United States v. Windward Properties, Inc.

821 F. Supp. 690, 23 Envtl. L. Rep. (Envtl. Law Inst.) 21182, 1993 U.S. Dist. LEXIS 6584, 1993 WL 164089
CourtDistrict Court, N.D. Georgia
DecidedMarch 31, 1993
Docket1:91-cv-00348
StatusPublished
Cited by16 cases

This text of 821 F. Supp. 690 (United States v. Windward Properties, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Windward Properties, Inc., 821 F. Supp. 690, 23 Envtl. L. Rep. (Envtl. Law Inst.) 21182, 1993 U.S. Dist. LEXIS 6584, 1993 WL 164089 (N.D. Ga. 1993).

Opinion

ORDER

CARNES, District Judge.

This case is presently before the Court on Defendant’s Motion for Partial Summary Judgment [15], Plaintiffs Motion for Partial Summary Judgment [27], and Plaintiffs Motion to Amend Complaint [33]. The Court has reviewed the record and the arguments of the parties and, for the reasons set out below, concludes that the motion to amend should be granted and both motions for summary judgment should be denied.

*692 BACKGROUND

Plaintiff, the United States of America, brought this case as a civil enforcement action pursuant to section 309 of the Clean Water Act (“CWA”), 33 U.S.C. § 1319, seeking injunctive relief and civil penalties against Defendant, Windward Properties, Inc. (“Windward”), for five alleged violations of the CWA at Windward’s 3400 acre real estate development in Alpharetta, Georgia. All five violations involve the unpermitted discharge of dredged or fill materials into three streams at the Windward site (Caney Creek, Big Creek, and Camp Creek) and their adjacent wetlands in violation of sections 301 and 404 of the CWA, 33 U.S.C. §§ 1311 and 1344. Count I of the Complaint, which is the subject of Defendant’s current motion for summary judgment, alleges violations by Windward between 1979 and 1982 during construction of the Lake Windward Dam. (Compl. ¶¶ 8-25). 1

DISCUSSION

A. Plaintiff’s Motion to Amend

Plaintiff has moved to amend its Complaint in this action to add Mobil Land Development Corporation (Georgia) as a defendant and to make technical changes to its factual allegations. The Federal Rules of Civil Procedure provide that leave to amend a complaint should be “freely given when justice so requires.” Fed.R.Civ.P. 15(a). “Courts have interpreted [amendment] provisions liberally, in line with the Federal Rules’ overall goal of resolving disputes, insofar as possible, on the merits and in a single judicial proceeding.” Spartan Grain & Mill Co. v. Ayers, 517 F.2d 214, 220 (5th Cir.1975). 2 In explaining the amendment standard, the Eleventh Circuit Court of Appeals has observed that “unless a substantial reason exists to deny leave to amend, the discretion of the district court is not broad enough to permit denial.” Shipner v. Eastern Air Lines, Inc., 868 F.2d 401, 407 (11th Cir.1989). In determining whether a substantial reason exists to deny leave to amend, the Court must consider the following factors: (1) undue delay, bad faith, or dilatory motive on the part of the movant, (2) repeated failure to cure deficiencies by amendments previously allowed, (3) undue prejudice to the opposing party by virtue of allowance of the amendment, and (4) futility of amendment. Nolin v. Douglas County, 903 F.2d 1546, 1550 (11th Cir.1990).

Defendant expresses concern that amendment of the Complaint will prolong this action unnecessarily. Plaintiff assures the Court, however, that the amendment will cause no delay in this proceeding, (Mem. in Supp. of Pl.’s Mot. to Amend at 7), and the Court will hold Plaintiff to this assurance. Accordingly, in light of the fact that consideration of the above-mentioned factors does not convince the Court that a substantial reason exists to deny Plaintiffs motion, the Court concludes that justice requires allowing Plaintiff to amend its Complaint.

B. Defendant’s Motion for Partial Summary Judgment

Defendant has moved for summary judgment as to Count I on two grounds. First, Defendant asserts that the action is barred by the statute of limitations. (Br. in Supp. of Mot. for Summ.J. [Def.’s Br.] at 11-29). Alternatively, Defendant argues that the action is barred by the doctrine of laches. (Id. at 29-49).

1. Statute of Limitations

The parties apparently agree that this action is governed by 28 U.S.C. § 2462, which provides that an action “shall not be entertained unless commenced within five years from the date when the claim first accrued *693 ...” 3 Both parties also agree that the critical question in this case is when the Government’s claim “accrued.” Defendant asserts that a CWA claim accrues on the date of the violation—-in this case, not later than March 1982—and, as a result, Plaintiffs claim is barred by the statute of limitations as this action was not filed until February 14, 1991. Plaintiff, on the other hand, raises three arguments in opposition to the motion for summary judgment. First, the Government asserts that the claim did not accrue until Defendant’s unlawful activities were discovered. (PL’s Mem. in Opp’n to Mot. for Summ.J. [PL’s Mem.] at 9). Second, Plaintiff argues that Windward’s unlawful actions constitute an ongoing violation. (Id. at 16). Finally, Plaintiff alleges that the statute of limitation does not apply to the Government’s request for injunctive relief. (Id. at 22).

a. Statutes of limitation and injunctive relief

L3] As an initial matter, the Court must determine whether § 2462 applies at all to Plaintiffs request for injunctive relief. Plaintiff argues that, because that section applies only to actions “for the enforcement of any civil fine, penalty or forfeiture,” it does not apply to requests for injunctive relief. (Pl.’s Mem. at 22-23). The Court concludes, however, that the weight of authority dictates a contrary result. The majority of courts that have considered the question, including the United States Supreme Court, have held that when legal and equitable relief are available concurrently (i.e., when an action at law or equity could be brought on the same facts), “equity will withhold its relief ... where the applicable statute of limitations would bar the concurrent legal remedy.” Cope v. Anderson, 331 U.S. 461, 464, 67 S.Ct. 1340, 1341, 91 L.Ed. 1602 (1947). See also Russell v. Todd, 309 U.S. 280, 289, 60 S.Ct. 527, 532, 84 L.Ed. 754 (1940); United Transp. Union v. Florida East Coast Ry., 586 F.2d 520, 524 (5th Cir. 1978) (when “both legal and equitable relief [are] sought ... the statute of limitations bars both”); Gilbert v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. United States Steel Corp.
966 F. Supp. 2d 801 (N.D. Indiana, 2013)
United States v. Telluride Company
146 F.3d 1241 (Tenth Circuit, 1998)
State v. Chrysler Outboard Corp.
580 N.W.2d 203 (Wisconsin Supreme Court, 1998)
Westinghouse Electric Corp. v. Pennsylvania Department of Environmental Protection
705 A.2d 1349 (Commonwealth Court of Pennsylvania, 1998)
A-C Reorganization Trust v. E.I. DuPont De Nemours & Co.
968 F. Supp. 423 (E.D. Wisconsin, 1997)
United States v. Banks
Eleventh Circuit, 1997
Reichelt v. United States Army Corps of Engineers
969 F. Supp. 519 (N.D. Indiana, 1996)
United States v. Reaves
923 F. Supp. 1530 (M.D. Florida, 1996)
United States v. Telluride Co.
884 F. Supp. 404 (D. Colorado, 1995)
Fec v. Nrsc
877 F. Supp. 15 (District of Columbia, 1995)
United States v. Aluminum Co. of America
824 F. Supp. 640 (E.D. Texas, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
821 F. Supp. 690, 23 Envtl. L. Rep. (Envtl. Law Inst.) 21182, 1993 U.S. Dist. LEXIS 6584, 1993 WL 164089, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-windward-properties-inc-gand-1993.