A-C Reorganization Trust v. E.I. DuPont De Nemours & Co.

968 F. Supp. 423, 27 Envtl. L. Rep. (Envtl. Law Inst.) 21472, 1997 U.S. Dist. LEXIS 9549, 1997 WL 366074
CourtDistrict Court, E.D. Wisconsin
DecidedJune 27, 1997
Docket94-C-574
StatusPublished
Cited by11 cases

This text of 968 F. Supp. 423 (A-C Reorganization Trust v. E.I. DuPont De Nemours & Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A-C Reorganization Trust v. E.I. DuPont De Nemours & Co., 968 F. Supp. 423, 27 Envtl. L. Rep. (Envtl. Law Inst.) 21472, 1997 U.S. Dist. LEXIS 9549, 1997 WL 366074 (E.D. Wis. 1997).

Opinion

DECISION AND ORDER

STADTMUELLER, Chief Judge.

This action includes causes of action under the Comprehensive Environmental Response, Compensation and Liability Act (“CERCLA”), 42 U.S.C. § 9601 et seq., and other theories, arising from the presence of wastes at a site in Oak Creek, Wisconsin (“Oak Creek Facility”). Before the court is the motion to amend the complaint of plaintiffs A-C Reorganization Trust (“A-C Trust”) and The Edison M. Boerke Trust (“Boerke Trust”) (collectively, “Plaintiffs”). Plaintiffs seek to add a claim under 42 U.S.C. § 6972(a)(1)(B), part of the Resource Conservation and Recovery Act (“RCRA”), 42 U.S.C. §§ 6901 et seq. Defendant/third-party plaintiff E.I. DuPont de Nemours (“DuPont”) and defendants/third-party defendants EPEC Polymers, Inc. (“EPEC”) and Tennessee Gas Pipeline Company (“Tennessee Gas”) (together, the “Tenneco Defendants”) oppose the motion to amend. The motion is. fully briefed and ready for decision.

I. LEGAL STANDARD

Once a party’s leave to amend as of right expires, amendments may only be made after adverse parties consent or by leave of court, which shall be freely given as justice requires. Fed.R.Civ.P. 15(a). Consider *426 ations that justify denying leave to amend include undue delay, bad faith, dilatoriness, undue prejudice, repeated failure to cure deficient pleading, and futility of the amendment. Perrian v. O’Grady, 958 F.2d 192, 194 (7th Cir.1992). Futility requires that an amendment cannot possibly support a valid theory of liability. Goulding v. Feinglass, 811 F.2d 1099, 1103 (7th Cir.), cert. denied, 482 U.S. 929, 107 S.Ct. 3215, 96 L.Ed.2d 701 (1987). A court can also deny amendment where litigation is artificially protracted by bad faith or absent-mindedness. Fort Howard Paper Co. v. Standard Havens, Inc., 901 F.2d 1373, 1379 (7th Cir.1990). When a motion to amend is filed well after the original complaint, the party seeking amendment must substantiate it, as it is addressed to the court’s discretion and “requires more to compel acceptance than the fact that the pleading sought to be added states a claim.” Glatt v. Chicago Park Dist., 87 F.3d 190, 194 (7th Cir.1996). In considering any delay, the court “should consider the likelihood that the new claim is being added in a desperate effort to protract the litigation and complicate the defense; its probable merit; whether the claim could have been added earlier; and the burden on the defendant in having to meet it.” Id.

II. FACTUAL OVERVIEW

Plaintiffs make the following allegations in their RCRA claim: Defendants’ past generation of waste at and past operation and ownership of the Oak Creek Facility have given rise to an imminent and substantial endangerment to health and the environment. The conditions causing this endangerment include the presence in the soil, surface water or groundwater of solid or hazardous waste in amounts or concentrations exceeding established state and federal limits, as well as the migration of these wastes toward or into Lake Michigan. Plaintiffs have met the requirements of bringing such a private claim: (1) neither the Administrator of the U.S. Environmental Protection Agency (“EPA”) nor the State of Wisconsin has commenced any action, engaged in any removal or remedial action, incurred any costs, obtained any court orders, or issued any administrative orders that would bar this action under 42 U.S.C. § 6972(b)(2)(B) or (C); and (2) Plaintiffs provided 90 days notice of the claim to the EPA, Wisconsin, and defendants. 42 U.S.C. § 6972(b)(2)(A).

Testing completed by Plaintiffs in December 1996 and by the Wisconsin Department of Natural Resources (“DNR”) in 1995 disclosed that soil at the Oak Creek Facility contains, in significant amounts, solid or hazardous wastes including toxic metals, toxic semi-volatile organic compounds, and toxic volatile organic compounds. 1 Plaintiffs’ testing also revealed that the Oak Creek Facility’s groundwater contained, in significant amounts, some of these same as well as additional solid or hazardous wastes. 2 Almost all of these wastes in the groundwater were found to be migrating toward or into Lake Michigan. 3

In addition to Plaintiffs’ allegations, there are uncontested facts relating to EPA and DNR actions regarding the site. Because Plaintiffs must substantiate the motion to amend, it is appropriate to consider these facts.

EPA’s involvement with the Oak Creek Facility began in 1985, when it commenced a removal action to halt the release or threatened release of hazardous substances. Un *427 der EPA’s and DNR’s oversight, DuPont excavated the contaminated construction debris, incinerated it, and redeposited the remediated materials onto the A-C Trust parcel.

On September 28, 1995, EPA issued an Administrative Order on Consent, CERCLA § 106, 42 U.S.C. § 9606 (“Consent Order”), regarding arsenic contamination on the Boerke Trust parcel. DuPont Ex. 12. The Consent Order requires DuPont to perform an “Engineering Cost Evaluation/Cost Analysis” (“EE/CA”), which is one of the first steps in a non-time critical removal action. DuPont Ex. 11. The EE/CA’s purpose to investigate the site, characterize the potential risks involved, and to “identify the scope, goals, and objective for a removal action” and is one step in the removal action process. DuPont Ex. 11 at 31, 5. EPA makes a final decision on the scope and nature of the cleanup.

In March 1996, DNR issued an order requiring DuPont and the Trusts to take immediate action to move some incinerated materials in wastewater lagoons away from an eroding lake bluff. DNR Order, Tenneco Defendants’ Ex. E at 3-4. DNR stated the order was justified by the materials’ imminent threat to the environment. Id. at 2. In addition, DuPont was to evaluate alternatives for removing, containing, or treating the thermally-treated materials located on the A-C Trust Parcel. Id. at 3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Residents of Gordon Plaza v. Cantrell
25 F.4th 288 (Fifth Circuit, 2022)
Sierra Club v. Chesapeake Operating, LLC
248 F. Supp. 3d 1194 (W.D. Oklahoma, 2017)
Clean Harbors, Inc. v. CBS Corp.
875 F. Supp. 2d 1311 (D. Kansas, 2012)
Francisco Sanchez v. Esso Standard Oil Co.
572 F.3d 1 (First Circuit, 2009)
Carrier Corp. v. Piper
460 F. Supp. 2d 853 (W.D. Tennessee, 2006)
United States v. American Electric Power Service Corp.
137 F. Supp. 2d 1060 (S.D. Ohio, 2001)
Anderson v. Cornejo
199 F.R.D. 228 (N.D. Illinois, 2000)
Organic Chemical Site PRP Group v. Total Petroleum, Inc.
58 F. Supp. 2d 755 (W.D. Michigan, 1999)
Lefebvre v. Central Maine Power Co.
7 F. Supp. 2d 64 (D. Maine, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
968 F. Supp. 423, 27 Envtl. L. Rep. (Envtl. Law Inst.) 21472, 1997 U.S. Dist. LEXIS 9549, 1997 WL 366074, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-c-reorganization-trust-v-ei-dupont-de-nemours-co-wied-1997.