US FOR USE OF ENDICOTT ENT. v. Star Brite

848 F. Supp. 1161
CourtDistrict Court, D. Delaware
DecidedApril 5, 1994
DocketCiv. A. No. 92-626-JLL
StatusPublished

This text of 848 F. Supp. 1161 (US FOR USE OF ENDICOTT ENT. v. Star Brite) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
US FOR USE OF ENDICOTT ENT. v. Star Brite, 848 F. Supp. 1161 (D. Del. 1994).

Opinion

848 F.Supp. 1161 (1994)

UNITED STATES of America For the Use of ENDICOTT ENTERPRISES INC. t/a Enco, a Delaware corporation, Plaintiff,
v.
STAR BRITE CONSTRUCTION COMPANY, INCORPORATED, a New Jersey corporation, and Employers Insurance of Wausau, a Mutual Company, a Wisconsin corporation, Defendants.

Civ. A. No. 92-626-JLL.

United States District Court, D. Delaware.

April 5, 1994.

Noel E. Primos, of Schmittinger & Rodriguez, Dover, DE, for plaintiff Endicott Enterprises, Inc.

Rachel B. Mersky, of Walsh & Monzack, Wilmington, DE, and Thomas J. Hirsch, of Ocean Tp., NJ, for defendants Star Bright Const. Co. and Employers Ins. of Wausau.

*1162 FINDINGS OF FACT AND CONCLUSIONS OF LAW

LATCHUM, Senior District Judge.

I. INTRODUCTION

On October 28, 1992, the plaintiff, Endicott Enterprises, Inc., t/a Enco ("Enco"), brought this Miller Act, 40 U.S.C. §§ 270a-270d, action against defendants, Star Brite Construction Company, Inc. ("Star Brite") and Employers' Insurance of Wausau, A Mutual Company ("Wausau"), to recover amounts due for work it allegedly completed under its subcontract with Star Brite to perform the mechanical work of Star Brite's prime contract with the United States Government to renovate three airplane hangers at the Dover Air Force Base, Dover, Delaware.

Enco claims that it justifiably walked off the job because Star Brite repeatedly failed to make progress payments in accordance with the terms of its subcontract. It contends that it is entitled to damages for breach of contract.

Star Brite, conversely, contends that Enco was behind schedule and had been fully paid when it walked off the job. In addition, it claims that even if Enco had not been fully paid, it failed to give Star Brite adequate notice of its intention to do so pursuant to the subcontract. It counterclaims for damages it allegedly sustained when Enco unjustifiably stopped work.

This Court held a nonjury trial from Monday, January 10, 1994 to Thursday, January 13, 1994. After carefully considering the sufficiency and weight of the testimony adduced at trial, the demeanor of the witnesses who testified, the exhibits admitted into evidence, and the post-trial memoranda filed by the parties, the Court finds that Star Brite breached the subcontract by failing to pay Enco adequate progress payments in accordance with the terms of the subcontract and denies Star Brite its counterclaim. The Court enters the following findings of fact and conclusions of law as required by the Federal Rules of Civil Procedure, Rule 52(a).

II. FINDINGS OF FACT

1. This Court finds that Mr. Endicott, Enco's vice-president and chief witness at trial, was more credible than either Mr. Lynardakis or Mr. Smilios, Star Brite's supervisor and president, respectively, and chief witnesses at trial.

2. In late September of 1991, the United States of America ("government") and defendant Star Brite entered into three contracts whereby Star Brite agreed to perform alterations and renovations for buildings 779, 793, and 794 at the Dover Air Force Base, Dover, Delaware. (Docket Item ["D.I."] 1, ¶¶ 2, 4, 6.) The government agreed to pay Star Brite $689,920.00 for Building 779, $617,000.00 for Building 793, and $661,000.00 for Building 794. (Id.)

3. In early October of 1991 the defendant Star Brite, as principal, and defendant Wausau, as surety, executed a standard government form of payment bond to the government pursuant to the provisions of 40 U.S.C. § 270a. (Id., ¶¶ 3, 5, 7.) These bonds bound the defendants jointly and severally for $344,975.00 for Building 779, $308,500.00 for Building 793, and $330,500.00 for Building 794 if Star Brite failed to make all payments to all persons supplying labor and material for the three buildings. (Id.)

4. On January 3, 1992, Star Brite and Enco entered into a written subcontract whereby Enco was to provide all mechanical services and some mechanical materials for the three buildings. (PX 1.)[1] Under this subcontract, Star Brite was to pay progress payments on a monthly basis to ensure that Enco would have enough money to continue work on the project. (Id., Article 11.2.)

5. Star Brite was entitled to keep a 10% retainage from each progress payment. (Id.)

6. On January 13, 1992, Enco commenced work at the Dover Air Force Base. (PX 2.)

7. Enco submitted its bill to Star Brite for the work it had completed for a particular month at the end of that month or at the *1163 beginning of the next month, and payment by Star Brite was due within two to three weeks after that date. (D.I. 28, pp. 121-122; D.I. 27, pp. 5-6.)

8. For the work completed in January, Enco billed Star Brite $29,000. (PX 46.)

9. Enco experienced billing problems with Star Brite from the beginning. With respect to the January bill, Mr. Endicott testified that, "And the bill, I believe, was $29,000. They told us that we had only done $2,000 worth of work." (D.I. 26, pp. 8-9.)

10. Star Brite paid Enco for January's work with a check dated February 25, 1992, in the amount of $26,290.00. (PX 13.)

11. For work completed in February, Enco billed Star Brite $64,887.40 at the end of February or beginning of March. (PX 46.)

12. On March 17, 1992, George Lynardakis, Star Brite's supervisor, sent Enco a telegram informing them that Enco was falling behind schedule and directing Enco to correct the deficiency within 72 hours. (PX 3.)

13. Star Brite sent Enco a check dated March 27, 1992, for $32,500.00 (about one half of the amount due). (PX 14.)

14. In reply to Star Brite's March 17, 1992 letter, Enco sent a letter dated April 2, 1992, informing Star Brite that they were not behind schedule and had not been fully paid for the work they had completed. This letter warned that "[y]our blatant decrease of our invoices (which are based on the Government inspectors, Acceptance and Approval, reference Article 11.2 of the agreement) will be tolerated no further reference Article 4.7.1 of the agreement." The letter further informed Star Brite of deficiencies in Star Brite's work which impeded Enco's progress and requested a meeting. (PX 5.)

15. At the end of March or beginning of April, Enco invoiced Star Brite another $39,645.02 for the work completed in March, increasing the total amount invoiced to $133,532.42. (PX 46.)

16. In an effort to settle matters, Mr. Endicott met with Gus Poniros, who was affiliated in some way with Star Brite and was sent by Star Brite to meet with Mr. Endicott, on or about April 7, 1992. Mr. Poniros surveyed the work Enco had completed as of that date and the parties came to a settlement evidenced by six sheets of paper in Mr. Endicott's handwriting. (DX 1.) In exchange for lowering the $133,532.42 to $97,800.00, Enco received Star Brite's assurance that: (1) Star Brite would pay RE Micheals Co., a supplier, $10,000.00 on behalf of Enco the next business day; (2) Star Brite would pay Enco $25,000.00 the week of the 20th of April; and (3) the set of values breaking down the remaining $132,200.00[2] were values that Star Brite "could live with" and that Enco would be paid based on the agreed upon schedule.[3] (D.I. 26, p. 178; D.I. 28, p. 116; D.I. 29, p. 113; DX 1.)

*1164 17.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

F.E. Myers Co. v. Pipe Maintenance Services, Inc.
599 F. Supp. 697 (D. Delaware, 1984)
American General Corp. v. Continental Airlines Corp.
622 A.2d 1 (Court of Chancery of Delaware, 1992)
J. J. White, Inc. v. Metropolitan Merchandise Mart, Inc.
107 A.2d 892 (Superior Court of Delaware, 1954)
Austin Elcon Corp. v. Avco Corp.
590 F. Supp. 507 (W.D. Texas, 1984)
Reiver v. MURDOCH & WALSH, PA
625 F. Supp. 998 (D. Delaware, 1985)
Citadel Holding Corp. v. Roven
603 A.2d 818 (Supreme Court of Delaware, 1992)
Fabrizio v. Fabrizio
48 A.2d 375 (Supreme Court of Connecticut, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
848 F. Supp. 1161, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-for-use-of-endicott-ent-v-star-brite-ded-1994.