Wayment v. Howard

2006 UT 56, 144 P.3d 1147, 561 Utah Adv. Rep. 37, 2006 Utah LEXIS 152, 2006 WL 2788975
CourtUtah Supreme Court
DecidedSeptember 29, 2006
Docket20050547, 010903790
StatusPublished
Cited by26 cases

This text of 2006 UT 56 (Wayment v. Howard) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wayment v. Howard, 2006 UT 56, 144 P.3d 1147, 561 Utah Adv. Rep. 37, 2006 Utah LEXIS 152, 2006 WL 2788975 (Utah 2006).

Opinion

WILKINS, Associate Chief Justice:

¶ 1 Appellant Lee R. Howard seeks review of the trial court’s decision finding for Appel-lees Glynn F. Wayment and Edward C. England on their claim of interference with water right number 35-8073 and against Howard’s counterclaims of trespass, negligence, and nuisance. We affirm on all issues.

BACKGROUND

¶ 2 Appellee Wayment owns real property bordered on the south by Appellee England. England’s property is bordered on the south by Appellant Howard’s property. A slough, traditionally known as the “Marriot Slough,” traverses the Appellees’ and the Appellant’s property. Appellees are successors in title to water right number 35-8073. This right was originally obtained by Mary Marriot in 1916 and provided for a flow rate of 0.5 cubic feet per second (cfs) of water to be used as irrigation water.

¶ 3 The trial court found that Appellees (as well as their predecessors) have accessed this water by damming the northern end of the slough, allowing the slough to fill, and then pumping water out of the slough to irrigate. The dam remains in place throughout the irrigation period so that any water arriving on the Appellees’ property remains there until (1) it is used by the Appellees, (2) it is drained at the end of the irrigation period, or (3) if the water level in the slough is too high, it runs down a tin beneath' 5900 West and reenters the slough on the Appellant’s property.

¶ 4 This process was described by Marriot in her original Application to Appropriate Water (submitted to the Utah State Water Engineer (“State Engineer”)), the Proof of Appropriation of Water (completed by the State Engineer’s office), as well as an explanatory letter from Marriot to the State Engineer. Marriot originally applied for a flow of 1 cfs but stated in her application that “it is not probable that a continuous flow of one [cfs] can be obtained, but it is the intention of the appropriator to pump as much as possible at a time and then resting [sic] untill [sic] the slough fills again.” It takes at least one day to pump the water out of the slough and at least two more days for the slough to refill. Because of this process, the flow is inconsistent; the flow decreases as the slough fills. The State Engineer’s office measured an average flow of 0.53 cfs and, as a result, authorized the appropriation at 0.5 cfs. No flow measurements have been taken other than those by the State Engineer while *1149 considering approval of Marriot’s 1914 application.

¶ 5 Appellant does not own a water right, but rather owns shares in an irrigation company, known as the Knight Irrigation Company, and irrigates using the water from a diversion point south of the separation tin. Appellant constructed a dike across the slough in 1998, without State Engineer approval. Later, Appellant consulted the Army Corps of Engineers, which granted a permit for the dike and instructed Appellant to place two pipes into the dike. Appellant complied by installing one pipe 36 inches in diameter and one 15 inches in diameter. Two witnesses at trial testified that Appellant intended to impound water with the dike. Accordingly, Appellees claim (and the trial court found) that the dike impedes the flow through the slough, requiring a significant build-up of water in the slough before water will flow through the dike and into the slough on Appellees’ property.

¶ 6 In 2000, Appellees paid to have the slough on their property dredged so that water would flow more freely. Though temporarily stopped, dredging was completed after the Army Corp of Engineers approved the process. Appellant did not allow any dredging on his property.

¶ 7 Appellees brought suit in 2001, claiming interference with their water right. The action included claims and counterclaims of trespass, nuisance, and negligence. Following two motions by Appellant for summary judgment, which the trial court denied, the case was tried in November 2003. The trial court decided the case in favor of Appellees, finding interference with Appellees’ water right, and ordered Appellant’s dike modified to allow unrestricted flow. The court also permanently enjoined Appellant from farther interference. After several overruled objections, the court entered final judgment in May 2005. Appellant now appeals.

ANALYSIS

¶ 8 The two questions presented to us on appeal are (1) whether the evidence at trial supports the trial court’s final judgment findings and (2) whether summary judgment was properly denied. Additionally, several subsidiary issues are raised, including whether Appellees can supplement additional water to their appropriated water right, whether the trial court correctly found that the flow of the Marriott Slough is “generally south to north,” and whether Appellees are limited by their water right to a duty of only three acre-feet. Because we conclude that the trial court’s findings of interference were adequately supported by the evidence, we need not, and therefore do not, reach the subsidiary issues raised by Appellant. These subsidiary issues do not alter our conclusion with respect to the trial court’s action. We therefore address only the two central issues, namely, the trial court’s (1) final judgment findings and (2) denial of summary judgment.

I. REVIEW OF THE EVIDENTIARY SUPPORT FOR THE TRIAL COURT’S FINDINGS

¶ 9 Appellant first contends that the trial court’s final judgment finding interference is unsupported by the evidence. A determination of interference, much like one of impairment, is best viewed as a mixed question of fact and law. The trial court must first find facts regarding the claim of interference and then determine whether those facts are within the ambit of interference as applied to the water right at issue. 1 When reviewing a mixed question of fact and law, we typically grant some level of deference to the trial court’s application of law to the facts. 2 In this instance, because the issue of interference is extremely fact dependent, we grant broad deference to the trial court. 3 In addition, when appealing a highly fact dependent issue, the appellant has a *1150 duty to marshal the evidence. 4 This duty requires an appellant to marshal all of the facts used to support the trial court’s finding and then show that these facts cannot possibly support the conclusion reached by the trial court, even when viewed in the light most favorable to the appellee. 5 An appellant may not simply cite to the evidence which supports his or her position and hope to prevail. 6 Furthermore, fading to properly marshal is sufficient ground for affirming the trial court’s finding. 7 We will review the trial court’s findings and Appellant’s marshaled evidence.

A. The Pumping and Refilling Cycle

¶ 10 Appellant argues that the only evidence of interference is in relation to the flow, rather than the amount, of Appellees’ water right.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Second Big Springs v. Granite Peak
2023 UT App 22 (Court of Appeals of Utah, 2023)
Arave v. Pineview West Water Company
2020 UT 67 (Utah Supreme Court, 2020)
Rocky Ford v. Kents Lake
2020 UT 47 (Utah Supreme Court, 2020)
Camco Constr. Inc. v. Utah Baseball Acad. Inc.
2018 UT App 78 (Court of Appeals of Utah, 2018)
Veysey v. Nelson
2017 UT App 77 (Court of Appeals of Utah, 2017)
Bresee v. Barton
2016 UT App 220 (Court of Appeals of Utah, 2016)
Veysey v. Veysey
2014 UT App 264 (Court of Appeals of Utah, 2014)
Kerr v. City of Salt Lake
2013 UT 75 (Utah Supreme Court, 2013)
Skypark Airport Ass'n v. Jensen
2013 UT App 229 (Court of Appeals of Utah, 2013)
ASC Utah v. Wolf Mountain
2013 UT 24 (Utah Supreme Court, 2013)
ASC Utah, Inc. v. Wolf Mountain Resorts, L.C.
2013 UT 24 (Utah Supreme Court, 2013)
Pintar v. Houck
2011 UT App 304 (Court of Appeals of Utah, 2011)
Bingham v. Roosevelt City Corp.
2010 UT 37 (Utah Supreme Court, 2010)
Normandeau v. Hanson Equipment, Inc.
2009 UT 44 (Utah Supreme Court, 2009)
Davis v. Young
2008 UT App 246 (Court of Appeals of Utah, 2008)
Kendall Insurance, Inc. v. R & R GROUP, INC.
2008 UT App 235 (Court of Appeals of Utah, 2008)
Utah County v. Butler
2008 UT 12 (Utah Supreme Court, 2008)
Normandeau v. HANSON EQUIPMENT, INC.
2007 UT App 382 (Court of Appeals of Utah, 2007)
Questar Gas Com. v. Pub. Ser. Com.
2007 UT 79 (Utah Supreme Court, 2007)
In Re Questar Gas Co.
2007 UT 79 (Utah Supreme Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2006 UT 56, 144 P.3d 1147, 561 Utah Adv. Rep. 37, 2006 Utah LEXIS 152, 2006 WL 2788975, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wayment-v-howard-utah-2006.