VEPCO v. Norfolk Southern Ry. Co.

683 S.E.2d 517, 278 Va. 444
CourtSupreme Court of Virginia
DecidedSeptember 18, 2009
Docket081294
StatusPublished
Cited by30 cases

This text of 683 S.E.2d 517 (VEPCO v. Norfolk Southern Ry. Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
VEPCO v. Norfolk Southern Ry. Co., 683 S.E.2d 517, 278 Va. 444 (Va. 2009).

Opinion

683 S.E.2d 517 (2009)

VIRGINIA ELECTRIC AND POWER COMPANY, et al.
v.
NORFOLK SOUTHERN RAILWAY COMPANY.

Record No. 081294.

Supreme Court of Virginia.

September 18, 2009.

*519 Anne Marie Whittemore (J. Tracy Walker IV, McGuireWoods; Everett G. Allen, Jr.; *520 Stephen M. Faraci, Sr.; LeClairRyan, on briefs), Richmond, for appellants.

Craig Thomas Merritt (Michael W. Smith; R. Braxton Hill IV; Christian & Barton, on brief), Richmond, for appellee.

Present: HASSELL, C.J., KOONTZ, KINSER, LEMONS, and MILLETTE, JJ., and RUSSELL and LACY, S.JJ.

OPINION BY Senior Justice ELIZABETH B. LACY.

This appeal arises from a contract dispute between a railway company and two utility companies over periodic cost adjustments of rates charged by the railway company for transportation of coal to an electricity generating facility in Halifax County. The principal issue we consider is whether the circuit court correctly determined that the contract in question was unambiguous in requiring the application of a specific rail cost adjustment factor for calculating quarterly adjustments to the coal transportation rates. We also consider whether the circuit court erred in striking certain affirmative defenses raised by the utilities to the railway company's claim for breach of the contract and subsequently entering a judgment of more than $77 million plus interest in favor of the railway company.

BACKGROUND

The essential facts are not in dispute. On April 5, 1989, Old Dominion Electric Cooperative ("ODEC") entered into a contract with Norfolk and Western Railway Company, the predecessor in interest to Norfolk Southern Railway Company ("Norfolk Southern"), for the regular transportation of coal to an electricity generating facility ODEC was constructing in Clover, Virginia. ODEC subsequently sold an undivided one-half interest in the Clover facility to Virginia Electric and Power Company ("VEPCO").[1]

The contract, which was styled as a "Coal Transportation Agreement" ("CTA"), addressed the transportation rates for coal deliveries to the Clover facility in Article 25, which provided in relevant part:

Unless specified otherwise, all rates and charges in this Agreement shall be subject to adjustment in accordance with this Article. Rate adjustments shall be based upon the ICC generated RCAF. During the term of this Agreement, should the RCAF described in this Agreement ... be modified or changed other than renormalizing, a new factor which closely tracks the RCAF shall be agreed to by the Parties.
....
The amount of each such adjustment shall be determined according to the applicable procedures prescribed by the ICC in Ex Parte No. 290 (Sub. No. 2) and published in Title 49 C.F.R., Part 1102, Section 1102.1 and Interstate Commerce Act, Section 10707, as may be amended, incorporated herein by reference.

The CTA defines the term "RCAF" as the Rail Cost Adjustment Factor, as "prescribed by the ICC in Ex Parte No. 290."[2] The ICC-generated RCAF refers to an index for coal transportation rates first established pursuant to Section 203 of the Staggers Rail Act of 1980. See former 49 U.S.C. § 10707a(a)(2)(B) (1980). In general, the purpose of the index was to create a calculation methodology by which rail freight delivery rates in long-term contracts could be adjusted for evolving costs and, where required to be applied, such rates would be protected from challenge as to their reasonableness. Railroad Cost Recovery Procedures-Productivity Adjustment, Ex Parte No. 290 (Sub. No. 4), 5 I.C.C. 2d 434 (1989).

Accordingly, the ICC initiated regulatory proceedings designated "Ex Parte No. 290 (Sub. No. 2)" in which it developed first an interim, and later a final, RCAF index. See *521 Railroad Cost Recovery Procedures, Ex Parte No. 290 (Sub. No. 2), 1 I.C.C. 2d 207 (1984) (establishing the final index); Railroad Cost Recovery Procedures, Ex Parte No. 290 (Sub. No. 2), 364 I.C.C. 841 (1981) (creating the interim index). The RCAF index established in Ex Parte No. 290 (Sub. No. 2) did not use rail productivity as an element of the calculation used for determining the adjustment factor for rail rates. See Railroad Cost Recovery Procedures-Productivity Adjustment, Ex Parte No. 290 (Sub. No. 4), 5 I.C.C. 2d 434 (noting that in the original rail cost adjustment factor the Commission "considered, but rejected, proposals to ... recogniz[e] the impact of improved productivity on the cost of rail outputs"). This version of RCAF became known as the Rail Cost Adjustment Factor-Unadjusted ("RCAF-U").

On March 22, 1989, the ICC adopted a modified RCAF index that was based on RCAF-U, but further adjusted that index by accounting for improvements in rail productivity. Railroad Cost Recovery Procedures-Productivity Adjustment, Ex Parte No. 290 (Sub. No. 4), 5 I.C.C. 2d 434. This cost adjustment factor became known as the Rail Cost Adjustment Factor-Adjusted ("RCAF-A"). RCAF-A was created in a separate sub-docket of Ex Parte No. 290 from RCAF-U, and modifications to RCAF-U continued independently from the calculation of RCAF-A. See, e.g., Railroad Cost Recovery Procedures, Ex Parte No. 290 (Sub. No. 2), 6 I.C.C. 2d 956 (1990) (adopting change in materials and supplies component of RCAF-U); see also Edison Electric Inst. v. ICC, 969 F.2d 1221, 1222, 1230 (D.C.Cir.1992) (holding that, although the Act neither prohibited nor required a productivity adjustment, the ICC was statutorily authorized and properly exercised its discretion to prospectively improve RCAF by a productivity adjustment).

Although RCAF-A is presently the only index permitted to be used in regulated rail transportation contracts that must apply a rate adjustment factor, Congress requires the Surface Transportation Board, the successor to the ICC, to continue to publish both the RCAF-U and RCAF-A indices, recognizing that there are contracts remaining in force that use RCAF-U and parties to unregulated contracts may continue to use RCAF-U as the basis for rate adjustment provisions if they choose to do so. See 49 U.S.C. § 10708 (2006); see also Burlington N. R.R. Co. v. Nebraska Pub. Power Dist., 931 F.Supp. 1470, 1476 (D.Neb.1996) (noting that "[t]he ICC has remained neutral about whether particular [unregulated] contracts required the use of RCAF(U) or RCAF(A)").

In the present case, the parties agree that at the time the CTA was executed, they were free to select either RCAF-U or RCAF-A to adjust the rates to be charged under the CTA. It is also not disputed that because of the differences in the method of calculating the two indices, use of RCAF-U for adjusting coal transportation rates under the CTA would result over time in significantly higher amounts being owed by the utilities to Norfolk Southern than would be owed under rates adjusted by RCAF-A.

On June 29, 1989, William B. Bales, Norfolk Southern's Vice President for Coal and Ore Traffic, sent a memorandum to ODEC detailing the quarterly rate adjustment for transportation of coal under the CTA. In each subsequent quarter thereafter through the third quarter of 2003, Bales or another Norfolk Southern executive prepared and transmitted to ODEC a similar memo detailing the adjusted coal transportation rates for the Clover facility for the upcoming quarter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mazzara v. Provencher
W.D. Texas, 2020
D'Ambrosio v. Wolf
809 S.E.2d 625 (Supreme Court of Virginia, 2018)
Mikhaylov v. Sales
784 S.E.2d 286 (Supreme Court of Virginia, 2016)
Wooten v. Bank of Am., N.A.
777 S.E.2d 848 (Supreme Court of Virginia, 2015)
Terry v. Evans (In re Evans)
527 B.R. 228 (E.D. Virginia, 2015)
Fairfax Square, L.L.C. v. Hermes of Paris, Inc.
89 Va. Cir. 406 (Fairfax County Circuit Court, 2015)
CVAS 2, LLC v. City of Fredericksburg
Supreme Court of Virginia, 2015
Harvard v. Shore Bank
89 Va. Cir. 328 (Norfolk County Circuit Court, 2014)
Tri-Port Terminals, Inc. v. Hitch Southern Branch Terminal, L.L.C.
87 Va. Cir. 314 (Chesapeake County Circuit Court, 2013)
Richard Douglas Thomas, Jr. v. Commonwealth of Virginia
742 S.E.2d 403 (Court of Appeals of Virginia, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
683 S.E.2d 517, 278 Va. 444, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vepco-v-norfolk-southern-ry-co-va-2009.