Consum Engy Co v. FERC

CourtCourt of Appeals for the D.C. Circuit
DecidedNovember 4, 2005
Docket03-1403
StatusPublished

This text of Consum Engy Co v. FERC (Consum Engy Co v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consum Engy Co v. FERC, (D.C. Cir. 2005).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued September 8, 2005 Decided November 4, 2005 Reissued December 23, 2005

No. 03-1403

CONSUMERS ENERGY COMPANY, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

WISCONSIN ELECTRIC POWER COMPANY, ET AL., INTERVENORS

Consolidated with 04-1252

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Deborah A. Moss argued the cause and filed the briefs for petitioner.

Patrick Y. Lee, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were Cynthia A. Marlette, General Counsel, and Dennis Lane, Solicitor. 2

Before: GINSBURG, Chief Judge, and TATEL and BROWN, Circuit Judges.

Opinion of the Court filed by Circuit Judge TATEL.

TATEL, Circuit Judge: In these consolidated cases, petitioner, a public utility, challenges two Federal Energy Regulatory Commission orders denying reimbursement for certain costs incurred in connection with the establishment of a now-defunct regional transmission organization. Finding FERC’s decisions neither arbitrary nor capricious, we deny the petitions for review.

I.

In the late 1990s, FERC began encouraging transmission- owning utilities to place their transmission facilities under the control of Regional Transmission Organizations (RTOs). In response, petitioner Consumers Energy Company (CECo), joined several other transmission-owning utilities to develop the Alliance RTO. Although FERC initially approved the Alliance companies’ development plan, it eventually rejected the plan, finding that the Alliance RTO lacked sufficient geographic scope to exist as a stand-alone entity. See Alliance Cos., 97 F.E.R.C. ¶ 61,327, 62,529-30 (2001). In that same December 2001 order, FERC found that the public interest would be better served if the Alliance companies placed their transmission facilities under the control of an already existing RTO, the Midwest Independent System Operator (MISO). See id. at 62,531. Acknowledging that the Alliance companies had incurred significant expenses in developing the Alliance RTO, FERC stated that it would consider proposals for recovery of all prudently incurred Alliance start-up costs. See id. In a later order, issued April 25, 2002, FERC clarified that it would “allow recovery of all costs prudently incurred by any Alliance 3

GridCo participant to establish an RTO once it is a member of an RTO.” Alliance Cos., 99 F.E.R.C. ¶ 61,105, 61,442 (2002). Critical to the issues before us, FERC has interpreted this “April 25 order” as imposing two requirements for recovery of “prudently incurred” Alliance costs: parties seeking reimbursement must have (1) been an Alliance GridCo participant, and (2) joined an RTO.

After FERC announced that Alliance RTO members could recover their costs, CECo sold its transmission facilities to another utility, Michigan Transco. FERC officially authorized that transaction on February 13, 2002, see Trans-Elect, Inc., 98 F.E.R.C. ¶ 61,142 (2002), but the parties subsequently amended the sales contract to account for the later-issued April 25 order. The amended contract provided that only CECo could recover the Alliance RTO costs that it incurred in connection with the transmission facilities, and that if FERC decided to reimburse Michigan Transco instead of CECo, Michigan Transco must remit the recovered funds to CECo. Michigan Transco also agreed to make reasonable efforts to help CECo obtain reimbursement. On May 1, six days after the April 25 order, CECo and Michigan Transco closed the sale. As required by the sales contract, Michigan Transco immediately transferred control of the transmission facilities to MISO.

Setting the stage for the issues now before us, MISO then requested FERC authorization to reimburse CECo approximately $8.3 million for its Alliance-related costs. FERC denied MISO’s request, explaining that because CECo had sold its transmission facilities to Michigan Transco, it had never joined an RTO as required for recovery by the April 25 order. FERC also asserted that, through the sale to Michigan Transco, CECo had received adequate compensation for its Alliance development costs. See Midwest Indep. Transmission Sys. Operator, Inc., 103 F.E.R.C. ¶ 61,219, 61,838 (2003) (the 4

“CECo order”); Midwest Indep. Transmission Sys. Operator, Inc., 104 F.E.R.C. ¶ 61,298, 62,121 (2003) (denying rehearing).

Having failed in its efforts to reimburse CECo directly, MISO asked FERC for permission to give the $8.3 million to Michigan Transco, which had a contractual obligation to pass the money along to CECo. FERC denied MISO’s request, explaining that it amounted to a collateral attack on the Commission’s earlier order denying MISO’s request to reimburse CECo, and in any event, that Michigan Transco was ineligible to recover the costs because it had never been an Alliance participant as required by the April 25 order. See Midwest Indep. Transmission Sys. Operator, Inc., 107 F.E.R.C. ¶ 61,131 (2004) (the “Michigan Transco order”); Midwest Indep. Transmission Sys. Operator, Inc., 108 F.E.R.C. ¶ 61,010 (2004) (denying rehearing).

CECo filed petitions for review of the CECo and the Michigan Transco orders. We consider both petitions in these consolidated proceedings. See Consumers Energy Co. v. FERC, No. 04-1252 (D.C. Cir. Aug. 5, 2004).

II.

We will set aside FERC’s orders only if we find them “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A). In evaluating FERC’s interpretation of its own orders, we afford the Commission substantial deference, upholding the agency’s decision “unless its interpretation is plainly erroneous or inconsistent” with the order. Bluestone Energy Design, Inc. v. FERC, 74 F.3d 1288, 1292 (D.C. Cir. 1996) (internal quotations omitted); see also CMC Real Estate Corp. v. ICC, 807 F.2d 1025, 1034 (D.C. Cir. 1986) (“It is well established that an agency’s interpretation of the intended effect of its own orders 5

is controlling unless clearly erroneous.”). Applying this highly deferential standard of review, we consider each order in turn.

The CECo Order

Although we agree with CECo that FERC provided no evidence for its assertion that CECo was “adequately compensated” for its Alliance-related costs through the sale of its transmission facilities to Michigan Transco, FERC gave an additional explanation for its decision—that CECo failed to comply with the express terms of the April 25 order—which is both well-reasoned and independent from the compensation rationale. See Greater Boston Television Corp. v. FCC, 444 F.2d 841, 851 (D.C. Cir. 1970) (stating that the court would not vacate an agency decision “because of errors that are not material”). Recall that the April 25 order states that FERC will “allow recovery of all costs prudently incurred by any Alliance GridCo participant to establish an RTO once it is a member of an RTO.” Alliance Cos., 99 F.E.R.C. at 61,442 (emphasis added). As FERC explained, because CECo had sold its transmission facilities, it had no way of becoming a member of an RTO—a prerequisite for recovery under the April 25 order.

Acknowledging that FERC’s decision comports with the April 25 order’s plain language, CECo argues that denying recovery “elevates form over substance and is contrary to [FERC’s] policy goal.” Petitioner’s Br. at 32.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Consum Engy Co v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consum-engy-co-v-ferc-cadc-2005.