Magnolia Warehouse & Storage Co. v. Davis

195 S.W. 184, 108 Tex. 422, 1917 Tex. LEXIS 104
CourtTexas Supreme Court
DecidedMay 30, 1917
DocketNo. 2521.
StatusPublished
Cited by45 cases

This text of 195 S.W. 184 (Magnolia Warehouse & Storage Co. v. Davis) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Magnolia Warehouse & Storage Co. v. Davis, 195 S.W. 184, 108 Tex. 422, 1917 Tex. LEXIS 104 (Tex. 1917).

Opinion

Mr. Justice TANTIS

delivered the opinion of the court.

This suit was instituted to recover damages for the breach of an existing contract between Davis & Blackwell, as partners, who were plaintiffs in the District Court, and the Magnolia Warehouse & Storage Company, a corporation, which was defendant in the District Court. The contract required Davis & Blackwell to excavate and move about 20,000 cubic yards of earth from a certain lot situated near Harrisburg, about four miles south of the City of Houston, upon which lot the plaintiff in error, the Magnolia Warehouse & Storage Company, desired to erect a warehouse. Davis & Blackwell, who are defendants in error here, sought to recover damages for the refusal of the plaintiff in error to permit them, in accordance with said contract, to do the excavating provided for therein, which, refusal is alleged to have resulted to them in the loss of large profits under said contract. There was a jury trial. The verdict was favorable to Davis & Blackwell, the defendants in error. Appeal was taken by the plaintiff in error from said judgment. The case on such appeal was decided by the Court of Civil Appeals for the Eighth District, which court affirmed the judgment of the District Court. A writ of error was granted by this court on the petition of the Magnolia Warehouse '& Storage Company, plaintiff in error.

*424 The original petition of the defendants in error alleged the terms of the contract, but did not allege the contract to be in writing. The plaintiff in error, in its answer, alleged that the contract was in writing, and that the defendants in error were bound by the written contract, which was quoted in said answer. By supplemental petition the defendants in error admitted the written contract, but alleged that it showed on its face that other agreements had been made by the parties to it, which were not incorporated therein, and to which the said written contract specifically referred; that the real argeement between the parties was partly in writing and partly verbal; that the plans and specifications mentioned in said contract were verbal specifications, and that article 8 of said written contract showed that the parties were contracting with reference to the removal of the earth from the place of excavation to points that had been agreed upon between them verbally, and that the contract showed upon its face that the parties had agreed upon a distance to which the dirt would have to be hauled, but said contract did not set forth the place or the distance to which the earth should be hauled by the defendants in error, on all of which questions the defendants in error were entitled to make proof of said agreements by parol testimony. The defendants in error also' alleged that prior to the execution of said contract, and at the time the plaintiff in error was asking for bids upon the work contemplated, the latter designated as one point at which to deliver the dirt, a certain gully near the said lot; and designated cars as another point of delivery, to be placed by it on the railroad track nearest to their lot upon which the remainder of said dirt was to be loaded; that the points to which the said earth was to be removed had been indicated and designated by the plaintiff in error as being on the cars and in the gully mentioned.

The trial court permitted the defendants in error to prove by parol testimony, over the objection of the plaintiff in error, that the points which were designated to which the excavated earth was to be removed was a gully adjacent to the lot, and on cars adjacent to the lot, which were to be furnished by the plaintiff* in error. Objection was(made to the introduction of this evidence, on the ground that it tended to vary, contradict, alter, add to, change and explain away the terms of said written contract by oral testimony, and that there was no allegation in the defendants in error’s petition of any accident, fraud or mutual mistake in making said written contract; for which reasons it was and is claimed that the evidence was inadmissible, and should have been excluded by the trial court.

The general rule is that parol testimony can not be received to contradict, vary, add to or subtract from the terms of a valid written contract. But one of the exceptions to the general rule is, that if .the written instrument itself shows to be either ambiguous or incomplete parol testimony is admissible to show what the real contract was to the extent necessary to remove the ambiguity, and to make the contract complete in its terms which show to be incomplete. The exception to *425 the general rule is as well settled as is the rule itself. Jones, Commentaries on Evidence, sec. 434.

We think the evidence objected to was admissible. Section 8 of the contract provides that Davis & Blackwell agree to “furnish the tools, appliances and labor necessary to excavate the earth . . . and transport the same to points that have been indicated.” This clearly indicates that the parties had agreed upon the points to which the earth should be carried. But such points are not named in the written contract.. In this respect the contract is incomplete, and parol testimony was admissible to locate these points which had been agreed upon as indicated. Again, while section 8 states that the points to which the earth is to be carried have been indicated, section 33 contradicts this statement by providing that the earth shall be hauled into ■such place as may be designated by the owner, which was the plaintiff in error. Section 8 is silent as to the location of the points for delivering the dirt, but states that the points “have been indicated,” while section 33 leaves it to the owner to designate subsequent tó the execution of the contract the location of said points. Section 30 states that “the contractor has examined the plans and the site of the work and understands the distance to which the earth will have to be hauled.” But it fails to state the distance it is to be hauled, or the points to which it is to be hauled. . This section also provides that there should be no payment for overhaul, which again indicates that the parties had agreed upon the distance the dirt should be hauled, and the points of delivery. This again shows the written contract to be incomplete in that it fails to provide for the length of the haul, or the points of delivery. Said sections 8, 33 and 30, referred to, are as follows:

“Art. 8. The contractor agrees to furnish the tools, appliances and labor necessary to excavate the earth on the west side of the property where it is proposed to build a warehouse and transport the same to points that have been indicated. It being the purpose to grade the property to a uniform and true plane. The total number of cubic yards to be moved is estimated at twenty thousand.”
' “Art. 33. In consideration of the completion of the work embraced in these plans and specifications, and in conformity with the conditions herein, the Magnolia Warehouse & Storage Company agrees to pay to the contractor 33£ cents per cubic yard for each cubic yard excavated and hauled into such place as may be designated by the owner, and 33-J cents per cubic yard for each cubic yard excavated and loaded on cars.”
“Art. 30. The grading work shall be paid for by the cubic yard excavation measurement only. Eo payment for overhaul will be allowed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Edascio, L.L.C. v. NextiraOne, L.L.C.
264 S.W.3d 786 (Court of Appeals of Texas, 2008)
Morgan Buildings & Spas, Inc. v. Humane Society of Southeast Texas
249 S.W.3d 480 (Court of Appeals of Texas, 2008)
Atlantic Lloyds Insurance Co. v. Butler
137 S.W.3d 199 (Court of Appeals of Texas, 2004)
Martin v. Ford
853 S.W.2d 680 (Court of Appeals of Texas, 1993)
Decorative Center of Houston v. Employers Casualty Co.
833 S.W.2d 257 (Court of Appeals of Texas, 1992)
Jack H. Brown & Co. v. Toys "R" US, Inc.
906 F.2d 169 (Fifth Circuit, 1990)
Landrum v. Devenport
616 S.W.2d 359 (Court of Appeals of Texas, 1981)
Warren Bros. Co. v. A.A.A. Pipe Cleaning Co.
601 S.W.2d 436 (Court of Appeals of Texas, 1980)
TM Productions, Inc. v. Nichols
542 S.W.2d 704 (Court of Appeals of Texas, 1976)
M. C. Winters, Inc. v. Cope
498 S.W.2d 484 (Court of Appeals of Texas, 1973)
Neco Engineering Co. of Texas, Inc. v. Lee
487 S.W.2d 185 (Court of Appeals of Texas, 1972)
Hardin v. James Talcott Western, Inc.
390 S.W.2d 517 (Court of Appeals of Texas, 1965)
Wooten Properties, Inc. v. Smith
368 S.W.2d 707 (Court of Appeals of Texas, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
195 S.W. 184, 108 Tex. 422, 1917 Tex. LEXIS 104, Counsel Stack Legal Research, https://law.counselstack.com/opinion/magnolia-warehouse-storage-co-v-davis-tex-1917.