Varilek v. Mitchell Engineering Co.

558 N.E.2d 365, 200 Ill. App. 3d 649, 146 Ill. Dec. 402, 1990 Ill. App. LEXIS 939
CourtAppellate Court of Illinois
DecidedJune 27, 1990
Docket1-88-2475
StatusPublished
Cited by21 cases

This text of 558 N.E.2d 365 (Varilek v. Mitchell Engineering Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Varilek v. Mitchell Engineering Co., 558 N.E.2d 365, 200 Ill. App. 3d 649, 146 Ill. Dec. 402, 1990 Ill. App. LEXIS 939 (Ill. Ct. App. 1990).

Opinion

JUSTICE RIZZI

delivered the opinion of the court:

Plaintiff brought a personal injury action against defendant Mitchell Engineering Company (Mitchell), a division of Ceco Corporation, and former defendants not involved in this appeal. Mitchell filed a third-party action against the plaintiff’s employer, Phalen Steel Erectors (Phalen). The former defendants were dismissed as a result of settlement agreements that they entered into with the plaintiff. The third-party action was dismissed as a result of a settlement agreement that was entered into between Phalen and the plaintiff. In Phalen’s settlement agreement with the plaintiff, Phalen agreed to waive its workmen’s compensation lien.

At the close of plaintiff’s case in chief, the trial court granted Mitchell’s motion for a directed verdict as to a willful and wanton count. The case went to the jury on plaintiff’s product liability count and Mitchell’s affirmative defenses of assumption of risk “and/or” misuse. The jury found in favor of plaintiff on liability and assessed his damages in the amount of $3,943,750. However, the jury also found that 63% of the plaintiff’s damages were due to assumption of risk and/or misuse. Thus, the amount of plaintiff’s damages to be recovered was reduced to $1,459,187.

Plaintiff filed a post-trial motion seeking a judgment notwithstanding the verdict for the full $3,943,750 in damages found by the jury or a new trial on damages only, or a new trial on liability and damages, and costs. Mitchell filed a post-trial motion seeking a setoff for the amount of settlements reached between plaintiff and former defendants, and seeking a setoff for the amount of the workmen’s compensation lien that was waived by Phelan in its settlement agreement with the plaintiff.

The trial court ruled that plaintiff was entitled to costs as the prevailing party. However, the trial court entered judgment in favor of plaintiff for zero damages on the basis that plaintiff’s settlement amounts with former defendants and costs exceeded the $1,459,187 that plaintiff was to recover as a result of the reduced verdict. The trial court also ruled that the waiver amount of the workmen’s compensation lien by Phalen is not to be included as part of the setoff.

Plaintiff has appealed. Plaintiff’s relevant contentions are that (1) there was no evidence of assumption of risk or misuse; (2) the trial court erred in granting Mitchell's motion in limine barring plaintiff’s expert from testifying as to inflation and real wage growth and from using actual rather than neutral numbers in computing present cash value; (3) the trial court erred in granting Mitchell’s motion for a directed verdict as to the willful and wanton count; and (4) the trial court erred in applying plaintiff's award of costs as part of the setoff. Plaintiff therefore concludes that he is entitled to a judgment notwithstanding the verdict by reinstating the totality of the damages assessed by the jury, or alternatively, to a new trial on damages only, or to a new trial on liability and damages.

Mitchell has cross-appealed as to the trial court’s ruling regarding the exclusion of the waiver amount of Phalen’s workers’ compensation lien as a setoff, and as to the trial court’s ruling regarding the propriety of awarding certain items as costs. Mitchell has not appealed the jury’s verdict as to liability on the product liability count.

We vacate the judgment entered in the trial court; enter judgment on the verdict in favor of the plaintiff and against Mitchell as to liability; enter a judgment notwithstanding the verdict in favor of plaintiff on Mitchell’s affirmative defenses of assumption of risk and misuse; vacate all setoffs and costs; grant plaintiff a new trial on damages only; and remand for a new trial on damages only.

Plaintiff, age 32, was injured on June 5, 1979. He was employed by Phalen as a journeyman ironworker and was working on the erection of a one-story, 16- to 20-foot high, prefabricated steel building, known as the Sinnissippi Saw Mill Building, located in Oregon, Illinois. The building was about 60 feet wide and 100 feet long, with a lean-to or shed that juts out as an extension of the building.

The prefabricated parts and material for the building were manufactured and sold by Mitchell as a building kit. Plaintiff had been working on the erection of the building four or five days before the accident occurred. On the day of the occurrence, the concrete floor and the metal framework for the building had already been erected. The metal roof framework consisted of beams, trusses, rafters, eave struts, purlins and wind brace rods.

The rafters are beams that are used to support the roof. They form columns which are 20 feet apart. The 20-foot space between each column is called a bay. On one side of the building, the rafters run from west to east and are pitched, rising one inch for every 12 inches, to the center line of the roof. On the other side of the building, the rafters have the same pitch but run from east to west to the center line of the roof. A shallow peak is formed where the rafters meet at the center of the building. The pitch for the roof is slight, just enough to allow rain water to run off the roof.

The eave struts are horizontal members which make up the perimeter braces for the length of the roof, and they run from north to south. An eave strut is straight iron about 20 feet long and eight inches high. Its ends are C shaped. The top of the eave strut is a ridge about four inches wide, and the bottom is a ridge about five inches wide with an upward lip at the end.

The purlins are horizontal members that are secured to the top of the rafters and run parallel with the eave struts for the entire length of the building from north to south, and are set four feet apart. A purlin is straight iron about 20 feet long and about eight inches high. It is shaped with an outward projecting flange at the top and an inward projecting flange at the bottom. The top and bottom flanges are each three inches wide.

The wind brace rods are three-eighth inch steel rods that are about 21 feet long. There are two rods for each bay. The two rods are bolted into the rafters and run diagonally, crisscrossing underneath the purlins from one rafter column to the next rafter column in each bay. The two criss-crossing rods make an X configuration underneath the purlins for each bay. The rods are “used to plum up the iron before you put up the walls and the roof.” Also, “in a nutshell, it is an attempt to make a four-cornered structure into two, three-cornered structures that are much more rigid.”

The roof for the building was in the process of being installed at the time of the occurrence. The roof consists of panels that are about three feet wide and 20 feet long. The panels are made of Galvalume, which is galvanized sheet steel, and they have vertical parallel ridges that are uniformly spaced about every 12 inches. When the panels were supplied by Mitchell, they were covered with a heavy and excessive film of oil which, according to the jury’s verdict, made the panels unreasonably dangerous for their intended use, including their installation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reese v. Conagra Foods, Inc.
2024 IL App (1st) 240315-U (Appellate Court of Illinois, 2024)
Pasillas v. Okuma American Corp.
946 F. Supp. 2d 762 (N.D. Illinois, 2013)
Country Mutual Insurance v. Sunbeam Products, Inc.
500 F. Supp. 2d 986 (N.D. Illinois, 2007)
Ettinger v. Triangle-Pacific Corp.
799 A.2d 95 (Superior Court of Pennsylvania, 2002)
Staub v. Toy Factory, Inc.
749 A.2d 522 (Superior Court of Pennsylvania, 2000)
ADM Partnership v. Martin
702 A.2d 730 (Court of Appeals of Maryland, 1997)
Wingo v. Rockford Memorial Hospital
Appellate Court of Illinois, 1997
WINGO BY WINGO v. Rockford Memorial Hosp.
686 N.E.2d 722 (Appellate Court of Illinois, 1997)
Richardson v. Chapman
676 N.E.2d 621 (Illinois Supreme Court, 1997)
Martin v. ADM Partnership
666 A.2d 876 (Court of Special Appeals of Maryland, 1995)
Arellano v. S G L Abrasives
617 N.E.2d 130 (Appellate Court of Illinois, 1993)
Cleveringa v. J.I. Case Co.
595 N.E.2d 1193 (Appellate Court of Illinois, 1992)
Freese v. Buoy
576 N.E.2d 1176 (Appellate Court of Illinois, 1991)
Corlett v. Caserta
562 N.E.2d 257 (Appellate Court of Illinois, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
558 N.E.2d 365, 200 Ill. App. 3d 649, 146 Ill. Dec. 402, 1990 Ill. App. LEXIS 939, Counsel Stack Legal Research, https://law.counselstack.com/opinion/varilek-v-mitchell-engineering-co-illappct-1990.