Blair v. Ferris

2017 NY Slip Op 3586, 150 A.D.3d 1365, 54 N.Y.S.3d 716, 2017 WL 1712790
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 4, 2017
Docket523502
StatusPublished
Cited by3 cases

This text of 2017 NY Slip Op 3586 (Blair v. Ferris) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blair v. Ferris, 2017 NY Slip Op 3586, 150 A.D.3d 1365, 54 N.Y.S.3d 716, 2017 WL 1712790 (N.Y. Ct. App. 2017).

Opinion

*1366 Egan Jr., J.

Appeal from a judgment of the Supreme Court (Muller, J.), entered January 19, 2016 in Clinton County, upon a decision of the court partially in favor of plaintiff.

In September 2008, defendant William P. Ferris Jr. (hereinafter Ferris) and defendant Kristen M. Ferris (hereinafter collectively referred to as defendants) entered into a contract with plaintiff to construct a single-family residence upon certain real property located in the City of Plattsburgh, Clinton County. The initial plans called for the construction of a two-story, single-family residence—comprising approximately 2,700 square feet—with an attached two-car garage for the contract price of $277,524; as originally designed, the plans called for a sizeable unfinished storage area on the second floor of the home. The contract further provided that any changes or additional work that was “not specified by [the] blue prints or contract” would be charged at certain specified rates—specifically, labor would be billed at $35 per hour per laborer, equipment would be billed at $120 per hour and materials would be billed at the “[a]s charged price.” Thereafter, in January 2009, plaintiff and defendants entered into a second contract that, insofar as is relevant here, modified the billing rates for any-changes or additional work performed by increasing the labor rate to $40 per hour per laborer and imposing a 15% mark-up on materials; the equipment rate remained unchanged. 1 A building permit was obtained and, in April 2009, plaintiff began excavating the site.

After the excavation work commenced and shortly before the foundation for the residence was poured, plaintiff learned that defendants had acquired an adjoining lot (thus requiring additional clearing and excavating) and, further, had revised the architectural plans to incorporate an in-law apartment— comprising approximately 900 square feet—into what now qualified under the local zoning ordinance as a two-family residence. According to plaintiff, although defendants provided him with certain elevation details that had been marked up to reflect, among other things, the addition of the in-law apartment, he did not see the revised architectural plans prior to *1367 commencing the excavation work. 2 There is no question that, during the course of the ensuing construction, defendants significantly expanded the scope of the project and that plaintiff, in turn, performed certain additional work with respect thereto, and defendants raise no issue as to the quality of the services rendered. There also is no dispute that no written change orders were either requested or prepared, and, in response to informal inquiries as to the cost overruns, plaintiff advised defendants that they were approximately $100,000 over budget.

Plaintiff completed his work on the project in or about December 2009 and, in January 2010, tendered an invoice to defendants requesting payment in the amount of $85,000—a figure that was computed on a time and materials basis and that purportedly represented the additional services and/or materials provided by plaintiff in connection with the project. Defendants declined to pay and, upon the advice of counsel, plaintiff prepared a second invoice in March 2010 in the amount of $160,633—a figure derived based upon the contract price. When defendants did not tender the requested sum, plaintiff filed a mechanic’s lien in the amount of $160,633 and thereafter commenced this action to foreclose upon the lien. Defendants answered and counterclaimed for damages in the amount of $129,720—contending that plaintiff had willfully exaggerated the lien.

Following a nonjury trial, Supreme Court found that plaintiff had a valid and existing mechanic’s lien in the principal sum of $57,600 plus interest and, accordingly, entered judgment in favor of plaintiff. As to defendants’ counterclaim, Supreme Court determined that, although the amount of the lien was incorrect, defendants failed to establish that plaintiff had willfully exaggerated the lien. Defendants now appeal.

Consistent with the provisions of Lien Law § 3, “a contractor who performs labor or furnishes materials for the improvement of real property with the consent, or at the request of, the owner shall have a lien for the principal and interest, of the value, or the agreed price, of such labor or materials upon the real property improved or to be improved and upon such improvement. A lienor may seek amounts due from both written contracts and from change orders for extras, depending on *1368 whether the owner gave his [or her] consent for the extra work. The lienor’s right to recover is limited by the contract price or the reasonable value of the labor and materials provided[,] [and] [t]he lienor has the burden of establishing the amount of the outstanding debt by proffering proof either of the price of the contract or the value of [the] labor and materials supplied” (DiSario v Rynston, 138 AD3d 672, 673 [2016] [internal quotation marks, ellipsis and citations omitted]). Proof of damages may be based solely upon the oral testimony of a witness— provided “the witness has knowledge of [either] the actual costs” (W.M.S. Bldrs. v Newburgh Steel Prods., 289 AD2d 567, 567 [2001] [internal quotation marks and citation omitted], lv denied 98 NY2d 603 [2002]; see Electronic Servs. Intl. v Silvers, 284 AD2d 367, 368 [2001], lv dismissed 97 NY2d 700 [2002], lv denied 99 NY2d 508 [2003]) or “the actual value of such extra work” (CNP Mech., Inc. v Allied Bldrs., Inc., 84 AD3d 1748, 1749 [2011]). Such knowledge may be gleaned from experience in the field (see Johnson v Robertson, 131 AD3d 670, 673 [2015]; compare Peak v Northway Travel Trailers, Inc., 27 AD3d 927, 928-929 [2006]), as well as detailed descriptions and personal observations of—or involvement in—the work performed (see W.M.S. Bldrs. v Newburgh Steel Prods., 289 AD2d at 567; Austin v Barber, 227 AD2d 826, 828 [1996]; see also Electronic Servs. Intl. v Silvers, 284 AD2d at 368; compare DiSario v Rynston, 138 AD3d at 674). Indeed, as long as the damages sought are not premised upon “pure speculation or bare assertions” that, in turn, find no support in the record (Proper v State Farm Mut. Auto. Ins. Co., 63 AD3d 1486, 1487 [2009]), documentary evidence will not be required (see CNP Mech., Inc. v Allied Bldrs., Inc., 84 AD3d at 1749; Austin v Barber, 227 AD2d at 828).

As noted previously, there is no question that defendants asked plaintiff to perform additional work on the project and that plaintiff, in turn, provided certain additional services and materials in conjunction therewith. 3 There also is no dispute that plaintiff is a reputable contractor who built a quality home for defendants, and that defendants, in turn, accepted the services and product that plaintiff provided. Hence, our inquiry distills to whether plaintiff tendered sufficient admissible proof to support the damages claimed in the lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Esperanza Mansion Group LLC v. Mehlenbacher
2025 NY Slip Op 04370 (Appellate Division of the Supreme Court of New York, 2025)
KTG Hospitality, LLC v. World Class Constr. Inc.
2024 NY Slip Op 32991(U) (New York Supreme Court, New York County, 2024)
Lapenna Contr., Ltd. v. Mullen
2020 NY Slip Op 06183 (Appellate Division of the Supreme Court of New York, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2017 NY Slip Op 3586, 150 A.D.3d 1365, 54 N.Y.S.3d 716, 2017 WL 1712790, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blair-v-ferris-nyappdiv-2017.