could be heard on Monday, August 15, 1988.

Special Action Jurisdiction

Rule 8, Arizona Rules of Procedure for Special Actions, provides as follows:

A decision of a Superior Court in a special action shall be reviewed by appeal where there is an equally plain, speedy, and adequate remedy by that means. Procedure for appeal shall be as prescribed by the applicable rules, except that on application of either party, for cause shown at any time after filing of notice of appeal, the court in which the appeal is pending may waive or order an acceleration of any or all appeal procedures. Where there is no equally plain, speedy, and adequate remedy by appeal, a judgment in a special action in a Superior Court may be reviewed by a special action directed against the original defendants. 3

*227

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sw Fabrication v. Phoenix
Court of Appeals of Arizona, 2019
Power v. Gilbert
Court of Appeals of Arizona, 2015
Fidelity National Title Co. v. Town of Marana
204 P.3d 1096 (Court of Appeals of Arizona, 2009)
State v. Shipman
94 P.3d 1169 (Court of Appeals of Arizona, 2004)
State of Arizona v. Shipman Sweeney
Court of Appeals of Arizona, 2004
Tire Shredders, Inc. v. Pima County
965 P.2d 86 (Court of Appeals of Arizona, 1998)
Burnette v. Bender
908 P.2d 1086 (Court of Appeals of Arizona, 1995)
Big D Construction Corp. v. Court of Appeals
789 P.2d 1061 (Arizona Supreme Court, 1990)
REM Construction, Inc. v. Houghton
783 P.2d 261 (Court of Appeals of Arizona, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
766 P.2d 96, 159 Ariz. 223, 24 Ariz. Adv. Rep. 20, 1988 Ariz. App. LEXIS 376, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-sun-contractors-co-v-superior-court-arizctapp-1988.