Weeks Dredging & Contracting, Inc. v. United States

33 Cont. Cas. Fed. 74,614, 11 Cl. Ct. 37, 1986 U.S. Claims LEXIS 792
CourtUnited States Court of Claims
DecidedSeptember 26, 1986
DocketNo. 694-84C
StatusPublished
Cited by20 cases

This text of 33 Cont. Cas. Fed. 74,614 (Weeks Dredging & Contracting, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weeks Dredging & Contracting, Inc. v. United States, 33 Cont. Cas. Fed. 74,614, 11 Cl. Ct. 37, 1986 U.S. Claims LEXIS 792 (cc 1986).

Opinion

POST-TRIAL INTERLOCUTORY OPINION

REGINALD W. GIBSON, Judge:

I. Introduction

This opinion endeavors to resolve a number of interlocutory issues arising out of the trial on the merits in subject case which was before the court from August 7 through September 11, 1986. In that connection, we address herein several motions by the parties: (1) plaintiffs motion in limine filed August 7, 1986; (2) plaintiffs motion to disqualify certain witnesses of the defendant made on August 25 and 26, 1986, as well as to strike certain testimony and exhibits;1 and (3) defendant’s motion to strike certain testimony of plaintiff’s expert witness made orally on September 10, 1986,2 and modified by written submission filed September 15, 1986. Supportive memoranda of law have been filed by the parties addressing each of the issues presented by the respective motions. In addition, this opinion also contains a statement of certification to the U.S. Court of Appeals for the Federal Circuit, pursuant to 28 U.S.C. § 1292(d)(2) (1982), relative to the controlling questions of law addressed in the parties’ FRE Rule 615 motions. Lastly, the parties are hereby ordered to appear before this court for a status conference relative to fixing a post-trial briefing schedule on Friday, October 10, 1986, at 10 a.m.

II. Statement of the Case

In this government contract case (i.e., awarded as DACW 01-79-C-0125 on April 2, 1979), the plaintiff, Weeks Dredging & Contracting, Inc. (Weeks) seeks an equitable adjustment in the amount of $3,941,648.00 (plus interest) arising out of a differing site conditions claim relative to a dredging contract entered into with the U.S. Army Corps of Engineers (Corps) on the now completed Tennessee-Tombigbee Waterway. Plaintiff claims that during the dredging operations in compliance with the contract, it encountered subsurface soil conditions which were materially different than those estimated by the Corps and contained in the Invitation for Bid, DACW 01-79-B-0039 (IFB). As a result, it is claimed, Weeks required an additional 215 days, beyond the stipulated contract completion date, in order to complete the project. Weeks now claims monetary compensation, inter alia, for the unanticipated 215 days of additional dredge time.

In reply, defendant alleges a number of exculpatory circumstances which it claims overcome plaintiff’s entitlement to any equitable adjustment. For example, defendant alleges that plaintiff’s project overruns were due to—(i) plaintiff’s own inadequate pre-bid site investigation, (ii) Weeks’ own inaccuracy in interpreting the contract documents, and (iii) also to an inexperienced and poorly qualified work force, rather than to a material differing site condition. In addition, and alternatively, defendant strenuously asserts that, as a matter of law, plaintiff’s claim is conclusively barred from any entitlement due to its failure to provide the Corps with timely notice of the differing site conditions claim as required by the contract.3

[40]*40It is because of this latter defense, i.e., of untimely notice which was initially raised in defendant’s pretrial submission, that plaintiff moved, in limine, to preclude defendant from adducing evidence of lack of timely notice at trial. From the beginning, i.e., in its complaint filed on December 26, 1984, plaintiff averred in paragraph 15 that:

Weeks gave the Corps timely notice of said differing site conditions, certified its claims, and requested an equitable adjustment to the Contract price and time plus a remission of liquidated damages assessed by the Corps.

(emphasis added). In fact, said averment appeared twice in the complaint by its incorporation into both Counts I and II. In its answer filed on March 20, 1985, defendant admitted the foregoing allegations contained in paragraph 15 as it appeared in both places (i.e., paragraph 19) in plaintiff’s complaint. Therein, defendant succinctly, unconditionally, and unambiguously states in response—“15. Admits.” It is plaintiff’s position, therefore, that inasmuch as defendant never amended its answer to provide otherwise (nor sought to explain such failure), and the issue was never addressed during pretrial discovery, which discovery concluded on November 30, 1985 (approximately 11 months after the complaint was filed), defendant is irreversibly bound at this posture by the unequivocal admission contained in its answer. As a consequence, plaintiff argues, defendant necessarily must be prohibited from raising the issue of timely notice by adducing evidence relative to the absence of such at trial. In support of its motion in bar, plaintiff cites to the decisions found at Baskett v. United States, 2 Cl.Ct. 356 (1983); Smith v. Chapman, 436 F.Supp. 58 (W.D. Tex.1977); and Seven-Up Bottling Co. v. Seven-Up Co., 420 F.Supp. 1246 (E.D.Mo. 1976).

Defendant, of course, opposes plaintiff’s motion on a number of grounds. First, it avers that inasmuch as plaintiff waited until the first day of trial to file its motion in limine, defendant alleges plaintiff's motion is itself untimely. Defendant also claims that the authorities cited to by plaintiff are inapposite in that they overlook the additional point that while admissions may be binding, in the discretion of the court, they may also be overlooked. For this proposition, defendant cites to McGee v. O & M Boat Co., 412 F.2d 75 (5th Cir.1969), and Freedom National Bank v. Northern Illinois Corp., 202 F.2d 601, 605 (7th Cir. 1953). On the foregoing proffered authority, and given the alleged erroneous nature of its admission, defendant argues that it should be relieved of any burden flowing therefrom. Lastly, defendant argues that no prejudice to plaintiff would occur were the motion in limine denied.

The second motion of the plaintiff, one framed to disqualify certain defense witnesses and to strike evidence and exhibits, arises out of somewhat serious and reprehensible circumstances which surfaced during the trial. In that connection, on Monday morning, August 25, 1986, following a weekend recess, defendant’s expert witness, Mr. Ronald Nettles, resumed the stand to permit counsel for the plaintiff to continue with his cross-examination. Counsel for plaintiff commenced his questioning with two seemingly innocuous questions. In substance, they sought to ascertain whether Mr. Nettles had, since the time and date his oath was administered, discussed his testimony with the defendant’s party representative, Dr. William Lang, and also whether Dr. Lang had discussed with Mr. Nettles the testimony of other plaintiff witnesses, particularly Dr. Kondner.4 Quite surprisingly, Mr. Nettles answered both questions in the affirmative (“Yes, I have.” and “Yes, he has.”).5 Upon [41]*41further pointed questioning of Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

RMH Tech LLC v. PMC Indus., Inc.
352 F. Supp. 3d 164 (D. Connecticut, 2018)
NCLN20, Inc. v. United States
99 Fed. Cl. 734 (Federal Claims, 2011)
State v. Copeland
2011 WI App 28 (Court of Appeals of Wisconsin, 2011)
Yankee Atomic Power Co. v. United States
94 Fed. Cl. 678 (Federal Claims, 2010)
Alli v. United States
86 Fed. Cl. 33 (Federal Claims, 2009)
Kislev Partners, L.P. v. United States
84 Fed. Cl. 378 (Federal Claims, 2008)
Norman v. United States
56 Fed. Cl. 255 (Federal Claims, 2003)
American Management Systems, Inc. v. United States
57 Fed. Cl. 275 (Federal Claims, 2003)
Marathon Oil Co. v. United States
42 Fed. Cl. 267 (Federal Claims, 1998)
Northrop Corp. v. United States
38 Cont. Cas. Fed. 76,491 (Federal Claims, 1993)
Smith v. Commissioner
92 T.C. No. 91 (U.S. Tax Court, 1989)
Thompson v. Commissioner
92 T.C. No. 29 (U.S. Tax Court, 1989)
Colorado Nat'l Bankshares, Inc. v. Commissioner
92 T.C. No. 14 (U.S. Tax Court, 1989)
Weeks Dredging & Contracting, Inc. v. United States
34 Cont. Cas. Fed. 75,356 (Court of Claims, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,614, 11 Cl. Ct. 37, 1986 U.S. Claims LEXIS 792, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weeks-dredging-contracting-inc-v-united-states-cc-1986.