Village of Fox Lake v. Aetna Casualty & Surety Co.

534 N.E.2d 133, 178 Ill. App. 3d 887, 128 Ill. Dec. 113, 1989 Ill. App. LEXIS 68
CourtAppellate Court of Illinois
DecidedJanuary 25, 1989
Docket2-88-0055
StatusPublished
Cited by39 cases

This text of 534 N.E.2d 133 (Village of Fox Lake v. Aetna Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Village of Fox Lake v. Aetna Casualty & Surety Co., 534 N.E.2d 133, 178 Ill. App. 3d 887, 128 Ill. Dec. 113, 1989 Ill. App. LEXIS 68 (Ill. Ct. App. 1989).

Opinion

PRESIDING JUSTICE UNVERZAGT

delivered the opinion of the court:

On September 28, 1981, plaintiff Village of Fox Lake (the Village) filed an action in the circuit court of Lake County against defendants Aetna Casualty & Surety Co. (Aetna) and Santucci Construction Co. (Santucci) to recover damages allegedly caused by Santucci’s breach of contract for installation of sewer and water lines in the Village and by Aetna’s breach of its performance bond obligations. The Village subsequently filed several amended complaints eventually making Angelo D. Ventrella (Ventrella) a party to the case in June 1983. In its complaint, the Village advanced several theories of recovery, all of which grew out of its claim that Santucci did not timely pay its suppliers and subcontractors.

In count I of its complaint the Village sought recovery against Aetna, as surety for Santucci, for breach of its bond obligation. Count II sought recovery of alleged out-of-pocket costs incurred by the Village from Aetna and Santucci. Count IIA asserted that certain sworn contractor’s affidavits submitted by Santucci were fraudulent and that this constituted not only an actionable tort, but also an additional breach of the contract. In count III the Village sought recovery on a third-party beneficiary theory claiming that it was a third-party beneficiary of the contract between Santucci and its surety, Aetna. Count IV sought exemplary damages occasioned by the tort of fraud allegedly committed by Ventrella as the individual who signed the contractor’s affidavits on behalf of Santucci.

Aetna filed a counterclaim against the Village and a third-party complaint against Santucci. Santucci filed a counterclaim against the Village seeking recovery for unlawful termination by the Village of the contract between the Village and Santucci. Santucci also filed a third-party complaint against the Village’s engineers, Baxter & Woodman, Inc.

Motions for summary judgment were filed by the Village, Santucci, and Aetna. The trial court, on December 16, 1986, denied the Village’s motion, granted certain portions of the summary judgment motions filed by Santucci and Aetna, and denied other portions. Among its findings, the court held that Aetna's performance bond was limited to the penal sum of its performance bond; that the Village waived the liquidated damages provision of the contract between the Village and Santucci; and that Aetna effectively reserved its rights against the Village when it began performing on its surety bond contract. The court denied summary judgment with respect to the following issues: whether Santucci’s breach of the contract was material; whether section 25(d) of the contract provided the sole remedy for the Village against Santucci; and whether the Village had a cause of action for fraud against Santucci and its agent, Angelo D. Ventrella.

Upon motions to reconsider, the court reaffirmed its denial of the Village’s motion for summary judgment while granting Aetna’s cross-motion for summary judgment and Santucci’s cross-motion for partial summary judgment.

The record reveals that on December 15, 1975, the Village entered into a contract with Santucci for the installation of sewer and water mains within the Village of Fox Lake. Santucci, as principal, and Aetna, as surety, executed a performance bond in accordance with section 1 of “An Act in relation to contractors entering into contracts for public construction” (111. Rev. Stat. 1975, ch. 29, par. 15) (the Bond for Public Works Act) and in accordance with terms of the contract between the Village and Santucci. Both the contract amount and the bond amount were $2,491,906.75. At the time the contract was executed, the Village did not have the money to pay Santucci because it had not sold general obligation bonds to finance the project. The Village refrained from issuing a notice to proceed on the project until July 1976 when it obtained sufficient money to pay Santucci.

In order for the work to proceed on the sewer and water mains, the Village was required to obtain easements from property owners so the contractor could perform its work on the private property of Village residents. Some of these easements had been obtained when the notice to proceed was issued by the Village engineers in July 1976. The original completion date for the project was July 1978. The completion date as fixed by the Village after it had granted extensions of time to Santucci was December 1978. As of either date, the Village had not procured all easements required for the completion of the work. As a result of the Village’s failure to procure these easements when the project commenced, Santucci was, from time to time, forced to stop its work on one sewer or water line and relocate its forces to another area of the project. While the failure to obtain necessary easements did not cause a complete shutdown of the work, it did result in increased costs to Santucci and delays in the completion of the work.

Santucci submitted to the Village monthly pay requests for work done during the previous month. The contractor used the funds it received from the Village for each pay request to pay its subcontractors and suppliers for work they performed for Santucci during the period covered by the request. Santucci prepared the pay estimates for approval by Baxter & Woodman, the Village’s engineers. These estimates, after approval by Baxter & Woodman, became the monthly pay requests which were then approved by the Village.

Santucci’s contract stated:

“In preparing estimates, the material delivered on the site and preparatory work done may be taken into consideration.”

On numerous occasions during preparation of its pay estimates, Santucci sought oral confirmation of its right to payment of materials delivered to and stored on the jobsite but not yet incorporated into the work. On all but one occasion, approval of these requests was refused by Baxter & Woodman. According to Santucci, these oral requests were not inserted in the written pay estimates because their rejection would have resulted in payment delays of up to 30 days on amounts due on the balance of the estimate. Santucci claimed that at the time of the receipt of the Village’s August 8, 1978, notice of termination, Santucci had approximately $62,000 in materials stored on the jobsite for which it had not been able to obtain payment.

Santucci’s contract provided, in paragraph 25(a) of the general conditions, that the contractor’s monthly program payment would be made by the 15th day of the month following submission of its approved estimate, provided that estimate was submitted before the first of the month. In Santucci’s and Aetna’s response to the Village’s motion for summary judgment, the defendants stated that the Village was 6 to 13 days late in payment to Santucci on 5 of the first 18 pay requests. The defendants claimed that the late payments, coupled with a nonpayment for on-site materials, caused Santucci continuing cash flow problems which, in turn, affected the contractor’s ability to pay suppliers as promptly as required by paragraph 27 of the general conditions of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anchor Properties, LLC v. City of Rock Island
2025 IL App (4th) 250497-U (Appellate Court of Illinois, 2025)
EFN Calumet City Properties, LLC v. City of Calumet City
2025 IL App (1st) 242106-U (Appellate Court of Illinois, 2025)
Slyce Coal Fired Pizza Co. v. Metropolitan Square Plaza, LLC
2025 IL App (1st) 221279 (Appellate Court of Illinois, 2025)
Hounen Solar, Inc v. UL LLC
N.D. Illinois, 2023
Direct Auto Insurance Co. v. O'Neal
2022 IL App (1st) 211568 (Appellate Court of Illinois, 2022)
Harleysville Insurance Co. v. Mohr Architecture, Inc.
2021 IL App (1st) 192427-U (Appellate Court of Illinois, 2021)
Wishnia v. Signature Bank
N.D. Illinois, 2019
Radiant Star Enterprises, L.L.C. v. Metropolis Condominium Ass'n
2018 IL App (1st) 171844 (Appellate Court of Illinois, 2018)
Radiant Star Enterprises, L.L.C. v. Metropolis Condominium Association
2018 IL App (1st) 171844 (Appellate Court of Illinois, 2018)
Hassebrock v. CEJA Corporation
2015 IL App (5th) 140037 (Appellate Court of Illinois, 2015)
Henderson Square Condominium Ass' v. LAB Townhomes, L.L.C.
2014 IL App (1st) 130764 (Appellate Court of Illinois, 2014)
Rohr Burg Motors, Inc. v. Kulbarsh
2014 IL App (1st) 131664 (Appellate Court of Illinois, 2014)
The Henderson Square Condominium Association v. Lab Townhouses
2014 IL App (1st) 130764 (Appellate Court of Illinois, 2014)
The Henderson Square Condominium Association v. Lab Townhouses
2014 IL App (1st) 130764 (Appellate Court of Illinois, 2014)
The Henderson Square Condominium Association v. LAB Homes, L.L.C.
2014 IL App (1st) 130764 (Appellate Court of Illinois, 2014)
Gillespie Community Unit School District No. 7 v. Wight & Co.
2014 IL 115330 (Illinois Supreme Court, 2014)
Balmoral Racing Club, Inc. v. Churchill Downs, Inc.
953 F. Supp. 2d 885 (N.D. Illinois, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
534 N.E.2d 133, 178 Ill. App. 3d 887, 128 Ill. Dec. 113, 1989 Ill. App. LEXIS 68, Counsel Stack Legal Research, https://law.counselstack.com/opinion/village-of-fox-lake-v-aetna-casualty-surety-co-illappct-1989.