F.E. Myers Co. v. Pipe Maintenance Services, Inc.

599 F. Supp. 697, 1984 U.S. Dist. LEXIS 21443
CourtDistrict Court, D. Delaware
DecidedDecember 6, 1984
DocketCiv. A. 83-761-JLL
StatusPublished
Cited by20 cases

This text of 599 F. Supp. 697 (F.E. Myers Co. v. Pipe Maintenance Services, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
F.E. Myers Co. v. Pipe Maintenance Services, Inc., 599 F. Supp. 697, 1984 U.S. Dist. LEXIS 21443 (D. Del. 1984).

Opinion

FINDINGS OF FACTS AND CONCLUSIONS OF LAW

LATCHUM, Senior District Judge.

This action arises out of an agreement involving the purchase and sale of equipment used in the construction of a sewage disposal system at Bellevue State Park (“Bellevue”), New Castle County, Wilmington, Delaware. F.E. Myers Company (“Myers”) asserts in its complaint that Pipe Maintenance Services, Inc. (“PMS”), the general contractor responsible for installing the sewage collection project at Bellevue, agreed to purchase materials from Myers for use by PMS in connection with its construction contract with the State of Delaware, and that PMS has refused to pay for the materials specified in the contract after demand was made by Myers. Myers also claims that because defendant PMS executed as principal, and defendant Transamerica Insurance Co., executed as surety a payment bond in connection with the State of Delaware contract, the defendants, as a result of their default under the bond by failing to pay Myers, are jointly and severally liable for $31,868, the total price of the supplied materials.

In its answer PMS denies that the $31,-868 is due to Myers by reason of a counterclaim for damages of $15,777.83 because of Myers’ late performance, defective materials supplied and the wrongful refusal to warrant and guarantee the materials supplied.

*699 The case was tried to the Court without a jury on August 14, 1984.

After carefully considering the sufficiency and weight of the testimony adduced at trial, the demeanor of the witnesses who testified, the exhibits admitted into evidence and the post trial memoranda filed by the parties, the Court makes the following findings of facts and conclusions of law as required by Rule 52(a), Fed.R.Civ.P. FINDINGS OF FACTS

1. Myers is a division of McNeil Corporation, a corporation organized under the laws of the State of Ohio with its principal place of business in the State of Ohio. (Docket Item [“D.I.”] 1, 5.) PMS is a corporation organized under the laws of the Commonwealth of Pennsylvania with its principal place of business in Exton, Pennsylvania. (Id.) Transamerica Insurance Company is a corporation organized under the laws of the State of California, has its principal place of business in Philadelphia, Pennsylvania, and is authorized to do business in the State of Delaware under the Delaware Insurance Code. (Id.) The amount in controversy exceeds $10,000, exclusive of costs and interest.

2. In July of 1982, Mechem Company (“Mechem”) obtained the plans and specifications from the State of Delaware for the proposed construction of a grinder pump pressure collection system 1 at Bellevue State Park. (Tr-A at 170.) 2 Mechem, a distributor for various pump manufacturers, then submitted proposals for pump equipment to the general contractors who were planning to submit bids to the State of Delaware on the Bellevue project. (Id.)

3. On August 3, 1982, PMS was awarded the contract (No. BEL-100-1982) entitled Grinder Pump Pressure Collection System, Bellevue State Park, New Castle County, by the Department of Natural Resources and Environmental Control, Division of Parks and Recreation for the State of Delaware. (PX 1.)

4. On August 18, 1982, PMS as principal, and Transamerica Insurance Co. as surety, executed in connection with the Bellevue project a payment bond which provided that it shall be discharged upon the payment to:

“all and every person furnishing material or performing labor in and about the construction of said Project, all and every sum of money due him, them or any of them, for all such labor and materials for which the contractor is liable.”

(PX 2.)

5. Mechem then approached PMS to determine whether Mechem’s proposal was satisfactory. (Tr-A at 170.) Although PMS indicated that Mechem’s prices were favorable, inasmuch as Mechem was only the distributor 3 and not the original manufacturer, there were some questions as to specifications that needed to be answered. (Id. at 171.) Mechem had included the specifications of pumps manufactured by Myers, however, the Myers pumps, as originally designed, did not meet the specifications for the Bellevue project. 4

6. On August 20, 1982, there was a meeting among PMS, Hans C. Albertsen, as the owner of Mechem, and the representatives from the state including the engineer at Bellevue. Subsequent to that meeting, Albertsen sent a letter to Harold M. Miller of Andrews, Miller & Associates, the state engineers, in which Albertsen stated that his firm, as the local representative for F.E. Myers, could provide the five *700 grinder pumps needed for the Bellevue project. 5 (Tr-A at 102-103; DX 2.)

7. On September 7,1982, Albertsen submitted a proposal 6 to Michael Carpenter, project coordinator for PMS. (Tr-A at 35; DX 1.) The proposal, 7 Mechem’s price for five grinder pumping stations 8 and one winch unit, was for $31,869.00. 9

8. On October 1, 1982, Michael Carpenter of PMS verbally authorized Albertsen to proceed with the purchase of the grinder pumps. However, Albertsen told Carpenter that a written purchase order was needed to process the order. (Tr-A at 174.)

9. Because the Myers pumps were not the ones originally specified, the State of Delaware decided to have their consulting engineers evaluate the Mechem submission. (Tr-A at 172.) At the time of the original submission, the State did not have consulting engineers under contract because they had already done their work on the project and been paid. (Id. at 171.)

10. On October 7, 1982, Carpenter submitted the information to Steve Corazza of the Department of Natural Resources & Environmental Control for approval by the consulting engineers, Andrews, Miller & Associates. (PX 3.) Albertsen received the approved drawings dated October 13, 1982. (Id. at 197.)

11. A few days after October 21, 1982, Albertsen received a letter of approval from the consulting engineer and on October 25, 1982, PMS submitted a purchase order to Mechem for the five grinder pumps. 10 (DX 3.)

12. After Mechem received the written purchase order from PMS, Mechem submitted the approved drawings and the purchase order for the five grinder pumps to Myers. (Tr-A at 175.)

13. At the end of October, Myers was shut down three days for annual inventory. In addition, Myers experienced a major reduction in its work force due to poor business conditions during the time the equipment was being manufactured. (DX 7.) Myers, however, completed production of the equipment sometime between the middle of November and the first week of December. (Tr-A at 191, 207.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Patel v. Sunvest Realty Corporation
Superior Court of Delaware, 2018
Newcomer v. Burkholder
Superior Court of Delaware, 2016
Hornberger Management Co. v. Haws & Tingle General Contractors, Inc.
768 A.2d 983 (Superior Court of Delaware, 2000)
Reybold Group, Inc. v. Chemprobe Technologies, Inc.
721 A.2d 1267 (Supreme Court of Delaware, 1998)
S&R Associates, L.P. v. Shell Oil Co.
725 A.2d 431 (Superior Court of Delaware, 1998)
Haft v. Dart Group Corp.
877 F. Supp. 896 (D. Delaware, 1995)
US FOR USE OF ENDICOTT ENT. v. Star Brite
848 F. Supp. 1161 (D. Delaware, 1994)
Freedman v. Chrysler Corp.
564 A.2d 691 (Superior Court of Delaware, 1989)
Transportes Aereos De Angola v. Ronair, Inc.
693 F. Supp. 102 (D. Delaware, 1988)
American Original Corp. v. Legend, Inc.
689 F. Supp. 372 (D. Delaware, 1988)
Miller v. Newsweek, Inc.
675 F. Supp. 872 (D. Delaware, 1987)
DiIenno v. Libbey Glass Division, Owens-Illinois, Inc.
668 F. Supp. 373 (D. Delaware, 1987)
Neilson Business Equipment Center, Inc. v. Monteleone
524 A.2d 1172 (Supreme Court of Delaware, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
599 F. Supp. 697, 1984 U.S. Dist. LEXIS 21443, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fe-myers-co-v-pipe-maintenance-services-inc-ded-1984.