Idaho Power Co. v. Idaho Public Utilities Commission

703 P.2d 707, 108 Idaho 943, 1985 Ida. LEXIS 522
Idaho Supreme Court·Decided July 16, 1985·No. 14780·Published·Cited by 3 cases

Opinion

BISTLINE, Justice.

Idaho Power Company applied to the Idaho Public Utilities Commission (Commission) for an increase in its rates to Idaho consumers in order to produce an additional $72,941,628 in annual revenues — percentage-wise approximately 28.60 percent. Pursuant to I.C. § 61-622, the Commission suspended the requested rate increase and scheduled hearings. Briefs were submitted and hearings were held between March and July, 1982. On August 20, 1982, the Commission entered Order No. 17499 determining Idaho Power’s revenue requirement. The Commission found that the company’s revenue deficiency was $39,-444,500, approximately 15.3 percent of the rates in effect when the application was filed.

On September 9,1982, Idaho Power timely filed a petition for rehearing which focused on five areas of concern, three of which have been appealed to this Court: the excess Boardman boiler' expenses, the Valmy plant minimum operating constraints, and the 110 percent thermal blocking formula. The petition for rehearing contended that the Commission erred in its original order with respect to conclusions based on testimony and other evidence presented on these issues. The Commis *945 sion denied the petition for rehearing and Idaho Power appealed.

I. THE BOARDMAN BOILER

In the early 1970’s, Idaho Power responded to increasing demand for electrical energy by contemplating construction of a coal-fired plant known as “Pioneer.” In conjunction with the Pioneer project Idaho Power entered into a contract with the Foster Wheeler Energy Corporation for the purchase of a boiler. However, because of controversy surrounding the Pioneer Plant application, a certificate of convenience and necessity was never issued, leaving Idaho Power faced with finding an alternate use for the already purchased boiler. The company was successful in arranging to have the boiler utilized at the Boardman plant. Because the boiler had been designed for Pioneer, it was larger and stronger than necessary for the Boardman facility. 1 Hence, Idaho Power’s partners in Board-man 2 declined to pay any part of the cost differential between the Pioneer boiler cost, and the cost of an adequate boiler for the Boardman site. The difference amounted to approximately 2.3 million dollars.

All of Idaho Power’s invéstment in the Boardman plant was included in the instant rate base application. The Commission found that the excess boiler payments were not reasonably incurred because the boiler had been purchased prior to the issuance of a certificate of convenience and necessity, I.C. § 61-526, as amended in 1970.

In its petition for rehearing, Idaho Power explained the boiler was acquired without a certificate because Idaho Power deemed that sound business judgment dictated that it act swiftly to take advantage of a good price which in turn would benefit its ratepayers. On that predicate, Idaho Power contended that the boiler expenditure was reasonably incurred.

Our review of the Commission’s determination is limited by the constraints of I.C. § 61-629. The Commission’s finding that the full boiler cost was not reasonably incurred being substantiated by competent evidence, we are not at liberty to interfere. Washington Water Power v. Idaho Public Util, 101 Idaho 567, 617 P.2d 1242 (1980); Boise Water Corp. v. Idaho Public Util. Commission, 97 Idaho 832, 555 P.2d 163 (1976); Oregon Short Line R. Co. v. Public Utilities Comm., 47 Idaho 482, 276 P.2d 970 (1929). Where Idaho Power was not justified in making that expenditure, but was then able to lessen its potential loss in concluding the purchase of the boiler and then putting it to an alternate use, the Commission properly found it reasonable to compensate Idaho Power for that portion of the boiler’s cost which would equate with the cost of a boiler adequate for the Boardman plant, but any excess should not be part of the rate base. 3 As was stated in Idaho Underground Water Users Ass’n. v. Idaho Power Co., 89 Idaho 147, 161, 404 P.2d 859, 866 (1965) “property not employed in the public service should not be incorporated into the base to be used to compute the fair rate of return.” Whether utility property should be included in the rate base is a factual determination, not a legal question. Id. The excess boiler payments for a larger- *946 than-necessary boiler are similar to property not employed in public service, and the Commission committed no error in refusing to include in the rate base the total cost of the boiler purchased for the Pioneer project. 4

II. THE VALMY MINIMUM CONSTRAINTS

Valmy is a thermal plant owned jointly by Idaho Power and the Sierra Pacific Power Company. With respect to this facility Idaho Power requested the minimum generating constraint be set at 50 percent for the months of June and July. 5 The Commission rejected this request and freed Valmy from all minimum generation constraints, including the proposed 50 percent constraint for June and July. The Commission found that spinning reserves need not be maintained because Idaho Power’s operating partner, Sierra Pacific, would use Idaho Power’s share of the output when Idaho Power does not want it. The Commission concluded there was no reason to set the minimum generation constraint above zero at the. Valmy facility for any time of the year for rate-setting purposes.

In its petition for rehearing, Idaho Power argued that the Commission’s assumption that Sierra Pacific will always desire to purchase Idaho Power’s share of the Val-my output was not supported by the evidence. Idaho Power noted in its petition that Sierra Pacific had recently joined the Northwest Power Pool and Intercompany Pool, which means that Sierra Pacific has access to alternate resources in the Pacific Northwest and may not always desire Idaho Power’s share of the Valmy output, the result being that Idaho Power will have to participate in operating the Valmy facility at minimum load.

In denying Idaho Power’s petition for rehearing on the Valmy minimum constraints issue, the Commission relied upon evidence in the record supporting the original finding that spinning reserves need not be maintained at the Valmy plant. The Commission pointed to the testimony of Mr. Barclay, the Vice-President of Planning and Resources for Idaho Power, as support for its determination that a zero percent minimum constraint was supported by the evidence. 6

Free access — add to your briefcase to read the full text and ask questions with AI

Idaho Power Co. v. Idaho Public Utilities Commission, 703 P.2d 707, 108 Idaho 943, 1985 Ida. LEXIS 522 (Idaho 1985).

703 P.2d 707 (Idaho Power Co. v. Idaho Public Utilities Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Utah Power & Light Co. v. Idaho Public Utilities Commission
730 P.2d 930 (Idaho Supreme Court, 1986)
Hayden Pines Water Co. v. Idaho Public Utilities Commission
723 P.2d 875 (Idaho Supreme Court, 1986)