United States v. United States Steel Corp.

966 F. Supp. 2d 801, 2013 WL 4495665, 77 ERC (BNA) 1644, 2013 U.S. Dist. LEXIS 118513
CourtDistrict Court, N.D. Indiana
DecidedAugust 21, 2013
DocketNo. 2:12-cv-304
StatusPublished
Cited by3 cases

This text of 966 F. Supp. 2d 801 (United States v. United States Steel Corp.) is published on Counsel Stack Legal Research, covering District Court, N.D. Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. United States Steel Corp., 966 F. Supp. 2d 801, 2013 WL 4495665, 77 ERC (BNA) 1644, 2013 U.S. Dist. LEXIS 118513 (N.D. Ind. 2013).

Opinion

OPINION and ORDER

PHILIP P. SIMON, Chief Judge.

The Environmental Protection Agency and three similar state entities from Indiana, Michigan, and Illinois initiated this action against U.S. Steel in an 18-count complaint. (For simplicity’s sake, I will refer to the Plaintiffs in this case collectively as the EPA). The EPA alleges that three of U.S. Steel’s plants — one in each of the three states — are and have been violating the Clean Air Act. U.S. Steel says its done no such thing, but the merits of the case will be decided later. The only thing presently before me is whether Count 1 and parts of Count 3 are barred by the applicable statute of limitations and must therefore be immediately dismissed. As explained in detail below, I only buy half of that argument. U.S. Steel’s Motion to Dismiss will therefore be granted in part and denied in part.

BACKGROUND

In 1990, U.S. Steel performed a “reline” of its No. 4 furnace at its Gary Works facility in Gary, Indiana. A reline is the process whereby the furnace is completely shut down and the interior lining is updated. The legal issues raised in U.S. Steel’s motion to dismiss all really emanate from this 1990 relining. One might reasonably wonder why a court in the year 2013 is dealing with actions taken by a company some 23 years earlier; U.S. Steel is wondering the same thing. In all events, U.S. Steel believes it could do the relining of the furnace without a permit, but the EPA disagrees. To understand the parameters of this disagreement, we have to dive into obscure world of the Clean Air Act (“CAA”), its regulations, and the myriad of acronyms that flow from them.

Here’s a broad outline of the parts of the CAA applicable to this case. The CAA establishes two types of air permits: construction permits and operating permits. Both types of permits are at issue in this case. The construction permitting program emerged from the 1977 amendments to the CAA which required all new “sources” — factories, power plants, refineries, etc. — to undergo a “New Source Re[804]*804view” (NSR). Under the NSR process, all post-1977 sources are required to meet various emission limits for pollutants. NSR consists of two programs — prevention of significant deterioration in air quality (PSD) and non-attainment with air quality standards (NA/NSR). Both of those programs are at issue in this case, but the differences are fairly immaterial to ‘ U.S. Steel’s motion to dismiss, so to simplify matters I’ll just refer to the whole construction permitting process as “NSR.”

Under the NSR program, the new source must obtain a pre-construction permit from the EPA, demonstrate that the construction will not increase emissions above a certain threshold, and show that facility operations are in continuous compliance with the best available control technology (BACT). The NSR permit then specifies what construction is allowed, what emission limits must be met, and how often the emissions source must be operated.

In addition to these construction permits, most sources also have to obtain operating permits, which are known as Title V permits. A Title V permit grants a source permission to operate, and it includes all air pollution requirements that apply to the source, including emissions limits and monitoring, record keeping, and reporting requirements.

Most of this CAA permitting — both NSR and Title V — is actually done at the state level. The EPA establishes the basic requirements for the CAA, and states can then take those minimum thresholds and develop their own unique requirements and procedures in what is called a State Implementation Plan (“SIP”). Indiana has codified its SIP at Titles 326 and 327 of the Indiana Administrative Code. Indiana’s SIP generally seems to mirror the federal requirements, including requirements that new sources must obtain a pre-construction NSR permit and install BACT.

All of this applies to new sources, those built after 1977. The Gary Works plant, however, has a lot of dust on it; steel production began there in the early part of the last century. That doesn’t take the plant out of the regulatory woods, however, because the CAA says that even pre1977 plants must comply -with the NSR permitting program any time a “major modification” is made to them. Enter the 1990 relining project. U.S. Steel concluded that the reline wasn’t a major modification, so it didn’t bother seeking a preconstruction NSR permit. Then, in 1996, U.S. Steel applied for a Title V operating permit, which was eventually issued by the state of Indiana. The EPA now argues that the 1990 reline was a major modification, that U.S. Steel thus should have sought a preconstruction NSR permit, and that consequently the Title V permit was improperly granted and should be invalidated. More specifically, the EPA alleges in Count 1 that U.S. Steel performed a major modification, which violated the CAA and Indiana’s SIP by operating Gary Works without an NSR permit and without BACT. In Count 3, the EPA alleges that U.S. Steel is operating Gary Works in violation of the Title V permitting program under the CAA and Indiana’s SIP.

Whether or not the 1990 reline was a major modification is likely to be a difficult question to answer. See, e.g., U.S. v. Midwest Generation, LLC, 720 F.3d 644, 645 (7th Cir.2013) (“The question ‘how much repair or change requires a permit?’ has been contentious and difficult.”). But that substantive question is not yet at issue here. Instead, the key question in U.S. Steel’s motion to dismiss is procedural: Did the EPA blow the statute of limitations by waiting until 2012 to file a lawsuit about the 1990 reline?

[805]*805ANALYSIS

A motion to dismiss pursuant to Rule 12(b)(6) “challenges the sufficiency of the complaint to state a claim upon which relief may be granted.” Hollinan v. Fraternal Order of Police of Chi. Lodge No. 7, 570 F.3d 811, 820 (7th Cir.2009). A plaintiffs failure to adhere to a statute of limitations is an affirmative defense and “is rarely a good reason to dismiss under Rule 12(b)(6).” Reiser v. Residential Funding Corp., 380 F.3d 1027, 1030 (7th Cir.2004). At the motion to dismiss stage, “the question is only whether there is any set of facts that if proven would establish a defense to the statute of limitations[.]” Clark v. City of Braidwood, 318 F.3d 764, 768 (7th Cir.2003). A plaintiff need not anticipate affirmative defenses in his complaint in order to survive a motion to dismiss. United States v. Lewis, 411 F.3d 838, 842 (7th Cir.2005) (citing Gomez v. Toledo, 446 U.S. 635, 640, 100 S.Ct. 1920, 64 L.Ed.2d 572 (1980)); see also Indep. Trust Corp. v. Stewart Info. Serv. Corp., 665 F.3d 930, 935 (7th Cir.2012). “The exception occurs where ... the allegations of the complaint itself set forth everything necessary to satisfy the affirmative defense, such as when a complaint plainly reveals that an action is untimely under the governing statute of limitations.” Lewis, 411 F.3d at 842 (citing Leavell v. Kieffer,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

USA v. Luminant Generation Co.,L.L.C., et a
905 F.3d 874 (Fifth Circuit, 2018)
Global Community Monitor v. Mammoth Pacific, L.P.
230 F. Supp. 3d 1235 (E.D. California, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
966 F. Supp. 2d 801, 2013 WL 4495665, 77 ERC (BNA) 1644, 2013 U.S. Dist. LEXIS 118513, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-united-states-steel-corp-innd-2013.