Utah Power & Light Co. v. Idaho Public Utilities Commission

730 P.2d 930, 112 Idaho 10, 1986 Ida. LEXIS 539
CourtIdaho Supreme Court
DecidedNovember 26, 1986
DocketNo. 16363
StatusPublished
Cited by2 cases

This text of 730 P.2d 930 (Utah Power & Light Co. v. Idaho Public Utilities Commission) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Utah Power & Light Co. v. Idaho Public Utilities Commission, 730 P.2d 930, 112 Idaho 10, 1986 Ida. LEXIS 539 (Idaho 1986).

Opinions

HUNTLEY, Justice.

This appeal presents the issue of whether the Idaho Public Utilities Commission (IPUC) should be sustained in its entry of an order wherein it determined that, as between Utah Power & Light Co. (UP & L) and Idaho Power Co. (IPC), the latter is the appropriate utility to provide future service to the Idaho National Engineering Laboratory operated by the U.S. Department of Energy (DOE) and located near Arco, Idaho.

A synopsis of the history of electrical service to the area in question is as follows: Electrical service was first provided in the area (i.e. to the City of Arco) by UP & L in 1925. Electrical service to the Naval Proving Grounds (predecessor to DOE) was first and exclusively provided by UP & L in 1943. In 1949, UP & L signed a 100 kilowatt electrical supply contract with the Atomic Energy Commission (predecessor to DOE), with the point of delivery to be the Scoville substation, owned by DOE, in Butte County. A three-party agreement was entered into in 1950 to provide that energy, with the U.S. Atomic Energy Commission designated as “buyer,” IPC as “seller” and UP & L “a party of the second part to the extent hereinafter provided.”

[12]*12Under the three-party agreement, approved by the IPUC, both Idaho Power and Utah Power billed DOE directly for their respective services, with the funds being deposited in a “pool account” and disbursed periodically under a separate two-party agreement between the utilities. Over the past thirty-five years DOE received less than 2% of its total energy from UP & L, UP & L primarily supplying standby capacity. Since 1978, IPC has been the sole supplier of energy to DOE.

At the time the three-party agreement was entered into, the sole certificate of public convenience and necessity for electrical service to customers in Butte County rested with UP & L. That agreement provided UP & L would construct a 132 kilo-volt service line from Goshen substation (owned by UP & L) to Scoville substation (owned by DOE). This line was the sole transmission connection for power to DOE from 1950 to 1970.

In 1957, the three-party agreement was amended to provide for the increased power requirements of DOE, with those requirements being increased from 20,000 kilowatts to 40,000 kilowatts. At the same time, UP & L and IPC entered into a two-party agreement regarding the method of transmission of the power, with UP & L largely responsible for delivery.

In February 1969, IPC was also granted a certificate of convenience and necessity for Butte County, which was amended later that year (amended certificate #268) and was “limited to the transmission, interchange and supply of high voltage electric power and energy.”

In 1970, IPC, UP & L and Montana Power Company constructed the AMPS line, a 230 kilovolt transmission line. UP & L, at the same time, built Antelope substation one-half mile east of DOE’s Scoville substation, giving DOE access to power supplied by the AMPS line.

On January 30, 1985, DOE petitioned the IPUC for a declaratory ruling that IPC, rather than UP & L, has the right to be sole supplier of electricity to INEL.

Several issues are before us on appeal: Whether the IPUC had jurisdiction to decide the issues raised and whether the case presented a controversy ripe for resolution; whether the IPUC correctly rejected the Electric Supplier Stabilization Act (ESSA) (I.C. § 61-332 et seq.) as the controlling statutory scheme, and; whether the IPUC’s finding that upon termination of the agreement, IPC is entitled to be sole supplier to DOE is supported by the evidence. We deal with each issue in turn.

JURISDICTION AND RIPENESS

In an order dated May 3, 1985, the IPUC concluded that it was vested with jurisdiction over the DOE’s petition for declaratory ruling and that the petition presented a controversy ripe for resolution, although prospective in nature, as the three-party agreement had not yet been terminated. UP & L contends that the IPUC erred in so concluding as DOE had not made a definite commitment to terminate the three-party agreement.

Although Idaho public utilities law does not specifically provide for declaratory judgments, the IPUC found that the Idaho Uniform Declaratory Judgments Act applied, as that act provided “the only place to look for guidance____” The IPUC cited I.C. § 10-1203 of the Uniform Declaratory Judgments Act, which provides for the issuance of a declaratory judgment in a contract dispute “before or after there has been a breach.” Harris v. Cassia County, 106 Idaho 513, 516-517, 681 P.2d 988, 991 (1984).

The IPUC further found that “the Department of Energy’s status as an electric customer would be threatened if it exercised its right to terminate the three-party agreement [without knowledge of the result of such action].”

We agree with the analysis of the IPUC and hold that, for the reasons stated, the IPUC correctly decided that it had jurisdiction to decide the issues presented by this case and that the issue was ripe for resolution.

[13]*13THE STATUTORY SCHEME

UP & L next contends that the IPUC erred in failing to decide the controversy under the statutory scheme provided by the Electric Supplier Stabilization Act (ESSA) (I.C. § 61-332 et seq.) and, instead, finding that I.C. §§ 61-501, -526 and -528 provide the appropriate guidance and authority to the IPUC in this case. We hold that the IPUC was correct in ruling that ESSA is inapplicable to this situation.

UP & L urges that I.C. § 61-332B of the ESSA is controlling. That section provides:

61-332B. Electric supplier prohibited from serving consumers or former consumers of another supplier. — No electric supplier shall construct or extend facilities, nor make any electric connections, nor permit any connections to be made to any of its facilities for the purpose of supplying electric service nor shall it supply or furnish electric service to any electric service entrance that is then or had at any time previously been connected for electric service to facilities or another electric supplier, without the written consent of such other electric supplier; provided, however, (a) such other electric supplier is then, or was previously the last supplier, lawfully connected to said electric service entrance, and (b) such other electric supplier is well and able to provide adequate electric service.

UP & L asserts that, under this analytic scheme, UP & L is a prior supplier willing and able to adequately supply DOE and has not given consent to IPC to solely supply DOE. Accordingly, UP & L asserts, the finding of the IPUC that IPC is entitled to supply DOE upon termination of the three-party agreement is erroneous. We are not persuaded.

1.C. § 61-334(2) of the ESSA is controlling and reads:

61-334. Special rules of interpretation. — Nothing contained in this act shall be construed to:
2. Apply to controversies between two (2) or more public utilities.

UP & L would have us interpret that statute to require only that controversies exclusively between two or more public utilities not be governed by the ESSA. The language of I.C. § 61-334(2), however, speaks for itself and we must construe statutes according to their plain and obvious meanings. Hartley v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ABC Agra v. Critical Access Group
Idaho Supreme Court, 2014
ABC Agra, LLC v. Critical Access Group, Inc.
331 P.3d 523 (Idaho Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
730 P.2d 930, 112 Idaho 10, 1986 Ida. LEXIS 539, Counsel Stack Legal Research, https://law.counselstack.com/opinion/utah-power-light-co-v-idaho-public-utilities-commission-idaho-1986.