Warren Bros. Co. v. A.A.A. Pipe Cleaning Co.

601 S.W.2d 436, 1980 Tex. App. LEXIS 3431
CourtCourt of Appeals of Texas
DecidedMay 15, 1980
Docket17626
StatusPublished
Cited by13 cases

This text of 601 S.W.2d 436 (Warren Bros. Co. v. A.A.A. Pipe Cleaning Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Warren Bros. Co. v. A.A.A. Pipe Cleaning Co., 601 S.W.2d 436, 1980 Tex. App. LEXIS 3431 (Tex. Ct. App. 1980).

Opinion

PEDEN, Justice.

Warren Brothers Company, defendant below, appeals from a judgment awarding A.A.A. Pipe Cleaning Company $22,044.34 for pipe cleaning services furnished pursuant to a proposal dated March 16, 1970. A.A.A. contends that the prices charged for the labor and services were reasonable and agreed to by Warren Brothers but that $22,361.48 of such charges remain unpaid. Warren Brothers argues that the parties contracted to calculate the charges in question on a lineal foot basis rather than by the hour, as A.A.A. billed them.

Warren Brothers was under contract with the State of Texas to construct the interchange at the intersection of North Belt Boulevard and U. S. Highway 59. Because North Belt was three to four feet below ground level at that intersection, a network of pipes was installed to drain water into a wellhouse where it could be removed by a pump. A second network of pipes drained the frontage roads and the main lines of Highway 59.

On March 16, 1970, A.A.A. submitted a proposal to Warren Brothers which provided: “Furnishing Sewer Jets and a Sewer Vac to clean 18" through 48" sewer lines on North Belt Freeway job.” The job location notation on this proposal reads “North Belt Freeway.” A Warren Brothers purchase order dated March 17, 1970, describes the job as “N Belt 59,” and provides for compensation on an hourly basis plus a flat fee for cleaning the wellhouse.

Pursuant to this purchase order, A.A.A. cleaned the pipe draining into the well-house, and cleaned the wellhouse itself on April 3rd and 4th. Other pipe running from the wellhouse was cleaned for up to a week following the cleaning of the well-house.

Warren Brothers then issued a second purchase order which referred to the job as “N Belt,” and provided that A.A.A. would “Clean remainder of Storm Lines on Rt. 59N 20 cents per Lineal Foot. Minimum of Three Sewer Sets After 4-8 — 70 Per Day. 10 hrs. 6 days.” This purchase order is undated, but apparently it was issued on April 6, 1970.

William Dewey, general manager for A.A.A. in 1970, testified that between April 6th and May 9th, A.A.A. worked on the storm lines on Highway 59. Only two A.A.A. invoices, PX-7, dated April 9, and PX-8, dated April 30, refer to the April 6 purchase order. PX-7 is the only A.A.A. invoice in evidence in which charges for amounts owed by Warren Brothers are made by the lineal foot. These charges are for work performed from April 6 through April 8. All other charges on A.A.A. invoices to Warren Brothers are computed by the hour.

It is the position of Warren Brothers, supported by testimony of its former project superintendent Dale Mantooth, that all work performed by A.A.A. on Highway 59 was intended by the parties to be billed under the April 6 purchase order, on a lineal *438 foot basis. The opposing contention of A.A.A., supported by the testimony of Mr. Dewey, was that only the small sewer lines that run beneath Highway 59 were intended by the parties to be cleaned pursuant to the April 6 purchase order at the rate of 20 cents per lineal foot. A.A.A. asserts that all other work, whether performed on the North Belt or on Highway 59, was intended by the parties to be billed by the hour under the first purchase order, and that A.A.A. based its petition solely upon the agreement of Warren Brothers to the terms of that March 16 proposal.

The case was submitted to a jury on two special issues, the first of which asked the jury to find “the unpaid balance of the amount Warren Brothers Company agreed to pay to A.A.A. Pipe Cleaning Company for the work done by A.A.A. Pipe Cleaning Company for Warren Brothers Company pursuant to the contract of March 16, 1970 and purchase order B-04501 [PX-1] in 1970 as shown by the evidence.” The jury answered “$22,044.34.” In answer to the second special issue the jury found that Warren Brothers had not paid or tendered payment to A.A.A. at the agreed rate for all work done pursuant to the March 16 proposal. Judgment was entered pursuant to this verdict.

Appellant’s third point of error is:

The trial court erred in admitting in evidence the testimony of William Dewey that the second purchase order was only intended to cover cleaning small lines that ran across Highway 59 over Defendant’s objection that such testimony violated the parol evidence rule, inasmuch as the purchase order by its terms required Plaintiff to ‘Clean Remainder of storm lines on RT 59 N 20 cents per lineal foot’ and not merely the small lines running across the highway.

Dewey testified, over objection, at several points in the trial that the April 6 purchase order was intended by the parties as an agreement that A.A.A. would clean only the small sewer lines that run under Highway 59 at the rate of 20 cents per lineal foot.

Volume 2 of Ray, Texas Law of Evidence (3rd ed. 1980) Sec. 1611, at 318-320, contains the following passage concerning the application of the parol evidence rule:

If, under the foregoing principles, the instrument appears, as read in the light of the surrounding circumstances, to be intended, not as a complete and all-inclusive embodiment of the terms relating to the subject matter of the instrument, but as a professedly partial or incomplete memorial or memorandum, then it may be supplemented by proof of other oral or written terms outside the document. Such is the case . . . where the instrument is a mere skeleton note or reminder obviously not designed to be complete. Likewise the indefiniteness of the words used in the instrument has been held to show that as to such terms the parties did not intend to supersede prior agreements as to the features covered by such vague terms.

Ray points out that the Texas cases dealing with incomplete instruments “shade by imperceptible degrees into those where the use of extrinsic evidence is justified by ambiguity in some term of the instrument,” Sec. 1611, n. 27, at 320, and states in Sec. 1685, at 412, that “(p)arol evidence is admissible to explain ambiguities apparent on the face of a writing. This proposition is well established, and frequently applied . .”

The Texas Supreme Court held in Magnolia Warehouse & Storage Co. v. Davis & Blackwell, 108 Tex. 422, 195 S.W. 184, 185 (1917):

one of the exceptions to the general [parol evidence] rule is that if the written instrument itself shows to be either ambiguous or incomplete, parol testimony is admissible to show what the real contract was to the extent necessary to remove the ambiguity, and to make the contract complete in its terms which show to be incomplete. The exception to the general rule is as well settled as is the rule itself.

Where a writing is incomplete or ambiguous, parol evidence is admissible to *439 explain the writing or to assist in the ascertainment of the true intention of the parties insofar as the parol evidence does not alter or contradict any part of the written memorandum in question. 1 In Henry v. Powers, 447 S.W.2d 738, 742 (Tex.Civ.App. 1969, no writ), we stated:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
601 S.W.2d 436, 1980 Tex. App. LEXIS 3431, Counsel Stack Legal Research, https://law.counselstack.com/opinion/warren-bros-co-v-aaa-pipe-cleaning-co-texapp-1980.