Pyramid Champlain Co. v. R.P. Brosseau & Co.

267 A.D.2d 539, 699 N.Y.S.2d 516
CourtAppellate Division of the Supreme Court of the State of New York
DecidedDecember 2, 1999
StatusPublished
Cited by29 cases

This text of 267 A.D.2d 539 (Pyramid Champlain Co. v. R.P. Brosseau & Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pyramid Champlain Co. v. R.P. Brosseau & Co., 267 A.D.2d 539, 699 N.Y.S.2d 516 (N.Y. Ct. App. 1999).

Opinion

—Mikoll, J.

Cross appeals from an order and judgment of the Supreme Court (Viscardi, J.), entered October 27, 1998 in Clinton County, upon a decision of the court in favor of defendant R.P. Brosseau & Company and plaintiff Westinghouse Electric Supply Company.

These consolidated actions involve various claims arising out of contracts for electrical work in connection with the construction of the Pyramid Champlain Centre North shopping mall in the Town of Plattsburgh, Clinton County. In early 1987, the owner/developer of the project, Pyramid Champlain Company, entered into three contracts with defendant R.P. Brosseau & Company (hereinafter Brosseau) to furnish and install electrical equipment in two “anchor” stores, Sears and J.C. Penne/s; the third contract covered electrical work within the mall building itself (hereinafter the mall contract). Most of the electrical equipment and supplies required for the project were custom designed and ordered by Brosseau from plaintiff Westinghouse Electric Supply Company (hereinafter WESCO), with the understanding that payment therefor could not be made until Pyramid paid Brosseau.

Brosseau first commenced work pursuant to the Sears contract, dated January 13, 1987, and shortly thereafter entered into and commenced work pursuant to the J.C. Pen[540]*540ney’s contract, dated February 19, 1997. Although the mall contract was entered into on March 7, 1987, Brosseau was unable to begin performance thereunder until March 30, 1987 due to Pyramid’s delay in making the site available and furnishing drawings and specifications. The contracts provided that Brosseau was to submit payment requisitions for labor and materials to Pyramid by the 25th of each month, which would be paid by the 10th of the following month. Initially, Pyramid paid Brosseau pursuant to requisitions that were submitted without dispute. As of April 9, 1987, Brosseau had paid WESCO a total of approximately $149,000 and was in full compliance with the contract with WESCO. Subsequently, however, Pyramid refused to pay requisitions submitted by Brosseau on April 25, 1987 and May 25, 1987, rendering Brosseau unable to pay WESCO for materials shipped after April 9, 1987. Brosseau continued working on the project until June 10, 1987, when it left the site as a result of Pyramid’s failure to make payments due under the contracts.1

Thereafter, Pyramid commenced action No. 1 against Brosseau alleging, inter alia, breach of contract and willful exaggeration of three mechanics’ liens Brosseau had filed in connection with each of the contracts. WESCO commenced action No. 2 against Brosseau, Pyramid and others seeking collection of unpaid sums due for materials, equipment and supplies delivered and incorporated into the project. Brosseau asserted claims against Pyramid seeking foreclosure of the three mechanics’ liens and damages for, inter alia, breach of contract. The actions were subsequently consolidated for discovery and trial and, following motions and discovery, a 16-day nonjury trial was conducted in 1996. In a written decision issued in 1998, Supreme Court determined that Pyramid breached its contracts with Brosseau by unjustifiably failing to pay the requisitions and was directly liable to WESCO based upon an enforceable oral promise to pay for materials shipped after April 9, 1987. Supreme Court further determined that Brosseau was jointly liable with Pyramid for certain amounts awarded to WESCO. Judgment was entered accordingly, prompting these cross appeals by Pyramid and WESCO.

We first take up Pyramid’s contention that Supreme Court erred in concluding that it breached its three contracts with Brosseau. We note at the outset that although the scope of our review of this nonjury trial is not limited to determining [541]*541whether the court’s findings are supported by the weight of the credible evidence, we customarily accord considerable deference to the trial court’s findings in view of its superior ability to assess credibility and consequently determine the weight to be accorded the evidence (see, Weinberg v Crilley, 252 AD2d 861; Harter v Krause, 250 AD2d 984). This principle is all the more saliently applied where, as here, the trial was lengthy and included much sharply conflicting testimony. Upon a full review of the record, we are satisfied that ample evidence supports Supreme Court’s findings and we find no compelling reason to disturb the credibility determinations which informed them (see, Weaver v Acampora, 227 AD2d 727; New Day Bldrs. v SJC Realty, 219 AD2d 623, 624).

Dealing first with the J.C. Penney’s and Sears projects, Pyramid’s site controller testified that he was instructed by his project manager to deny Brosseau’s April 25, 1987 and May 25, 1987 payment requisitions on the ground of nonperformance. The testimony established, however, that these projects were substantially completed when Pyramid refused payment: the J.C. Penney’s project was substantially complete by March 21, 1987 and the Sears project was 99% complete by June 10, 1987. That which was not complete on the Sears and J.C. Penney’s contracts was work that could not be performed until other aspects of the project were completed. An inspection conducted by OSHA established that Brosseau’s work was 100% compliant with its inspection standards. Moreover, Pyramid had requested and drawn down funds from the bank funding the project based on the scope of work completed. As noted by Supreme Court, Pyramid produced no evidence to justify its refusal to pay Brosseau the balance due on the Sears and J.C. Penney’s contracts.

As to the malí contract, the record contains ample evidence from which Supreme Court could have concluded that Brosseau’s failure to complete the contracts was the result of Pyramid’s conduct either designed to, or at the very least having the effect of, frustrating its performance. Relying on this evidence, the court concluded that the reasons cited by Pyramid as justifying denial of payment to Brosseau flowed from Pyramid’s own actions rather than Brosseau’s failure to adhere to the contract specifications or supply the requisite number of workers to complete the job in a timely fashion.

As noted, Brosseau’s delay in beginning work on the mall contract was occasioned by Pyramid’s failure to make the site available and to provide necessary drawings and specifications. Throughout the project, Pyramid continually made numerous, [542]*542substantial alterations to the contract terms, not only impeding Brosseau’s work but resulting in expansion of the scope of work in several areas, including temporary lighting, temporary power, fire alarms, fixtures and switch gears. As noted by Supreme Court, “Pyramid had four managers each directing Brosseau to jobs not planned, to change the material used, or to move already installed material without additional compensation.” Moreover, while Pyramid apparently knew as early as April 1987 that Brosseau planned to use a particular type of standard electrical cable, it failed to advise him of its intent to prohibit the use of such cable until it was incorporated into the project. As to the myriad of Pyramid’s claims of Brosseau’s inadequate performance, the court cited the absence of any witness to testify as to any specific failure and it refused to credit “self-serving” memos or letters placed in Brosseau’s contract file.

Nor do we find that Supreme Court erred in calculating the damages owed by Pyramid to Brosseau.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Century Indem. Co. v. Brooklyn Union Gas Co.
2024 NY Slip Op 24088 (New York Supreme Court, New York County, 2024)
Perez v. Masonry Servs., Inc.
2020 NY Slip Op 08012 (Appellate Division of the Supreme Court of New York, 2020)
Lapenna Contr., Ltd. v. Mullen
2020 NY Slip Op 06183 (Appellate Division of the Supreme Court of New York, 2020)
Cook v. Massachusetts Mut. Life Ins. Co.
2017 NY Slip Op 7825 (Appellate Division of the Supreme Court of New York, 2017)
Cook v. Massachusetts Mutual Life Insurance Co.
155 A.D.3d 1568 (New York Supreme Court, 2017)
Blair v. Ferris
2017 NY Slip Op 3586 (Appellate Division of the Supreme Court of New York, 2017)
NY Professional Drywall Of OC, Inc. v. Rivergate Development, LLC
137 A.D.3d 1509 (Appellate Division of the Supreme Court of New York, 2016)
Davis v. CEC, Inc.
135 A.D.3d 1049 (Appellate Division of the Supreme Court of New York, 2016)
Science Applications International Corporation v. Environmental Risk Solutions, LLC
132 A.D.3d 1161 (Appellate Division of the Supreme Court of New York, 2015)
Hutter v. Countrywide Bank, N.A.
41 F. Supp. 3d 363 (S.D. New York, 2014)
HAMILTON, ELIJAH v. PICARDO, GEORGE
Appellate Division of the Supreme Court of New York, 2014
Hamilton v. Picardo
118 A.D.3d 1260 (Appellate Division of the Supreme Court of New York, 2014)
Lewiarz v. Travco Insurance
82 A.D.3d 1464 (Appellate Division of the Supreme Court of New York, 2011)
Saratoga Associates Landscape Architects v. Lauter Development Group
77 A.D.3d 1219 (Appellate Division of the Supreme Court of New York, 2010)
Steinbeck v. Steinbeck Heritage Foundation
400 F. App'x 572 (Second Circuit, 2010)
McGuire v. Parties, Picnics & Promotions
45 A.D.3d 1264 (Appellate Division of the Supreme Court of New York, 2007)
Capogna v. Guella
41 A.D.3d 522 (Appellate Division of the Supreme Court of New York, 2007)
L.S. & Sons Farms, LLC v. Agway, Inc.
41 A.D.3d 1152 (Appellate Division of the Supreme Court of New York, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
267 A.D.2d 539, 699 N.Y.S.2d 516, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pyramid-champlain-co-v-rp-brosseau-co-nyappdiv-1999.