Venable's Construction, Inc v. Aspen Midstream, LLC

Texas Court of Appeals, 1st District (Houston)·Decided December 31, 2025·No. 01-24-00702-CV·Published

Opinion

Opinion issued December 31, 2025

In The

Court of Appeals

For The

First District of Texas

contract set the lump sum price at about $39 million. The contract plainly has some fixed price provisions, with phrases like “Lump Sum,” “absolute cap,” and “not in addition to the Lump Sum price.” But the contract just as plainly contains provisions for extra work, change orders, and unit prices for such additional work.

How much was Aspen required to pay Venable’s? Venable’s took the position that the project ended up requiring additional footages and efforts beyond what the $39 million lump sum contemplated, so Aspen owed it another $1.77 million. Aspen disagreed about owing the additional amount. This lawsuit followed.

On cross-motions for summary judgment, the trial court sided with Aspen.

First, the court rejected the claim for additional compensation. Second, the court agreed with Aspen that Venable’s owes a duty to defend an Aspen affiliate in a suit by some Waller County landowners who say the project left the topsoil in disarray and hurt their rice farming. We agree with Aspen about the price issue, but we disagree about the duty to defend Aspen’s own affiliate. We therefore do not reach Aspen’s conditional cross-appeal concerning objections it made to some of the summary judgment evidence filed by Venable’s.

We affirm in part, reverse in part, and remand the issue of attorney’s fees under the Declaratory Judgments Act for further proceedings.

Background

A. Contractual Relationship Between Aspen and Venable’s In 2018, Aspen decided to install a new pipeline approximately 56 miles in length from Washington County to Waller County. It sought bids from contractors and ultimately accepted the bid from Venable’s. In 2019, they signed a written “Master Construction Agreement.”

This contract calls for Venable’s to do what it calls the “Work” in exchange for a “Lump Sum,” but it does considerably more than that. The contract consists of several parts, dozens of sections, and a variety of exhibits.

Part I (“General Terms, Understandings and Obligations of the Parties”) runs 3 pages in length and says that Venable’s shall perform the Work for a Lump Sum of $39,335,430.35. Part II (“Specific Terms and Conditions”) runs 24 pages in length and has 45 sections. Part III (“Instructions and Information to Bidder”) deals with the bid process and items such as insurance. Part IV (“Contractor Firm Offer”) has two subparts:

• Subpart A, entitled “Lump Sum Price,” and • Subpart B, entitled “Special Unit Prices.”

First, the Lump Sum Price in Subpart A reiterates the $39 million figure stated earlier in the contract. Second, the Special Unit Prices in Subpart B provide prices “For Extra Work Only.” That is, in the event of “Extra Work,” the Special Unit Prices

“shall be used in the event Contractor is required to supply and install Special Unit Items during the execution of Extra Work, pursuant to a change order authorized under Section 11 of Part II of the Agreement.” Having briefly described the four parts of the contract, we will examine those parts in greater detail before beginning the legal analysis.

1. Contract: Part I Part I of the contract calls for Venable’s to perform the agreed-upon Work and for Aspen to pay Venable’s the agreed-upon price. Part 1, section 1 speaks in terms of the “Work described in Exhibit ‘A’” but does not define the Work in any further detail. Exhibit A (“Scope of Work”) appears later in the agreement.

Part I also contains a price term in section 5:

Price. As total consideration for the Work to be performed hereunder, Company shall pay Contractor a total sum of 39,335,430.35 Dollars ($39,335,430.35) (“Lump Sum”)[.] Under no circumstances shall Company be obligated to compensate Contractor beyond the Lump Sum amount set forth in this Part I, Section 5 and the Work Offer attached hereto as Exhibit F.

Section 5 continues by stating that it takes precedence over any conflicting language elsewhere in the contract: “In the event of conflict in the terms of this Part I, Section 5 and any other Part(s) or Exhibits to this Agreement, this Part I Section 5 shall control and be decisive of the issue.”

2. Contract: Part II Part II, section 1 lists definitions. It defines “Work” as follows: “‘Work’ as used herein shall mean the doing of all things described in the Scope of Work defined in Part I all in accordance with the terms, conditions, and standards of the Agreement as well as any other additional things as may be necessary to achieve the intent of this Agreement in a timely manner.”

Section 6 (“Representations and Warranties”) contains a representation by Venable’s about the price:

Contractor’s Lump Sum price, as set forth in Section 5 of Part I, is an absolute cap irrespective of any occurrence, error or omissions in drawings or specifications, post agreement increases in materials, delay for right of entry or delivery of materials, any deviations between the issued for bid and/or issued for construction drawings and specifications, hindrance or other cause known or unknown . . . in the amount it will be compensated for completion of the Work hereunder.

Venable’s further represents that “under this Lump Sum Agreement, it is assuming all risk associated with the Work and that Contractor’s costs to assume such risk are included and reflected in its Lump Sum Price.”

Section 11 (“Extra Work – Changes”) provides for additional work “which arises outside and is independent or not otherwise included in this Agreement or its scope (hereinafter referred to as ‘Extra Work’).” Extra Work “may be occasioned by major changes in design or specification regarding Work of both a materially different nature and cost from that contemplated at the time of execution of this

Agreement, or the performance of other or additional Work incident to the completion of the project or facilities here involved, but not in contemplation of the parties at the time of execution of this Agreement.”

Section 11 spells out what will not qualify as Extra Work:

Notwithstanding anything contained herein to the contrary, Contractor agrees that any change in the amount of materials or Work of any kind or character as described in Part IV Subparts A and B of this Agreement shall not constitute Extra Work and are included within and not in addition to the Lump Sum price as set forth in Part I, Section 5 of this Agreement.

Section 19 deals with indemnity. As a result, many of its provisions come in bolded capital letters to make them conspicuous, even if not especially easy to read. Among other things, this section provides that Venable’s will indemnify, defend, release, and hold harmless Aspen (plus its parent, affiliates, partners, agents, and employees) from any claims alleged to arise out of any breach of the contract by Venable’s, or any act or omission as a result of negligence or willful misconduct of Venable’s related to the agreement or the performance of the Work. It contains a promise to defend against certain lawsuits by third parties: “This indemnity includes contractor’s agreement to pay all costs and expenses of defense, including without limitation reasonable attorneys’ fees, incurred by any company indemnitee.” (Emphasis omitted.)

Section 43 (“General”) states that the agreement “contains the entire agreement between the parties and shall not be modified or supplemented except by

written instrument duly executed by both parties.” It also includes a no-waiver clause: “No waiver of any of the provisions of this Agreement shall be deemed or shall constitute a waiver of any other provisions hereof (regardless of whether similar), nor shall any such waiver constitute a continuing waiver unless otherwise expressly provided.”

3. Contract: Parts III and IV Part III deals with bid proposals, various dates, exhibits, insurance, and other administrative items.

Free access — add to your briefcase to read the full text and ask questions with AI

Venable's Construction, Inc v. Aspen Midstream, LLC, (Tex. Ct. App. 2025).

Venable's Construction, Inc v. Aspen Midstream, LLC (Venable's Construction, Inc v. Aspen Midstream, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Subaru of America, Inc. v. David McDavid Nissan, Inc.
84 S.W.3d 212 (Texas Supreme Court, 2002)
Bonham State Bank v. Beadle
907 S.W.2d 465 (Texas Supreme Court, 1995)
English v. BGP International, Inc.
174 S.W.3d 366 (Court of Appeals of Texas, 2005)
Mastec North America, Inc. v. El Paso Field Services, L.P.
317 S.W.3d 431 (Court of Appeals of Texas, 2010)
Texas Real Estate Commission v. Nagle
767 S.W.2d 691 (Texas Supreme Court, 1989)
Tschirhart v. Tschirhart
876 S.W.2d 507 (Court of Appeals of Texas, 1994)
Gulf Liquids New River Project, LLC v. Gulsby Engineering, Inc.
356 S.W.3d 54 (Court of Appeals of Texas, 2011)
City of Dallas v. Shortall
114 S.W.2d 536 (Texas Supreme Court, 1938)
Thomas Lonergan v. San Antonio Trust Co.
104 S.W. 1061 (Texas Supreme Court, 1907)
Kachina Pipeline Company, Inc. v. Michael D. Lillis
471 S.W.3d 445 (Texas Supreme Court, 2015)
Uri, Inc. v. Kleberg Cnty.
543 S.W.3d 755 (Texas Supreme Court, 2018)