Camco Constr. Inc. v. Utah Baseball Acad. Inc.

2018 UT App 78, 424 P.3d 1154
CourtCourt of Appeals of Utah
DecidedApril 26, 2018
Docket20150932-CA
StatusPublished
Cited by7 cases

This text of 2018 UT App 78 (Camco Constr. Inc. v. Utah Baseball Acad. Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Camco Constr. Inc. v. Utah Baseball Acad. Inc., 2018 UT App 78, 424 P.3d 1154 (Utah Ct. App. 2018).

Opinion

MORTENSEN, Judge:

¶1 When the bank that funded the construction of an athletic facility balked at advancing more funds for the project, the owner of the facility cried foul. Several years of litigation followed, culminating in a bench trial. This appeal presents the opportunity for us to review many of the calls made by the trial court leading up to and following trial. We affirm in all respects.

BACKGROUND

¶2 KeyBank National Association provided Athletic Performance Institute LLC (API) financing for a twelve-month construction project to build an indoor athletic facility, which would then convert to a twenty-year, $1.9 million loan. API planned to lease the facility to Utah Baseball Academy Inc. (UBA). Robert Keyes owned both API and UBA. Keyes and UBA guarantied the loan to API. Appellants hired Camco Construction Inc. as the general contractor in the construction of the facility. 1

¶3 While the building was meant to "accommodate multiple sports," "a floor elevation problem" resulted in the facility only being suitable for baseball. This floor elevation issue was one of many problems that arose with both the funding and construction of the facility. When API and Camco could not resolve these disputes, Camco filed a mechanic's lien and, eventually, a lawsuit against API. Camco brought KeyBank into the suit "to assert lien priority."

¶4 Throughout the construction process, API filed draw requests with KeyBank, which KeyBank would pay out of the loan. One particular draw request-Draw Request No. 6-was not immediately funded because of the mechanic's lien. This draw request became a source of conflict between API and KeyBank, and API ultimately asserted claims for damages against KeyBank.

¶5 Another source of conflict between API and KeyBank arose in the context of the payment of accrued interest on the loan. While the loan documents were silent as to how such interest was to be handled, KeyBank made interest payments starting at the beginning of the loan period. At some point, KeyBank stopped making these payments. This gave rise to another claim for damages.

¶6 The proceedings in the trial court were long and complex. API filed a third party complaint against additional entities-Sporturf and Evergreen-and the trial court eventually bifurcated the related claims. The bifurcation led the trial court, in part, to conclude that the jury waiver included in KeyBank and API's loan documents should be enforced. Thus, the trial court heard Appellants' claims against KeyBank in a bench trial.

¶7 However, not all claims were heard at the bench trial, since the trial court had disposed of several of the claims on summary judgment. One claim peripheral to this appeal centered on a $15,000 payment from Keyes to a KeyBank employee, Roger Preston. The money came from API's construction equity account. This payment was problematic for a number of reasons, and KeyBank ultimately "refunded the $15,000, plus interest, and unconditionally tendered additional interest to API."

¶8 Appellants now challenge the results of the trial.

ISSUES

¶9 The issues raised on appeal fall into four main categories. First, Appellants argue that the trial court improperly granted summary judgment to KeyBank on several of Appellants' claims. Second, they argue that the trial court erroneously granted KeyBank's motion to strike Appellants' jury demand. Third, they argue that several of the court's trial rulings were unsupported. Fourth, they argue that the trial court erred in denying their motion for a mistrial. We address these contentions in turn.

ANALYSIS

I. Summary Judgment

¶10 We review a trial court's grant of summary judgment for correctness. Overstock.com, Inc. v. SmartBargains, Inc. , 2008 UT 55 , ¶ 12, 192 P.3d 858 .

¶11 On summary judgment, the trial court disposed of several of Appellants' claims. Those claims were for intentional infliction of emotional distress (IIED), lost profits, and fraud. We conclude that the trial court properly granted summary judgment in all three respects.

A. Intentional Infliction of Emotional Distress

¶12 In Utah, a plaintiff is entitled to damages

where the defendant intentionally engaged in some conduct toward the plaintiff, (a) with the purpose of inflicting emotional distress, or, (b) where any reasonable person would have known that such would result; and his actions are of such a nature as to be considered outrageous and intolerable in that they offend against the generally accepted standards of decency and morality.

Jackson v. Brown , 904 P.2d 685 , 687-88 (Utah 1995) (citation omitted). The trial court concluded that under relevant precedent, the IIED claim that Appellants asserted could not survive as a matter of law, where they "fail[ed] to allege a distinct and palpable injury that isn't derivative of the harm to the companies." (Citing Stone Flood & Fire Restoration, Inc. v.Safeco Ins. Co. of Am. , 2011 UT 83 , ¶ 40, 268 P.3d 170 .) The court further concluded that "as a matter of law there is not an allegation of sufficiently outrageous conduct to give rise to a claim for intentional infliction of emotional distress."

¶13 Appellants brought an IIED claim for alleged behavior connected to KeyBank's failure to pay Draw Request No. 6. Appellants argue that because there were disputed facts regarding whether KeyBank "fail[ed] to fund Draw 6 in a timely manner" and "failed to cooperate with API's replacement financing," summary judgment was inappropriate and the IIED claim should have been decided at trial. But in granting summary judgment on this issue, the trial court did not find facts or even conclude that there were no disputed facts. Instead, its ruling implicitly determined that any disputed facts were immaterial. In other words, whether or not KeyBank failed to fund the draw request or cooperate with replacement financing had no bearing on the outcome of the case; what mattered is that Appellants asserted the claim on behalf of two corporate entities and a private individual, revealing that either the claim was made on behalf of a corporation or the claim was derivative of injury to a corporation. Both situations required the trial court to grant summary judgment.

¶14 To begin, Keyes's claim for IIED could not stand inasmuch as it rested on conduct directed at either API or UBA. In Stone Flood , our supreme court addressed an analogous situation. See id. ¶¶ 32-44. The court considered whether shareholders could pursue a claim for IIED that stemmed from an injury to a corporation. See

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MOUNTAIN WEST TOWING v. WEST JORDAN
Court of Appeals of Utah, 2026
Lavender v. FCOI Preserve
2025 UT App 47 (Court of Appeals of Utah, 2025)
Nassi v. Hatsis
2023 UT App 9 (Court of Appeals of Utah, 2023)
Kelly v. Timber Lakes Property
2022 UT App 23 (Court of Appeals of Utah, 2022)
Peterson v. Hyundai Motor
2021 UT App 128 (Court of Appeals of Utah, 2021)
State v. Sevastopoulos
2020 UT App 6 (Court of Appeals of Utah, 2020)
Sprague v. Avalon Care Center
2019 UT App 107 (Court of Appeals of Utah, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2018 UT App 78, 424 P.3d 1154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/camco-constr-inc-v-utah-baseball-acad-inc-utahctapp-2018.