Anchor Properties, LLC v. City of Rock Island

2025 IL App (4th) 250497-U
CourtAppellate Court of Illinois
DecidedDecember 3, 2025
Docket4-25-0497
StatusUnpublished

This text of 2025 IL App (4th) 250497-U (Anchor Properties, LLC v. City of Rock Island) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anchor Properties, LLC v. City of Rock Island, 2025 IL App (4th) 250497-U (Ill. Ct. App. 2025).

Opinion

NOTICE 2025 IL App (4th) 250497-U This Order was filed under FILED Supreme Court Rule 23 and is NO. 4-25-0497 December 3, 2025 not precedent except in the Carla Bender th limited circumstances allowed 4 District Appellate IN THE APPELLATE COURT under Rule 23(e)(1). Court, IL OF ILLINOIS

FOURTH DISTRICT

ANCHOR PROPERTIES, LLC, ) Appeal from the Plaintiff-Appellant, ) Circuit Court of v. ) Rock Island County THE CITY OF ROCK ISLAND, ) No. 21CH74 Defendant-Appellee. ) ) Honorable ) Richard A. Zimmer, ) Judge Presiding.

JUSTICE ZENOFF delivered the judgment of the court. Justices DeArmond and Vancil concurred in the judgment.

ORDER

¶1 Held: The appellate court affirmed the trial court’s judgment in favor of defendant in a breach of contract action where plaintiff materially breached the contract first.

¶2 Plaintiff, Anchor Properties, LLC (Anchor), filed a breach of contract action against

defendant, the City of Rock Island (City). Following a bench trial, the trial court ruled in favor of

the City. Anchor appeals, contending that the court erred in finding that Anchor breached its

agreement with the City and was therefore not entitled to specific performance or money damages

from the City. For the following reasons, we affirm.

¶3 I. BACKGROUND

¶4 On September 1, 2021, Anchor filed a complaint against the City asserting that the

City breached its contract with Anchor concerning a sewer line running underneath Anchor’s

property. Anchor alleged that the parties contracted on August 14, 2019, to protect both the City’s sewer line and Anchor’s parking lot, located on top of the sewer line. Anchor further alleged that

the expansion and contraction of the sewer line due to temperature variances damaged Anchor’s

concrete parking lot. Anchor demanded either a decree of specific performance requiring the City

to move the sewer line or money damages to repair the concrete.

¶5 The case proceeded to a bench trial on January 27, 2025. The following evidence

was presented.

¶6 Michael Edmunds, a co-owner of Anchor, testified that Anchor began construction

on its property in June 2019. At the beginning of the project, Anchor removed two and a half to

three feet of soil over the whole site. Anchor became aware of a sewer main running under the

property on July 10, 2019, after the foundation and flooring for the building had been poured. At

that time, the main was “at subgrade level,” meaning that it was essentially even with the top of

the soil.

¶7 In July 2019, Anchor reached out to Alan Fries, who was “a member of [the City’s]

community in economic development division.” Edmunds raised concerns about “freezing of the

pipe as it will not be below the frost line” and “[h]eaving and shifting of the ground and potentially

shearing of the pipe.” He asked Fries, “[I]f the pipe does freeze, break, or something else happens

that would cause the concrete in the parking lot needing to be torn out, who is responsible for the

replacement cost of that concrete?” He also asked whether the pipe should be rerouted. Edmunds

testified that he even “offered to do a cost share at some point in this at 50/50 with the City.”

However, the City refused to move the sewer main because doing so would be very expensive

($100,000 in 2025, or about $70,000 in 2019).

¶8 Fries forwarded Edmunds’s e-mail to Michael Kane, who was an assistant city

engineer at the time. Kane testified that they discussed “the depth of [the sewer line] in regards to

-2- possible freezing of the sewer main.” In an e-mail following a phone conversation between Kane

and Edmunds, Kane stated:

“If in the future it is necessary to repair the main, the City will conduct the necessary

repairs and will also repair any damage to existing driveway and parking lot

pavements necessitated by the sewer repairs.

If possible, it would be beneficial to raise grades in this section of the

parking lot at least another foot or so for protection of the pipe. However, the pipe

in this main is rated high enough to carry the proposed traffic loads. In addition, the

placement of fiber board insulation over the pipe trench would also provide an

additional layer of protection for the pipe.”

Kane clarified that by “traffic loads,” he meant that vehicles crossing the pavement would not

break the pipe and by “protection for the pipe,” he meant to protect the pipe from freezing. He

testified that additional grading and insulation would protect the pipe from freezing and prevent

temperature differentials between the pipe and the surrounding ground.

¶9 Following Kane’s e-mail to Edmunds, Anchor’s attorney drafted an “Agreement

Regarding Sewer Line” (Agreement). Edmunds e-mailed the proposed Agreement to Kane on

August 2, 2019, and asked Kane whether he was authorized to sign on the City’s behalf. Kane

testified that he gave the proposed Agreement to his supervisor, Larry Cook, who was the City’s

Public Works Department director. Cook eventually told Kane to “go ahead and sign it.” Kane

signed the Agreement and sent it back to Edmunds on August 14, 2019.

¶ 10 In relevant part, this Agreement states:

“WHEREAS, the parties intend to hereby set forth their understanding and

agreement regarding maintenance and service of the sewer line.

-3- ***

2. The City believes cleaning services are not necessary for the subject

sewer line, as the grey matter in the pipe moves with sufficient velocity it will cause

the pipe to remain clear of debris. Nonetheless, in the future, should the subject

sewer line or main require repair, the City will conduct the necessary repairs, at its

cost. Further, the City shall repair, at its cost, any damage to Anchor’s driveway

and parking lot pavement necessitated by (a) any such sewer repairs, (b) rupture of

the sewer line as a result of freezing or (c) any other occurrence related to the sewer

line or main, not caused by Anchor’s gross negligence or intentional act.

3. To the best of its ability, in accordance with its plans to construct a

building at the Anchor Property, as determined by [Anchor] in its discretion, it will

raise the grade in the area surrounding the sewer line, and place fibre [sic] board

insulation over the pipe trench.”

¶ 11 Kane explained that it was his understanding that Edmunds was concerned about

“who would be responsible for restoration of the parking *** lot, should any work have to be

performed on the sewer main.” He stated that sewer mains typically do not freeze and burst only

infrequently, but if that were to occur and a pipe required repairs, the City would sometimes have

to access private property to conduct those repairs. Kane testified that it was the City’s regular

practice to pay the cost to replace any concrete that they had to disrupt to access a pipe. He

acknowledged that he had not previously signed a contract on the City’s behalf.

¶ 12 Edmunds testified that he then “had conversations and discussions” with his general

contractor and subcontractors “in regard to the feasibility” of adding insulation and raising the

grade around the pipe. They “determined it wasn’t feasible to do that without any major revisions

-4- to the site plans and the whole project together,” especially given their “limited budget.” At that

point in August 2019, the foundation, floor, and plumbing under the floor had been completed, but

the construction on the building and parking lot had not yet begun.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Midland Hotel Corp. v. Reuben H. Donnelley Corp.
515 N.E.2d 61 (Illinois Supreme Court, 1987)
K'S Merchandise Mart, Inc. v. Northgate Ltd. Partnership
835 N.E.2d 965 (Appellate Court of Illinois, 2005)
Coleman v. Madison Two Associates
718 N.E.2d 668 (Appellate Court of Illinois, 1999)
First American Discount Corp. v. Jacobs
756 N.E.2d 273 (Appellate Court of Illinois, 2001)
William Blair & Co. v. Fi Liquidation Corp.
830 N.E.2d 760 (Appellate Court of Illinois, 2005)
Village of Fox Lake v. Aetna Casualty & Surety Co.
534 N.E.2d 133 (Appellate Court of Illinois, 1989)
Central Illinois Light Co. v. Home Insurance
821 N.E.2d 206 (Illinois Supreme Court, 2004)
Kraftco Corp. v. Koblus
274 N.E.2d 153 (Appellate Court of Illinois, 1971)
Bank One, Springfield v. Roscetti
723 N.E.2d 755 (Appellate Court of Illinois, 1999)
Penzell v. Taylor
579 N.E.2d 956 (Appellate Court of Illinois, 1991)
Thompson v. Gordon
948 N.E.2d 39 (Illinois Supreme Court, 2011)
RBS Citizens, National Ass'n v. RTG-Oak Lawn, LLC
943 N.E.2d 198 (Appellate Court of Illinois, 2011)
Wells v. State Farm Fire & Casualty Insurance Co.
2021 IL App (5th) 190460 (Appellate Court of Illinois, 2021)
Direct Auto Insurance Co. v. O'Neal
2022 IL App (1st) 211568 (Appellate Court of Illinois, 2022)
PML Development LLC v. Village of Hawthorn Woods
2023 IL 128770 (Illinois Supreme Court, 2023)
Arbogast v. Chicago Cubs Baseball Club, LLC
2021 IL App (1st) 210526 (Appellate Court of Illinois, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2025 IL App (4th) 250497-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anchor-properties-llc-v-city-of-rock-island-illappct-2025.