Van Cor, Inc. v. American Casualty Co.

208 A.2d 267, 417 Pa. 408, 1965 Pa. LEXIS 427
CourtSupreme Court of Pennsylvania
DecidedMarch 23, 1965
DocketAppeal, No. 236
StatusPublished
Cited by22 cases

This text of 208 A.2d 267 (Van Cor, Inc. v. American Casualty Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Van Cor, Inc. v. American Casualty Co., 208 A.2d 267, 417 Pa. 408, 1965 Pa. LEXIS 427 (Pa. 1965).

Opinion

Opinion

Per Curiam,

The order of the court below is affirmed on the following excerpts from the able opinion of Judge Charles Waters :

“Van Cor, Inc. [Van Cor], is successor to Daniel B. Van Campen Corporation, which contracted to perform the general construction work in the erection of a junior high school building for Marple-Newtown Joint School Authority. The authority awarded a separate contract to M. Zucker Co. [Zucker] for the electrical construction. . . . American Casualty Company of Beading, Pennsylvania [Casualty Company], was surety for [Zucker] in two bonds issued to the authority, one a ‘performance bond’ and the other a ‘labor and materialmen’s bond.’ [Zucker] encountered difficulty in the performance of its contract, and eventually went into bankruptcy and was declared in default. The uncompleted portion of the electrical work was performed by another contractor under contract with the authority, and the added expense to which the authority was thereby put over and above the original contract price for the electrical work was paid to the authority by [the Casualty Company] pursuant to the terms of its performance bond.
“The present action is brought by Van Cor, the building contractor, to recover, first, under the performance bond, damages which it claims to have suffered by reason of delays in the completion of its build[410]*410ing contract caused by [Zucker’s] failure to perform in accordance with its contract; and, second, under the labor and materialmen’s bond, for labor and material furnished by [Van Cor] to [Zucker] in the performance of its contract.
“There is no dispute of the fact that [Zucker] was in default or of the fact that the delay in completion of [Van Cor’s] contract, and the resultant loss to [Van Cor], were, in part at least, caused by [Zucker’s] faulty performance. Nor is it seriously disputed that [Van Cor] furnished to [Zucker] the labor and material forming the basis of [Van Cor’s] claim under the labor and materialmen’s bond. [The Casualty Company’s] position is, in respect of the first claim, that [its] undertaking in the performance bond does not render it answerable to other contractors for delays caused by its principal but runs only to the benefit of the school authority, the obligee; and, in respect of the second claim, that the suit is barred by the running of the one-year limitation contained in the bond and in the applicable statute, to which later reference will be made. . . .
“Giving our attention first to [Van Cor’s] claim for delay damages, we find that the cause of action on which [Van Cor] relies in its complaint is that [the Casualty Company], knowing that [Zucker] had become bankrupt and was unable to complete its contract, refused, despite demand, to perform the electrical contract promptly. I have never before heard it asserted that the surety in a performance bond is itself obligated to perform the contract of its principal. It may, of course, do so; but unless such a provision is contained in the bond the surety is not required to carry out the contract. . . . The condition of the bond in the instant case, which is the natural place to look for the nature and extent of the liability assumed by the oblig or, Com. v. Great American Indemnity Co., 312 Pa. [411]*411183, 187 (1933), is such ‘that if the said principal shall and does well and truly, in all respects, comply with all the terms, conditions and covenants contained and set forth in the aforesaid contract . . . and shall and does save harmless, protect, and indemnify the obligee, of, from and against all loss, damage and expense by reason of the principal’s failure for any cause whatsoever to comply with the aforesaid contract, . . . then this obligation shall be null and void: otherwise to be and remain in full force and effect.’ The language here is unambiguous; we cannot read into it any expansion of the obligation assumed.
“However, as the case developed at trial it became apparent that [Van Cor] was proceeding on a different theory. [Yan Cor] contends, and quite rightly, that the terms of the contract and specifications between the authority and [Zueker] became part of the bond issued by the surety. [Van Cor] contends further that paragraph 20 of the general conditions spells out the cooperation which [Zueker] was required to give to other contractors on the project; that by that paragraph other contractors, including [Van Cor], became donee beneficiaries of the contract between the authority and [Zueker]; that [the Casualty Company], having assumed the obligation to answer to the authority for its principal’s default, became liable to [Yan Cor] for [Zucker’s] failure to carry on its work with the required measure of cooperation.
“The paragraph of the electrical contract relied on by [Yan Cor], number 20, is headed ‘Cooperation,’ and from it [Yan Cor] in its complaint quotes the following sections: ‘(a) If this contract is proceeding with another, the contractor shall be responsible for any acts or omissions that interfere with the progress of the work of the other contractor or contractors. ... (c) Each contractor shall carefully examine all drawings [412]*412and specifications and carry on his work in such manner as not to interfere with or delay the work of other contractors. If any part of a contractor’s work depends upon the proper execution or results of some other contract, the former shall inspect and report in writing to the architect any defects in such work.’
“Other provisions in the contract papers are to somewhat the same effect, but need not be here stated in full.
“We are considering now the possible liability of one contractor to another arising out of such contract provisions, because I think it may safely be said that if [Zucker] were not liable at the suit of [Yan Cor], it would be futile to assert liability against the surety. [Citing] Brotherton v. Merritt-Chapman & Scott Corp., 213 F. 2d 477 (1954). . . .
“The Reed [v. Adams Steel & Wire Works, 57 Ind. App. 259, 106 N.E. 882] case contains a brief but clear statement of the law respecting third-party beneficiaries : ‘In order to entitle a person to maintain an action on a contract to which he is not a party, it must clearly appear that it was the purpose of the contract to impose an obligation on one of the contracting parties in favor of the person claiming the right of action.’
“That this is the law of Pennsylvania is clear from a reading of many of our appellate decisions, among them several which have been cited by [Van Cor]. Compare, for example, the statement found in Spires v. Hanover Fire Insurance Company, 364 Pa. 52, 56 (1950) : ‘To be a third party beneficiary entitled to recover on a contract it is not enough that it be intended by one of the parties to the contract and the third person that the latter should be a beneficiary, but loth parties to the contract must so intend and must indicate that intention in the contract; in other words, [413]*413a promisor cannot be held liable to an alleged beneficiary of a contract unless the latter was within his contemplation at the time the contract was entered into and such liability was intentionally assumed by him in his undertaking; the obligation to the third party must be created, and must affirmatively appear, in the contract itself.’ See also Burke v. North Huntingdon Township, 390 Pa.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allied Fire & Safety Equipment Co. v. Dick Enterprises, Inc.
972 F. Supp. 922 (E.D. Pennsylvania, 1997)
Knecht, Inc. v. United Pacific Insurance Company
860 F.2d 74 (Third Circuit, 1988)
Ingersoll-Rand Co. v. Insurance Co. of North America
47 Pa. D. & C.3d 444 (Bucks County Court of Common Pleas, 1987)
M.G.M. Construction Corp. v. New Jersey Educational Facilities Authority
532 A.2d 764 (New Jersey Superior Court App Division, 1987)
MGM Const. Corp. v. NJ Educ. Facilities Auth.
532 A.2d 764 (New Jersey Superior Court App Division, 1987)
Guy v. Liederbach
421 A.2d 333 (Superior Court of Pennsylvania, 1980)
General State Authority v. Sutter Corp.
403 A.2d 1022 (Commonwealth Court of Pennsylvania, 1979)
Gannon v. Baldt Anchor and Chain
459 F. Supp. 457 (E.D. Pennsylvania, 1978)
United States v. Royal Globe Indemnity Co.
435 F. Supp. 1031 (E.D. Pennsylvania, 1977)
Sharon Steel Corp. v. DeLaval Turbine, Inc.
4 Pa. D. & C.3d 325 (Mercer County Court of Common Pleas, 1977)
Pennsylvania Liquor Control Board v. Rapistan, Inc.
371 A.2d 178 (Supreme Court of Pennsylvania, 1976)
Hillbrook Apartments, Inc. v. Nyce Crete Co.
352 A.2d 148 (Superior Court of Pennsylvania, 1975)
Oliver B. Cannon & Sons, Inc. v. Dorr-Oliver Inc.
312 A.2d 322 (Superior Court of Delaware, 1973)
Line Lexington Lumber & Millwork Co. v. Pennsylvania Publishing Corp.
301 A.2d 684 (Supreme Court of Pennsylvania, 1973)
Miller v. Commercial Electric Construction, Inc.
297 A.2d 487 (Superior Court of Pennsylvania, 1972)
Fraim v. American Sanitary Sales & Services, Inc.
50 Pa. D. & C.2d 307 (Delaware County Court of Common Pleas, 1970)
Potato City, Inc. v. State Highway & Bridge Authority
45 Pa. D. & C.2d 185 (Dauphin County Court of Common Pleas, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
208 A.2d 267, 417 Pa. 408, 1965 Pa. LEXIS 427, Counsel Stack Legal Research, https://law.counselstack.com/opinion/van-cor-inc-v-american-casualty-co-pa-1965.