Ingersoll-Rand Co. v. Insurance Co. of North America

47 Pa. D. & C.3d 444, 1987 Pa. Dist. & Cnty. Dec. LEXIS 142
CourtPennsylvania Court of Common Pleas, Bucks County
DecidedOctober 8, 1987
Docketno. 85-000260-05-1
StatusPublished

This text of 47 Pa. D. & C.3d 444 (Ingersoll-Rand Co. v. Insurance Co. of North America) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Bucks County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ingersoll-Rand Co. v. Insurance Co. of North America, 47 Pa. D. & C.3d 444, 1987 Pa. Dist. & Cnty. Dec. LEXIS 142 (Pa. Super. Ct. 1987).

Opinion

GARB, P.J.,

Plaintiff has moved for summary judgment. It will be granted.

This is a suit in assumpsit initially against Insurance Company of North America as the bonding company for Mergentime Corporation. Both Mergentime and Neshaminy Water Resources Authority have been joined as additional defendants.

Mergentime was the prime contractor for the construction of the Point Pleasant Pumping Station. NWRA is the property owner. IN A furnished the performance bond. Plaintiff is a sub-contractor to Wertz Engineering Company. Wertz is a sub-contractor to Mergentime.

The chronology of events in this case is significant. The contract between Mergentime and NWRA was executed in December of 1982. Construction began on January 10, 1983. The bond in question was furnished by INA on December 9, 1982. On January 24, 1983, the contract between Mergentime and Wertz was executed. On January 27, 1983, the contract between Wertz and plaintiff was executed. That contract provided for plaintiff to manufacture and deliver the pumps to be used at the pumping station.

In February of 1983, plaintiff received the purchase order from Wertz and commenced work on the pumps and motors. On December 15, 1983, plaintiff shipped various items and submitted invoices therefor. The balance of the work was com-[446]*446pletéd for the most part by September of 1984. All of the items provided for in the contract between Wertz and plaintiff have been delivered, and there is no suggestion of any complaints with the quality of the workmanship.

The contract between Mergentime and NWRA has been identified as contract no. 60A. On September 11, 1984, a new contract was entered into between NWRA and Wertz which has been identified as contract no. 60B. This contract was entered into by virtue of the fact that Mergentime was permitted to withdraw from the project as a result of a certain contract entered into between it and NWRA. As a result of the entry of contract 60B, Wertz became the prime contractor on the project. As of October 5, 1984, Wertz had paid plaintiff the total of $558,534.70. This left a total balance on the contract between Wertz and plaintiff of $359,565.30. It is that amount which plaintiff seeks in this lawsuit.

In spite of demands made upon it, Wertz has failed to pay the aforesaid balance due and owing to plaintiff. For that reason, plaintiff now seeks compensation from INA as the insurer on the performance bond entered to guarantee the performance of Mergentime as the prime contractor on this project. INA does,not contest the fact of proper performance by plaintiff nor is there any dispute over the amount claimed. Rather, INA contends that it is not liable on its performance bond because of the substitution of contract 60B for contract 60A, asserting that it is not the insurer on the performance bond entered at the time of the entry of contract 60B. The foregoing factual contention is correct. However, we must disagree with the legal consequences flowing therefrom.

All of the foregoing facts are established on this record and, in fact, are conceded and admitted by [447]*447INA. It is well established that a summary judgment may be granted only if the pleadings, depositions, answers to interrogatories and admissions on file, together with any affidavits show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law. Toth v. Philadelphia, 213 Pa Super. 282, 247 A.2d 629 (1968). The burden of demonstrating that no genuine material issue of fact exists is on the moving party, and the record must be examined in a light most favorable to the non-moving party. Schacter v. Albert, 212 Pa. Super. 58, 239 A.2d 841 (1968). The court must accept as true all well pleaded facts in the nonmoving party’s pleadings and other proper evidence submitted in response to the motion, giving that party the benefit of all reasonable inferences to be drawn therefrom. Toth v. Philadelphia, supra. In passing upon a motion for summary judgment, the court’s function is not to decide issues of fact, but solely to determine whether there is an issue of fact to be tried. All doubts as to the existence of a genuine issue of material fact must be resolved against the moving party. Schacter v. Albert, supra. Finally, a summary judgment should be granted only when the case is clear and free from doubt. McFadden v. American Oil Company, 215 Pa. Super. 44, 257 A.2d 283 (1969), Lehnig v. Felton, 235 Pa. Super. 100, 340 A.2d 564 (1975) and Johns v. Cheeseman, 457 Pa. 414, 322 A.2d 648 (1974).

The bond filed by INA was entered pursuant to the Public Works Contractors’ Bond Law of 1967, the Act of December 20, 1967, P.L. 869, §1, 8 P.S. § 191 et seq. Therein, it is provided in 8 P.S. § 193(a) as follows:

“Before any contract exceeding $5,000 for the construction, reconstruction, alteration or repair of [448]*448any public building or other public work or public improvement, including highway work, of any contracting body is awarded to any prime contractor, such contractor shall furnish to the contracting body the following bonds, . . .

“(2) a payment bond at 100 percent of the payment amount. Such bond shall be solely for the protection of claimants supplying labor or materials to the prime contractor tc\ whom the contract was awarded, or to any of his subcontractors, in the prosecution of the work provided for in such contract, and shall be conditioned for the prompt payment of all such material furnished or labor supplied or performed in the prosecution of the work. ‘Labor or materials’ shall include public utility services and reasonable rentals of equipment, but only for periods when the equipment rented is actually used at the site.” (emphasis supplied)

It is clear that the bond was entered pursuant to this Act of Assembly. The bond specifically refers to the act. The language of the bond, in many respects, is taken directly from the Public Works Contractors’ Bond Law. Specifically, the bond provides that if the principal (Mergentime) and any subcontractor of the principal to whom any portion of the work under the contract shall be subcontracted, shall pay or shall cause to be paid in full all money which shall be due any claimant supplying “labor or materials in the prosecution and performance of the work in accordance with the contract and in accordance with the contract documents,” including any amendment, extension or addition to the contract, and/or to the contract documents for material furnished for “material furnished or labor supplied or labor performed” then the bond shall be null and void. It is further provided that the bond shall be solely “for the protection of claimants supplying la[449]*449bor or materials to the principal or to any subcontractor of the piincpal in the prosecution of the work covered by the contract, including any amendment, extension or addition to the contract.” The bond defines “claimant” as any “individual, firm, partnership, association or corporation” which is a direct quotation from the definitions section of the act.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guy v. Liederbach
459 A.2d 744 (Supreme Court of Pennsylvania, 1983)
SPIRES Et Ux. v. Hanover Fire Ins. Co.
70 A.2d 828 (Supreme Court of Pennsylvania, 1950)
Schacter v. Albert
239 A.2d 841 (Superior Court of Pennsylvania, 1968)
McFadden v. American Oil Co.
257 A.2d 283 (Superior Court of Pennsylvania, 1969)
JOHNS v. Cheeseman
322 A.2d 648 (Supreme Court of Pennsylvania, 1974)
Van Cor, Inc. v. American Casualty Co.
208 A.2d 267 (Supreme Court of Pennsylvania, 1965)
Line Lexington Lumber & Millwork Co. v. Pennsylvania Publishing Corp.
301 A.2d 684 (Supreme Court of Pennsylvania, 1973)
Toth v. Philadelphia
247 A.2d 629 (Superior Court of Pennsylvania, 1968)
Lehnig v. Felton
340 A.2d 564 (Superior Court of Pennsylvania, 1975)
Duncan-Lagnese & Associates, Inc. v. Stoney Creek Valley Sewer Authority
449 A.2d 666 (Superior Court of Pennsylvania, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
47 Pa. D. & C.3d 444, 1987 Pa. Dist. & Cnty. Dec. LEXIS 142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ingersoll-rand-co-v-insurance-co-of-north-america-pactcomplbucks-1987.