5 Brothers, Inc. v. D.C.M. of New York, LLC

39 Misc. 3d 711
CourtNew York Supreme Court
DecidedFebruary 13, 2013
StatusPublished

This text of 39 Misc. 3d 711 (5 Brothers, Inc. v. D.C.M. of New York, LLC) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
5 Brothers, Inc. v. D.C.M. of New York, LLC, 39 Misc. 3d 711 (N.Y. Super. Ct. 2013).

Opinion

OPINION OF THE COURT

Carolyn E. Demarest, J.

In this action, general contractor D.C.M. of New York, LLC moves to vacate an arbitration award rendered in favor of subcontractor Vintage Flooring & Tile Inc. Under a separate index number, Vintage moves to confirm the arbitration award.

Background

The underlying disputes stem from a construction improvement project for Best Buy retail store at Kings Plaza Mall. DCM, the general contractor for the project, entered into agreements with various subcontractors, including Vintage, for materials and work to be performed on the project.

The Arbitration between DCM and Vintage

On December 1, 2010, the parties entered into an agreement whereby Vintage was to provide labor and materials to DCM in connection with the Best Buy project. The agreement contained, inter alia, a mandatory arbitration clause. After certain controversies arose between the parties, DCM initiated arbitration by a demand filed May 13, 2011. On May 31, 2011, Vintage responded with an answer and counterclaims. Several hearings were conducted between February 14 and May 23, 2012, and upon the submissions by parties of voluminous exhibits, prehearing, post-hearing, and post-hearing reply briefs, Arbitrator Melvin J. Kalish rendered a decision on July 24, 2012, awarding Vintage $76,539.13, plus interest, and directed DCM to make payment within 20 days. The award indicated that the “mon[713]*713etary award to [Vintage] ... is intended to include all claims of [Vintage], its subcontractors and suppliers” and directed Vintage to, upon receipt of payment, “simultaneously provide to [DCM] or its counsel in form and substance acceptable for filing ... a Satisfaction of Mechanic’s Lien of the $207,000.00 Mechanic’s Lien.”

The 5 Brothers Action

Meanwhile, on September 23, 2011, 5 Brothers, Inc., another of the subcontractors on the Best Buy project, initiated an action (the 5 Brothers action) against DCM seeking, inter alia, judgment for unpaid amounts or foreclosure on its mechanic’s lien. 5 Brothers named, among other defendants, seven additional parties who had also filed mechanic’s liens against DCM in connection with the project, including Vintage. DCM filed its answer and counterclaim on October 20, 2011, and on November 15, 2011, Vintage filed cross claims for breach of contract, quantum meruit, foreclosure of its mechanic’s lien, account statement, and unjust enrichment against DCM, and cross claims for personal liability on the amount due and punitive damages against Brian Abbey, the sole member of DCM. In response, DCM answered and counterclaimed against Vintage for willful exaggeration of its mechanic’s lien. On October 24, 2012, DCM moved (a) to vacate the award of July 24, 2012 awarding $76,539.13 to Vintage, (b) for summary judgment dismissing Vintage’s lien claim, and (c) for summary judgment on its lien exaggeration claim. Vintage has not filed opposition papers.1

[714]*714Vintage’s Motion to Confirm the Arbitration

Not having received payment of the award, on September 21, 2012, Vintage moved to confirm the award in its separate proceeding (see Vintage Flooring and Tile Inc. v DCM of NY LLC, index No. 19094/2012). By papers dated October 31, 2012, DCM opposed Vintage’s motion, citing the pending 5 Brothers action and adopting all the arguments set forth in its motion to vacate filed in that action.

Discussion

DCM moves pursuant to CPLR 7511 (b) (1) (iii) to vacate and set aside the award, on the grounds that it is irrational, against public policy, and indefinite. DCM asserts that the award is irrational because (a) items were awarded to Vintage without proof or justification, and (b) it is based upon a willfully exaggerated mechanic’s lien. Furthermore, DCM argues, because the Arbitrator failed to address the amount DCM alleges is due to it under its willfully exaggerated lien claim, the award is indefinite and contrary to public policy as it precludes DCM’s recovery of treble damages.

Vintage has not filed papers opposing this motion. However, in its separate action, Vintage moves pursuant to CPLR 7510 to confirm the award. DCM opposes the motion, referencing the pending 5 Brothers action, incorporating its prior arguments, and reiterating that because the Arbitrator did not have the power to address its exaggerated lien claim, the award remains indefinite and incomplete.

The party seeking to set aside an arbitration award has the burden to show its invalidity (see Caso v Coffey, 41 NY2d 153, 159 [1976]). Where parties have voluntarily consented to arbitration, courts review awards with less scrutiny than they do awards made pursuant to compulsory arbitration (see Mount St. Mary’s Hosp. of Niagara Falls v Catherwood, 26 NY2d 493, 508 [1970]; Dahn v Luchs, 92 AD2d 537, 537 [2d Dept 1983]). Indeed, courts are reluctant to disturb arbitration awards (see Matter of Goldfinger v Lisker, 68 NY2d 225 [1986]). CPLR 7511 provides the four narrow grounds upon which an arbitration award may be vacated: if the rights of a party were prejudiced by “(1) corruption, fraud, or misconduct in procuring the award, (2) partiality of a supposedly neutral arbitrator, (3) the arbitrator exceeding his powers so that no final and definite award was made, or (4) failure to follow procedures provided by CPLR [715]*715article 75” (Matter of Matra Bldg. Corp. v Kucker, 2 AD3d 732, 733-734 [2d Dept 2003]). Upon the denial of a motion to vacate an award, a court should confirm it (see CPLR 7511 [e]). In support of vacatur, DCM claims both that the Arbitrator exceeded his powers and that the award is indefinite.

An arbitrator “ ‘ exceed [s] his power’ under the meaning of the statute where his ‘award violates a strong public policy, is irrational or clearly exceeds a specifically enumerated limitation on the arbitrator’s power’ ” (Matter of Kowaleski [New York State Dept. of Correctional Servs.], 16 NY3d 85, 90-91 [2010], quoting Matter of New York City Tr. Auth. v Transport Workers’ Union of Am., Local 100, AFL-CIO, 6 NY3d 332, 336 [2005]; see also Matter of Heifetz [Walker & Zanger], 227 AD2d 623, 624 [2d Dept 1996]). “An award is irrational only if there is no proof whatever to justify the award” (Matter of Susan D. Settenbrino, P.C. v Barroga-Hayes, 89 AD3d 1094, 1095 [2d Dept 2011] [citation omitted]).

The law and policy of this state are clear that arbitrators are not bound by the principles of substantive law or rules of procedure governing the traditional litigation process (see Matter of Salco Constr. Co. v Lasberg Constr. Assoc., 249 AD2d 309, 309 [2d Dept 1998]), nor must they “make findings, specify the formula used in calculating the award, or indicate the bases for the award” (id.). “It is well established that an arbitrator is not required to justify his award” (Dahn v Luchs, 92 AD2d 537, 538 [1983]).

DCM argues that the award must be vacated as irrational because the Arbitrator denied several back charges to DCM involving cleaning work. Though the Arbitrator stated that there was credible evidence establishing that Vintage had performed the cleaning work, DCM asserts that no such evidence was offered and that such an unjustified decision amounts to irrationality.

DCM’s argument is unavailing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith Barney Shearson Inc. v. Sacharow
689 N.E.2d 884 (New York Court of Appeals, 1997)
New York City Transit Authority v. Transport Workers' Union of America
845 N.E.2d 1243 (New York Court of Appeals, 2005)
Mount St. Mary's Hospital v. Catherwood
260 N.E.2d 508 (New York Court of Appeals, 1970)
Goldfinger v. Lisker
500 N.E.2d 857 (New York Court of Appeals, 1986)
Matra Building Corp. v. Kucker
2 A.D.3d 732 (Appellate Division of the Supreme Court of New York, 2003)
Susan D. Settenbrino, P.C. v. Barroga-Hayes
89 A.D.3d 1094 (Appellate Division of the Supreme Court of New York, 2011)
In re the Arbitration between Teamsters Local Union 693 & Coverall Service & Supply Co.
84 A.D.2d 609 (Appellate Division of the Supreme Court of New York, 1981)
Dahn v. Luchs
92 A.D.2d 537 (Appellate Division of the Supreme Court of New York, 1983)
In re the Arbitration between Guetta & Raxon Fabrics Corp.
123 A.D.2d 40 (Appellate Division of the Supreme Court of New York, 1987)
Gasbarre v. City of Rochester
155 A.D.2d 943 (Appellate Division of the Supreme Court of New York, 1989)
Rudolph's Women's Apparel of Mt. Kisco, Inc. v. Chiappinelli
167 A.D.2d 379 (Appellate Division of the Supreme Court of New York, 1990)
Scott v. Bridge Chrysler Plymouth, Inc.
214 A.D.2d 675 (Appellate Division of the Supreme Court of New York, 1995)
Guzman v. Estate of Fluker
226 A.D.2d 676 (Appellate Division of the Supreme Court of New York, 1996)
In re Heifetz
227 A.D.2d 623 (Appellate Division of the Supreme Court of New York, 1996)
Salco Construction Co. v. Lasberg Construction Associates, Inc.
249 A.D.2d 309 (Appellate Division of the Supreme Court of New York, 1998)
Wellbilt Equipment Corp. v. Fireman
275 A.D.2d 162 (Appellate Division of the Supreme Court of New York, 2000)
Executive Towers at Lido, LLC v. Metro Construction Services, Inc.
303 A.D.2d 545 (Appellate Division of the Supreme Court of New York, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
39 Misc. 3d 711, Counsel Stack Legal Research, https://law.counselstack.com/opinion/5-brothers-inc-v-dcm-of-new-york-llc-nysupct-2013.