Util. L. Rep. P 14,084 Bluestone Energy Design, Inc. v. Federal Energy Regulatory Commission

74 F.3d 1288, 316 U.S. App. D.C. 27
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 30, 1996
Docket91-1288, 93-1829
StatusPublished
Cited by32 cases

This text of 74 F.3d 1288 (Util. L. Rep. P 14,084 Bluestone Energy Design, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Util. L. Rep. P 14,084 Bluestone Energy Design, Inc. v. Federal Energy Regulatory Commission, 74 F.3d 1288, 316 U.S. App. D.C. 27 (D.C. Cir. 1996).

Opinion

Opinion for the Court filed by Circuit Judge TATEL.

TATEL, Circuit Judge:

The Federal Energy Regulatory Commission cited Bluestone Energy Design, Inc. for failing to comply with safety regulations governing small hydroelectric power plants and assessed a penalty of $206,100. We affirm the Commission’s findings that Bluestone violated the relevant safety regulations. We find, however, that in determining the amount of the fine, the Commission exceeded its authority by considering the time and resources that its staff devoted to Bluestone. We therefore set aside the penalty and remand to the Commission for reconsideration of the fine.

I.

The Federal Power Act, 16 U.S.C. §§ 791a-828c (1994), authorizes the Commission to issue regulations governing hydroelectric power projects, including rules “for the protection of life, health, and property.” § 803(c). The Commission’s safety regulations for hydroelectric projects are published at 18 C.F.R. part 12. At issue in this case are three sets of regulations, subparts C and D of part 12 and paragraph 12.4(b)(2)(iv). Subpart C directs hydroelectric project operators to file with the Commission an “emergency action plan” (“EAP”) detailing steps to warn nearby inhabitants and property owners in the event of a “project emergency” such as a dam breach. 18 C.F.R. § 12.20(a), (b)(2) (1995). Project operators must update their EAPs at least once a year. § 12.24(a), (d). Subpart D requires project operators to file a report by an independent consultant (“IC”) identifying any potential deficiencies in the power project or its operation that might endanger the public. § 12.32, .37. Paragraph 12.4(b)(2)(iv) subjects hydroelectric projects to the supervision of Commission regional engineers, who may require operators to take steps deemed “necessary or desirable.”

Commission regulations permit operators of small hydroelectric projects to apply for exemptions from certain requirements of the Federal Power Act. § 4.101-.108. If an exempted project has a dam that exceeds a height of thirty-three feet, however, it must, even with an exemption, continue to file EAPs (subpart C) and IC reports (subpart D). § 4.106(h). It also remains subject to Commission supervision under paragraph 12.4(b)(2)(iv). Id. Under certain circumstances, the Commission may grant exemptions from the EAP and IC report requirements, but not from Commission supervision under paragraph 12.4(b)(2)(iv). Subpart C provides that the Commission “may exempt” a project operator from the EAP requirement if the operator “satisfactorily demonstrates that no reasonably foreseeable project emergency would endanger life, health, or property.” § 12.21(a). According to sub-part D, the Commission “may grant an exemption” from the IC report requirement “in extraordinary circumstances that clearly establish good cause for exemption.” § 12.33(a). Subpart D explains that “[gjood cause for exemption may include the finding that ... [the project’s dams] meet the criteria for low hazard potential” set out at 33 C.F.R. part 222. § 12.33(b).

In the Electric Consumers Protection Act of 1986, Congress amended the Federal Power Act to authorize the Commission to assess penalties against any operator failing to comply with Commission regulations or compliance orders. See Pub.L. No. 99-495, § 12(c) — (d), 100 Stat. 1243, 1255-57 (1986) (codified at 16 U.S.C. § 823b(c)-(d) (1994)). The Commission may assess fines up to $10,000 per day per violation. 16 U.S.C. § 823b(c).

Petitioner Bluestone Energy Design, Inc. operates a small hydroelectric dam, the Clifton No. 3 project, on the Paeolet River in Spartanburg, South Carolina. Because the dam generates only 1.1 megawatts of power, the Commission considers it a small hydroelectric project and has granted it an exemption from certain requirements of the Federal Power Act. Bluestone’s exemption, *1291 however, contains a “Special Article,” Article 6, which provides that if Bluestone’s dam exceeds a height of thirty-three feet above streambed, the project is subject to subparts C and D and to paragraph 12.4(b)(2)(iv). The requirements of Article 6 are equivalent to those of 18 C.F.R. § 4.106(h), which the Commission had not yet adopted at the time it issued Bluestone’s exemption. Because a 12.5-foot section of Bluestone’s 280-foot dam is approximately thirty-five feet high, the dam is subject to subparts C and D and to paragraph 12.4(b)(2)(iv). Four homes approximately one mile downstream from the dam are located in the flood plain. Until destroyed by fire in September 1990, a trailer home was also situated in the flood plain.

On July 3, 1986, the Commission’s Atlanta Regional Office notified Bluestone by letter that, because the presence of downstream dwellings rendered the project a “high hazard” dam, Commission regulations required Bluestone to file an EAP and an IC report. The letter advised Bluestone that it could seek an exemption from these requirements by showing through a dam breach analysis that the dam would not endanger nearby dwellings in the event of a breach. This letter began a lengthy exchange of correspondence between Bluestone and Commission officials. Because of the importance of this exchange to the issues before us, we summarize below its key events.

Receiving no response to its July 3, 1986 letter, the Atlanta Regional Office twice notified Bluestone in early 1987 that its EAP was overdue. Rather than filing an EAP, Blue-stone submitted a dam breach study purportedly demonstrating that the dam was “low hazard.” In late March, the Atlanta Regional Office reminded Bluestone, again by letter, of Bluestone’s continuing obligation to submit an EAP and an IC report. Bluestone responded with an interim EAP in May 1987, but not with an IC report.

During the following year, Commission officials notified Bluestone at least three times that it was in violation of subpart D’s IC report requirement and at least once that it was in violation of subpart C’s requirement of an updated EAP. Although Bluestone filed an updated EAP in June 1988, from then until October 1992 it failed to submit an IC report or updated EAPs as they came due. Instead, Bluestone requested numerous extensions of time and filed approximately ten more dam breach studies in an effort to gain exemptions from subparts C and D. Commission officials repeatedly informed Bluestone that it was in violation of subparts C and D and that the data it was submitting did not demonstrate that the dam was low hazard.

On June 12, 1990, Commission staff issued a compliance order finding Bluestone in violation of subparts C and D. The Commission denied Bluestone’s requests for rehearing and reconsideration, respectively, in April and June 1991. See Bluestone Energy Design, Inc., 51 F.E.R.C. ¶ 62,239 (1990) (compliance order), reh’g denied,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Battineni v. Mayorkas
District of Columbia, 2024
Kourouma v. Federal Energy Regulatory Commission
723 F.3d 274 (D.C. Circuit, 2013)
Consum Engy Co v. FERC
D.C. Circuit, 2005
Morall v. Drug Enforcement Administration
412 F.3d 165 (D.C. Circuit, 2005)
CA Dept Water Rescr v. FERC
306 F.3d 1121 (D.C. Circuit, 2002)
AR Elec Engy Consum v. FERC
D.C. Circuit, 2002
Lee's Summit v. Surface Transportation Board
231 F.3d 39 (D.C. Circuit, 2000)
Ctrl VT Pub Svc Corp v. FERC
214 F.3d 1366 (D.C. Circuit, 2000)
Wonsover v. Securities & Exchange Commission
205 F.3d 408 (D.C. Circuit, 2000)
Granholm, Jennifer M v. FERC
180 F.3d 278 (D.C. Circuit, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
74 F.3d 1288, 316 U.S. App. D.C. 27, Counsel Stack Legal Research, https://law.counselstack.com/opinion/util-l-rep-p-14084-bluestone-energy-design-inc-v-federal-energy-cadc-1996.