Wellbilt Equipment Corp. v. Fireman

275 A.D.2d 162, 719 N.Y.S.2d 213, 2000 N.Y. App. Div. LEXIS 14135
Appellate Division of the Supreme Court of the State of New York·Decided October 12, 2000·Published·Cited by 18 cases

Opinion

OPINION OF THE COURT

Friedman, J.

On this appeal we are required to determine whether a Lien Law § 39-a claim, which seeks damages for the alleged wilful exaggeration of a lien, survives the consensual discharge of the lien. We conclude that where, as here, the lien is discharged on consent of the parties and the lienor’s action to foreclose the lien is discontinued, a wilful exaggeration claim does not survive.

In or about September 1994, defendants hired plaintiff Wellbilt to construct the Red Eye Grill restaurant in Manhattan.* Plaintiff asserts that after construction commenced defendants repeatedly changed architects, building plans, and interior requirements. As a result, plaintiff advised defendants that construction costs would likely rise.

After construction was largely completed, the Red Eye Grill restaurant opened for business in November of 1996. About the same time, plaintiff demanded that defendants make additional payments towards the construction cost, which plaintiff asserted had risen to $5,000,000. In a letter dated December 2, 1996, defendants admitted to plaintiff that it was entitled to more than $2,362,000 in fees, disputing only the amount that [164] plaintiff was due beyond that sum. Despite the acknowledgment that $2,362,000 was due, defendants paid plaintiff only $2,054,000, leaving a balance that, according to defendants’ own calculations, exceeded $300,000., In view of defendants’ failure to make payment beyond the $2,054,000, plaintiff filed a lien against the property.

The first lien, which was filed on July 22, 1997, alleged that the total cost of construction was $5,000,000, of which a balance of $2,946,000 remained unpaid. The dispute not being resolved, this action was commenced one month later.

Plaintiffs complaint asserted causes of action, inter alia, for breach of contract and foreclosure of the lien. Shortly after commencement of the action, however, plaintiff discovered that its lien was fatally defective because it had failed to file proof of service of the notice of lien with the County Clerk within 35 days as required by Lien Law § 11. In view of this, plaintiff refiled the lien on September 10, 1997, this time properly filing proof of service.

As plaintiffs foreclosure action was premised on the defective lien it had previously filed, plaintiff also served a supplemental summons and complaint identical in all respects to its original summons and complaint, except that the complaint sought to foreclose the second lien, instead of the first.

In response, defendants served an amended answer, which interposed various counterclaims. As is relevant to this appeal, the second counterclaim alleged that both of the liens filed by plaintiff were wilfully exaggerated, thereby requiring the liens to be discharged. The third counterclaim attacked the allegedly duplicative nature of the liens, i.e., since both liens were for the identical work, the liens viewed together were necessarily exaggerated. The fourth counterclaim sought damages pursuant to Lien Law § 39-a, asserting that the liens were wilfully exaggerated whether viewed individually or jointly.

Thereafter, plaintiff moved for partial summary judgment against defendants in the amount of $406,000 and for an immediate trial as to the extent of plaintiffs damages beyond that amount. The motion was premised upon a concession in defendants’ answer, which stated that plaintiff had been paid all but $406,000. Defendants cross-moved for summary judgment on their second, third, and fourth counterclaims, arguing that the two liens, when viewed together, were exaggerated since they were duplicative of each other.

Supreme Court granted plaintiff partial summary judgment, awarding it damages in the sum of $406,000 (a matter which is [165] not the subject of this appeal), leaving for trial a determination of whether plaintiff was entitled to any sums beyond $406,000. The court also denied defendants’ cross motion for summary judgment and granted plaintiff reverse summary judgment dismissing defendants’ second, third, and fourth counterclaims.

In dismissing defendants’ counterclaims, Supreme Court apparently viewed such claims as being rooted only in the alleged duplication of the liens. Since the court found that the first lien was void by operation of law, and that the second lien was filed merely because of plaintiffs failure to properly perfect the first lien, the court concluded that there was no basis for a wilful exaggeration claim. This appeal by defendants followed.

Before this appeal was perfected, however, defendants entered into a stipulation with plaintiff regarding the lien. Pursuant to that stipulation, plaintiff discharged the lien and discontinued its seventh cause of action, which sought to foreclose the lien. The stipulation did not resolve the issue of how much additional money plaintiff was owed. That issue was left for trial.

The principal issue presented by this appeal concerns the effect of this stipulation on defendants’ counterclaims. A subsidiary issue concerns the effect of plaintiffs filing of duplicate liens. Analysis of the matter must begin with the statutory backdrop.

Section 39 of the Lien Law provides that: “In any action * * * to enforce a mechanic’s lien * * * if the court shall find that a lienor has wilfully exaggerated the amount for which he claims a lien as stated in his notice of lien, his lien shall be declared to be void.”

Where a lien has been discharged under this section, Lien Law § 39-a permits the recovery of damages. Thus, section 39-a provides: “Where in any action * * * to enforce a mechanic’s lien * * * the court shall have declared said lien to be void on account of wilful exaggeration the person filing such notice of lien shall be liable in damages to the owner or contractor.”

Regarding the issue of plaintiffs filing of duplicate liens, we agree with Supreme Court’s conclusion that a wilful exaggeration claim premised upon this ground cannot stand. The first lien filed by plaintiff was, as a matter of law, void because of plaintiffs failure to file proof of service of the notice of lien with the County Clerk within 35 days as required by Lien Law § 11 (Outrigger Constr. Co. v Nostrand Ave. Dev. Corp., 217 [166] AD2d 689). In view of this, plaintiffs filing of a second lien, which it plainly did in recognition that its first lien was defective, could not support a claim of wilful exaggeration. Hence, Supreme Court was correct in finding that the second filing did not entitle defendants to summary judgment.

Defendants contend, however, that, even if Supreme Court was correct with regard to the duplication of the liens, the court nevertheless erred in dismissing their wilful exaggeration claims and granting plaintiff reverse summary judgment. In this regard, they point out that, setting aside the purported duplication of the lien, there remained a claim that the second lien, viewed individually, was itself wilfully exaggerated. Defendants further contend that the subsequent discharge of the lien pursuant to stipulation has no effect on the viability of their exaggeration claim. This latter contention by defendants does not bear scrutiny.

Free access — add to your briefcase to read the full text and ask questions with AI

Wellbilt Equipment Corp. v. Fireman, 275 A.D.2d 162, 719 N.Y.S.2d 213, 2000 N.Y. App. Div. LEXIS 14135 (N.Y. Ct. App. 2000).

275 A.D.2d 162 (Wellbilt Equipment Corp. v. Fireman) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

400 W 59th St Partners LLC v. Wyse
2025 NY Slip Op 50676(U) (NYC Civil Court, New York, 2025)
J.T. Magen & Co. Inc. v. Nissan N. Am., Inc.
2025 NY Slip Op 31006(U) (New York Supreme Court, New York County, 2025)
JDS Constr. Group LLC v. Copper Servs., LLC
2024 NY Slip Op 34551(U) (New York Supreme Court, New York County, 2024)
JDS Constr. Group LLC v. Copper Servs., LLC
2024 NY Slip Op 02097 (Appellate Division of the Supreme Court of New York, 2024)
Adria Infrastructure, LLC v. Henick-Lane, Inc.
172 N.Y.S.3d 448 (Appellate Division of the Supreme Court of New York, 2022)
Matter of Matrix Staten Is. Dev., LLC v. BKS-NY, LLC
2022 NY Slip Op 02795 (Appellate Division of the Supreme Court of New York, 2022)
Degraw Constr. Group, Inc. v. McGowan Bldrs., Inc.
2019 NY Slip Op 8820 (Appellate Division of the Supreme Court of New York, 2019)
Harrington v. Smith
138 A.D.3d 548 (Appellate Division of the Supreme Court of New York, 2016)
Great American Restoration Services, Inc. v. Flaton
48 Misc. 3d 78 (Appellate Terms of the Supreme Court of New York, 2015)
High Tech Enterprises & Electrical Services of NY, Inc. v. Expert Electrical, Inc.
113 A.D.3d 546 (Appellate Division of the Supreme Court of New York, 2014)
Goddard v. Martino
40 Misc. 3d 1050 (New York Supreme Court, 2013)
Martino v. Consolidated Edison Co. of New York, Inc.
105 A.D.3d 575 (Appellate Division of the Supreme Court of New York, 2013)
5 Brothers, Inc. v. D.C.M. of New York, LLC
39 Misc. 3d 711 (New York Supreme Court, 2013)
Executive Towers at Lido, LLC v. Metro Construction Services, Inc.
303 A.D.2d 545 (Appellate Division of the Supreme Court of New York, 2003)
Yellow Book of NY L. P. v. Dimilia
188 Misc. 2d 489 (Nassau County District Court, 2001)