Victor M. Solis Underground Utility & Paving Co. v. City of Laredo

751 S.W.2d 532, 1988 Tex. App. LEXIS 1491, 1988 WL 63106
CourtCourt of Appeals of Texas
DecidedApril 20, 1988
Docket04-86-00502-CV
StatusPublished
Cited by7 cases

This text of 751 S.W.2d 532 (Victor M. Solis Underground Utility & Paving Co. v. City of Laredo) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Victor M. Solis Underground Utility & Paving Co. v. City of Laredo, 751 S.W.2d 532, 1988 Tex. App. LEXIS 1491, 1988 WL 63106 (Tex. Ct. App. 1988).

Opinions

OPINION

BUTTS, Justice.

Victor M. Solis Underground Utility and Paving Co., Inc. and Victor M. Solis, individually, (Solis) originally sued the City of Laredo, Marvin Townsend, Amador Es-cudero, Baldmero Ortiz, Jack Van Horn, and Lockwood, Andrews and Newnam, (LAN) for breach of contract, harassment, conspiracy, tortious interference with contractual relationship, and defamation. The City of Laredo counterclaimed for breach of contract. During trial Solis dismissed, with prejudice, all causes of action against Townsend, Escudero, and Ortiz. Solis also dismissed all causes of action against the City of Laredo, except a claim for damages resulting from the City’s alleged breach of contract. The breach of contract actions were tried to the jury.

At the close of Solis’ evidence, the trial court directed verdicts in favor of appellees Jack Van Horn and LAN. The court then submitted special issues to the jury relating to Solis’ claim against the City for breach of contract. The court also submitted issues regarding the City’s counterclaim for breach of contract. Based on the jury’s findings, the court entered judgment that Solis take nothing in his breach of contract claim and further, that Solis pay the City $136,500.00 for damages in its breach of contract counterclaim and attorney’s fees.

This case stems from a contract between Solis and the City whereby Solis agreed to construct a storm sewer system known as the Mother Cabrini Project. The company began work on the project in January, 1984. After several months with continuing delays and disputes concerning the quality of the work, Van Horn, engineer-employee of LAN, the City’s consulting engineer on the project, recommended that the City order Solis to suspend work on the drainage project.

Solis obtained a temporary injunction, but that order was suspended. Solis filed for bankruptcy shortly thereafter. The City subsequently terminated the contract and completed the project using City employees. The instant suit resulted.

Solis argues in the first point of error that the trial court erred in directing a [534]*534verdict in favor of Van Horn and LAN. We disagree.

A defendant is entitled to a directed verdict only if reasonable minds cannot differ in their conclusion that the plaintiff failed to establish a cause of action against it. Jones v. Tarrant Utility Co., 638 S.W.2d 862, 865 (Tex.1982). Further, we must consider all the evidence in the light most favorable to the plaintiff, disregarding all contrary evidence and inferences.

Solis went to trial on two causes of action against Van Horn and LAN: one for tortious interference with a contractual relationship, the other for conspiracy. To establish a cause of action for tortious interference, the claimant must show (1) that the defendant maliciously interfered with a contractual relationship and (2) the defendant did so without legal justification or excuse. Sakowitz v. Steck, 669 S.W.2d 105, 107 (Tex.1984).

The Texas Supreme Court in Massey v. Armco Steel Co., 652 S.W.2d 932 (Tex.1983), held that:

An actionable civil conspiracy is a combination by two or more persons to accomplish an unlawful purpose or to accomplish a lawful purpose by unlawful means. [Citations omitted] The essential elements are: (1) two or more persons; (2) An object to be accomplished; (3) a meeting of minds on the object or course of action; (4) one or more unlawful, overt acts; and (5) damages as the proximate result.

Id. at 934.

The evidence shows that the City hired LAN with its employee, Van Horn, to serve as the project’s consulting engineer. Under its contract with the City LAN was obligated to continuously inspect the contractor’s work and report any failures of the work or materials to conform to the project specifications. The contractor was informed in its contract with the City of this duty to inspect.

Van Horn served as the project engineer for the Mother Cabrini work. He helped the City select the contractor, drafted the plans, and was responsible for overseeing the project through completion. Ortiz was City Inspector and worked as an on-site inspector under the direction of Van Horn.

Solis alleged that Van Horn and Ortiz went beyond the scope of their contract with the City and sought to prove that Van Horn conspired with Ortiz to harass appellant into breaching its contract with the City.

Solis testified that on numerous occasions Ortiz would disrupt the work at the work site. He maintained that Ortiz would hinder Solis’ ability to perform the contract. Other testimony came from Reynaldo Roberto Esparza, Ortiz’ former son-in-law. During direct examination Esparza testified:

Q: ... Did Mr. Ortiz ever tell you anything during this period of time that Mr. Van Horn said to him?
A: Mr. Ortiz told me that they had told him to put pressure on Mr. Solis. That’s what he told me.
Q: Was this at the time that the Mother Cabrini job was going on?
A: Yes.
Q: This is what — I know this is a little confusing.
This is what Mr. Ortiz told you that Mr. Van Horn had told him:
A: Yes.
Q: Did he tell you what kind of pressure?
A: Well, the way he told me, between all of them, they had a plan to put pressure on Mr. Solis so that Mr. Solis, during the project, would get angry, so he would commit something, so from there they could get a hold of him. Because their plan was that—
* * * * * *
A: So that he can be removed from the project.
* * * * * *
Q: You used the term “all of them,” Mr. Esparza. What do you mean by “all of them?” Who do you mean?
[535]*535A: Amador Escudero, Marvin Townsend, Jack Van Horn, and the other one, what’s his name?
* * * * * *

Ortiz denied any such plan existed. Moreover, since Ortiz was no longer a party to the suit, this was clearly hearsay as to Van Horn, and the objection should have been sustained. There was evidence that much of the work of Solis did not meet the plans and specifications, that Solis would not cooperate with supervisors on the job, nor even later with the supervising engineer appointed by the bankruptcy court.

Ortiz testified that Solis failed to turn in any schedule of work progress as required and that work (laid pipes) would be covered up before he could inspect it. He testified that on one occasion there was no superintendent on the project. At Van Horn’s instruction, Ortiz would send letters of notice to Solis showing the construction contract terms were not being met. He stated that as inspector he had the right “in the specifications book” to stop the work if something was wrong. Ortiz at first gave the letters of notice to Solis’ worker who in turn handed them to Solis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Holloway v. Skinner
898 S.W.2d 793 (Texas Supreme Court, 1995)
Holloway v. Skinner
860 S.W.2d 217 (Court of Appeals of Texas, 1993)
John Masek Corp. v. Davis
848 S.W.2d 170 (Court of Appeals of Texas, 1992)
Welder v. Welder
794 S.W.2d 420 (Court of Appeals of Texas, 1990)
McCartney v. Dunn & Conner, Inc.
563 A.2d 525 (Supreme Court of Pennsylvania, 1989)
Victor M. Solis Underground Utility & Paving Co. v. City of Laredo
751 S.W.2d 532 (Court of Appeals of Texas, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
751 S.W.2d 532, 1988 Tex. App. LEXIS 1491, 1988 WL 63106, Counsel Stack Legal Research, https://law.counselstack.com/opinion/victor-m-solis-underground-utility-paving-co-v-city-of-laredo-texapp-1988.