Questar Gas Com. v. Pub. Ser. Com.

2007 UT 79, 175 P.3d 545, 588 Utah Adv. Rep. 10, 2007 Utah LEXIS 184
Utah Supreme Court·Decided October 12, 2007·No. Nos. 20060279, 20060280·Published·Cited by 7 cases

Opinion

DURRANT, Justice:

INTRODUCTION

¶ 1 The Petitioners, including Roger Ball and Claire Geddes, seek review of two orders entered by the Utah Public Service Commission (the “Commission”). The first order denied Ball and Geddes’s request to intervene in the Commission’s proceedings involving Questar Gas Company’s (“Questar”) application to recover some of the costs of operating a carbon dioxide (“C02”) processing plant. The second order approved a Gas Management Cost Stipulation (the “Stipulation”) entered into by Questar, the Committee for Consumer Services (“Consumer Services”), and the Division of Public Utilities (the “Division”) that allows partial recovery for a limited time of Questar’s C02 processing costs. We now affirm the Commission’s first order and dismiss the petition for review as to the second order.

BACKGROUND

¶2 This is the third time we have addressed issues relating to the recovery of gas management and C02 processing costs in[548] curred by Questar and its affiliates.1 We quote liberally from these previous eases in reciting the facts relevant to this case.

I. QUESTAR I

¶ 3 In 1998, Questar, a regulated public utility, entered into a contract with its unregulated affiliate, Questar Pipeline, to construct a processing plant that would reduce the CO2 in coal seam gas, otherwise known as coal bed methane (“CBM”).2 Questar Pipeline was transporting CBM in steadily increasing quantities and needed the CO2 processing plant to address safety risks to Questar customers.3 CBM has a low heat content that cannot be used safely in most homes unless special adjustments are made to appliances or C02 is first removed from the gas at a processing facility.

¶4 On November 25, 1998, Questar submitted an application to the Commission for approval of the contract and requested authorization to transfer the costs of constructing and operating the CO2 plant directly to ratepayers.4 In its December 3, 1999 order, the Commission denied Questar’s request on the basis that these costs were not the kind of expenses allowed under Utah Code section 54 — 7—12(3)(d)(i), which is known as the pass-through statute.5 The Commission also noted that Questar bears the burden of establishing the prudence of its contract with Questar Pipeline because of their affiliate relationship.6 The Commission did not address whether Questar’s decision to enter into the contract with Questar Pipeline was prudent; rather, the Commission determined that, even assuming the prudence of the contract and the reasonableness of its terms, Questar had failed to present substantial evidence that the resulting rates would be just and reasonable.7

¶ 5 In Questar Gas Company v. Public Service Commission (Questar I), we set aside the Commission’s December 3, 1999 order, holding that Questar’s ability to recover costs was not limited to the pass-through statute.8 We based our decision on the Commission’s own prior practice, noting that the Commission, when reviewing past requests for cost recovery, determined whether the resulting rates were “just, reasonable and cost justified” and whether their approval was “in the public interest.”9 Aso, based on the Commission’s finding “that it was impossible to make a [prudence] determination because the record was insufficient and could not be created,” we limited our holding to the question of the procedure Questar should have followed to recover processing costs incurred between June 1999 and August 2000.10 We remanded the case to the Commission for further consideration in accordance with the appropriate cost recovery procedure.11

II. QUESTAR II

¶ 6 On December 17, 1999, over a year before we issued Questar I, Questar filed a general rate proceeding with the Commission, which included a request under Utah Code section 54-7-12(3)(a) for interim rate relief of over $7 million annually to cover the CO2 plant operating costs.12 Questar did not, however, seek approval of its contract with Questar Pipeline.13 The Commission held a hearing to consider this request for interim rate relief and granted the request on Janu[549] ary 25, 2000.14 Consumer Services petitioned the Commission for rehearing regarding the interim rate increase, arguing that the increase was not legally proper, factually supported, or in the public interest.15 By declining to respond to Consumer Services’ request, the Commission affirmed its January 25 order.16

¶ 7 On June 2, 2000, Questar and the Division filed a stipulation that resolved between them the issues of cost recovery and rate-making treatment of gas processing costs and provided that annual CO2 plant costs in the amount of $5 million should be passed on to ratepayers.17 Although Consumer Services objected to the cost recovery stipulation, the Commission approved the stipulation on August 11, 2000.18

Free access — add to your briefcase to read the full text and ask questions with AI

Questar Gas Com. v. Pub. Ser. Com., 2007 UT 79, 175 P.3d 545, 588 Utah Adv. Rep. 10, 2007 Utah LEXIS 184 (Utah 2007).

2007 UT 79 (Questar Gas Com. v. Pub. Ser. Com.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Turner v. Staker & Parson Companies
2012 UT 30 (Utah Supreme Court, 2012)
T-Mobile USA, Inc. v. Utah State Tax Commission
2011 UT 28 (Utah Supreme Court, 2011)
TAYLOR-WEST WEBER WATER IMPROVEMENT v. Olds
2009 UT 86 (Utah Supreme Court, 2009)
Taylor-West Weber Water Improvement District v. Olds
2009 UT 86 (Utah Supreme Court, 2009)
ABCO Enterprises v. Utah State Tax Commission
2009 UT 36 (Utah Supreme Court, 2009)
Desert Power, LP v. Public Service Commission
2007 UT App 374 (Court of Appeals of Utah, 2007)