Vestar Development Ii, Llc, an Arizona Limited Liability v. General Dynamics Corporation, a Corporation

249 F.3d 958, 2001 Daily Journal DAR 4601, 2001 Cal. Daily Op. Serv. 3732, 2001 U.S. App. LEXIS 8722, 2001 WL 492344
CourtCourt of Appeals for the Ninth Circuit
DecidedMay 10, 2001
Docket99-56455
StatusPublished
Cited by188 cases

This text of 249 F.3d 958 (Vestar Development Ii, Llc, an Arizona Limited Liability v. General Dynamics Corporation, a Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vestar Development Ii, Llc, an Arizona Limited Liability v. General Dynamics Corporation, a Corporation, 249 F.3d 958, 2001 Daily Journal DAR 4601, 2001 Cal. Daily Op. Serv. 3732, 2001 U.S. App. LEXIS 8722, 2001 WL 492344 (9th Cir. 2001).

Opinion

HUG, Circuit Judge:

The prospective buyer of a parcel of property brought this action against the prospective seller for breach of an agreement to negotiate. The prospective buyer expressly did not seek reliance damages. The only damages sought by the buyer were $48,000,000 in lost profits it expected to make by constructing a shopping center on the parcel it sought to buy and leasing space to merchants. Because an agreement of sale was never reached, the terms of which would be necessary to determine lost profits, we affirm on the grounds that the only damages sought can not be proven with reasonable certainty, as required by California law. Jurisdiction is based on diversity of citizenship, and the substantive issues are governed by California law.

I. Factual Background

Defendant-Appellee General Dynamics owned a tract of land in San Diego, California, that contained approximately 240 acres. In January 1994, Plaintiff-Appellant Vestar Development II, L.L.C. (“Ves-tar”) began negotiating to purchase a 50-acre portion of that tract. On July 24, 1997, Vestar sent a Letter of Understanding (“LOU”) to General Dynamics. The LOU was signed on behalf of Vestar. At the bottom of the last page, General Dynamics’ Staff Vice President signed it “agreed.” The LOU “sets forth the proposed business terms and conditions which will provide the basis for completing a formal Purchase & Sale Agreement.” Paragraph 27 of the LOU states that General Dynamics agrees to negotiate exclusively with Vestar for ninety days. 2 In a subsequent letter dated October 20, 1997, General Dynamics sought to extend the negotiating period by sixty days. Vestar signed the letter “accepted and agreed.” At an unspecified time after October 1997, General Dynamics informed Vestar that it would be selling the entire 240-acre tract to a third party.

II. Procedural History

Vestar filed suit in California Superior Court for the County of San Diego on May 12, 1998, alleging breach of the agreement to negotiate. General Dynamics removed this diversity case to the United States District Court for the Southern District of California. The district court granted General Dynamics’ motion to dismiss on *960 the grounds that Vestar had provided no consideration.

On October 8, 1998, Vestar filed a First Amended Complaint which set forth the consideration that it had provided. General Dynamics again moved to dismiss. The district court held that Vestar alleged sufficient consideration to state a claim for breach of an agreement to negotiate. However, because the only damages sought were lost profits, the district court granted General Dynamics’ motion to dismiss. Vestar’s First Amended Complaint alleged that it had been damaged by “the inability to purchase and develop” the 50-acre parcel and sought damages in excess of $48,000,000. The district court reasoned that “[t]his amount is entirely too speculative” and that “causation is too attenuated.” “Defendant could have upheld its end of the bargain, and the sale could still have fallen through due to some intervening event, or the Parties simply could have reached an impasse.”

In response, Vestar moved for clarification and/or reconsideration. The district court denied the motion. It reasoned that Vestar could not prove damages “with reasonable certainty” as required by California law. It also noted that damages for breach of an agreement to negotiate are usually confined to reliance damages. It expressed agreement with such a rule because (1) to do otherwise would effectively transform an agreement to negotiate into a final contract, and (2) there is no way of knowing what the terms of the ultimate agreement would have been. Because Vestar was seeking only lost profits, it requested that in the event its motion was denied, the complaint be dismissed in its entirety. The district court obliged, and Vestar now appeals. We have jurisdiction over this final judgment pursuant to 28 U.S.C. § 1291.

III. Analysis

A. Standard of Review

This court reviews de novo a district court’s dismissal for failure to state a claim under Federal Rule of Civil Procedure 12(b)(6). Romano v. Bible, 169 F.3d 1182, 1185 (9th Cir.1999). We can affirm the district court’s dismissal for failure to state a claim on any basis fairly supported by the record. Id. The substantive law of California applies in this removed diversity action: Stanford Ranch, Inc. v. Maryland Cas. Co., 89 F.3d 618, 624 (9th Cir.1996). Specifically:

When interpreting state law, federal courts are bound by decisions of the state’s highest court. In the absence of such a decision, a federal court must predict how the highest state court would decide the issue using intermediate appellate court decisions, decisions from other jurisdictions, statutes, treatises, and restatements as guidance. However, where there is no convincing evidence that the state supreme court would decide differently, a federal court is obligated to follow the decisions of the state’s intermediate appellate courts.

Lewis v. Tel. Employees Credit Union, 87 F.3d 1537, 1545 (9th Cir.1996) (internal quotations and citations omitted).

B. Enforceability of Agreements to Negotiate

General Dynamics contends on appeal that the judgment may be upheld on an alternate ground that was also argued before the district court: that the agreement to negotiate is unenforceable under California law. We note the possibility that agreements to negotiate may be unenforceable as a matter of law in California. See, e.g., Beck v. Am. Health Group Int’l, Inc., 211 Cal.App.3d 1555, 1562, 260 Cal.Rptr. 237, 242 (1989); Carter v. Milestone, 170 Cal.App.2d 189, 194, 338 P.2d 569, 573 *961 (1959); Smissaert v. Chiodo, 163 Cal.App.2d 827, 831, 330 P.2d 98, 101 (1958); Forgeron Inc. v. Hansen, 149 Cal.App.2d 352, 360, 308 P.2d 406, 412 (1957); Columbia Pictures Television v. Krypton Broad. of Birmingham, Inc., 106 F.3d 284, 291 (9th Cir.1997). Significantly, all of these cases involved attempts to enforce the underlying substantive contract, and do not directly address whether an agreement to negotiate is unenforceable in its own right.

However, certain language from these cases, when taken out of context, also can be read to suggest that an agreement to negotiate in itself may not be enforceable. See, e.g., Carter,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
249 F.3d 958, 2001 Daily Journal DAR 4601, 2001 Cal. Daily Op. Serv. 3732, 2001 U.S. App. LEXIS 8722, 2001 WL 492344, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vestar-development-ii-llc-an-arizona-limited-liability-v-general-ca9-2001.