United States v. Bethlehem Steel Corp.

829 F. Supp. 1047, 1993 WL 336590
District Court, N.D. Indiana·Decided August 31, 1993·No. 2:90-CV-326-RL·Published·Cited by 6 cases

Opinion

MEMORANDUM OPINION AND ORDER

LOZANO, District Judge.

The Plaintiff, the United States (“United States”) brought this action against Bethlehem Steel Corporation (“Bethlehem”) alleg *1050 ing that Bethlehem violated the Resource Conservation and Recovery Act (“RCRA”), 42 U.S.C. § 6901, et seq., and the Safe Drinking Water Act (“SDWA”), 42 U.S.C. § 300f, et seq. In an order dated March 19, 1993, 829 F.Supp. 1023, this Court found that Bethlehem failed to perform the corrective action program required by two Underground Injection Control (“UIC”) Permits that the Environmental Protection Agency (the “EPA”) issued to Bethlehem. As to the United States’ remaining five claims, the Court found that Bethlehem violated numerous RCRA requirements in its operation and management of three hazardous waste management units at its Burns Harbor facility (“the Facility”), i.e., a landfill and two terminal polishing lagoons. The Court granted the United States’ request for injunctive relief and held a civil penalty hearing, which began on July 6, 1993, and concluded on July 21, 1993. 1 After hearing testimony and reviewing the parties’ exhibits, this Court hereby issues the following findings of fact and conclusions of law.

FINDINGS OF FACT

Bethlehem’s Two Hazardous Waste Underground Injection Wells

Bethlehem owns and operates two Class I underground injection wells at the Facility. Bethlehem started using these wells in 1968 and continues to use them to dispose of waste ammonia liquor generated at the Facility. The waste ammonia liquor disposed of in the injection wells is a characteristic hazardous waste within the meaning of Section 1004(5) of RCRA, 42 U.S.C. § 6903(5) and 40 C.F.R. § 261.32. In accordance with the requirements of Section 1421 of SDWA, 42 U.S.C. § 300h, and 40 C.F.R. Part 144, on September 30,1985, the EPA issued to Bethlehem two UIC permits to operate the two underground injection wells. Each UIC permit authorizes Bethlehem to dispose of waste ammonia liquor into the wells in accordance with each permit and the UIC program.

On or about October 2, 1985, Bethlehem informed EPA’s, Region V Technical Programs Branch that Bethlehem fully intended to comply with the Preliminary Assessment requirements contained in Attachment F of Bethlehem’s two UIC permits in accordance with the schedule specified in those permits. On November 15, 1985, Bethlehem filed an administrative appeal of the UIC permits.

On January 19,1989, EPA rejected Bethlehem’s appeal, and the permits became final agency action. Bethlehem then appealed EPA’s decision to the Seventh Circuit Court of Appeals. The Seventh Circuit, which consolidated Bethlehem’s appeal with a similar appeal by Inland Steel Company, rejected the steel companies’ claims and upheld the validity of the UIC permits, including the corrective action requirements. Inland Steel Co. v. EPA 901 F.2d 1419 (7th Cir.1990).

During the course of the appeal, Inland had asked the Seventh Circuit to stay the applicability of the permits pending judicial review, but the Seventh Circuit denied the motion. Bethlehem therefore, did not receive a stay of the permits. Bethlehem knew that absent a stay, it was required to comply with the terms of the permits. Since January 19, 1989, Bethlehem has been required to but has failed to comply with the corrective action requirements of its UIC permits according to the terms of its UIC permits. Bethlehem’s two UIC permits required Bethlehem to submit to EPA the Preliminary Assessment Plan (“PSA”) by February 27, 1989, and a Remedial Investigation (“RI”) Report and Corrective Action Plan by July 19, 1989. Neither the PSA, the RI, nor the Corrective Action Plan were submitted by the required dates. As a result of Bethlehem’s prolonged failure to comply with its UIC permits, on April 19, 1990, EPA notified Bethlehem and the State of Indiana that Bethlehem was in violation of the SDWA and RCRA, due to Bethlehem’s failure to comply with Part I(J) and Part III(F) of its UIC Permits issued on September 30, 1985, and therefore, subject to civil penalties of $25,000 for each day of noncompliance.

The undisputed evidence shows that Bethlehem never attempted compliance prior to receiving the United States’ Notice of Violation in April 1990. Further, Bethlehem did *1051 not commence making the PSA required by the UIC permits until July 16, 1990, and not until January 31, 1992, did it submit its final “DRAFT” report on the assessments for the Solid Waste Management Units (“SWMUs”) it has identified to date. While EPA accepted Bethlehem’s delayed submissions, it never agreed that its acceptance of those late submissions would serve to extend Bethlehem’s time frame for compliance with its UIC permits. Bethlehem had since September 30, 1985, to either comply or initiate compliance with the permits. Instead, Bethlehem chose to not comply and appealed.

Bethlehem argues that it was impossible to adhere to the time schedule in the UIC permits. However, the evidence does not support Bethlehem’s contention. Bethlehem employs more than 30,000 employees nationwide, and more than 6,000 work at its 3300 acre Burns Harbor Plant. Once it started to undertake work in July 1990, Bethlehem could have assigned additional employees to reduce by 40% the time it took to complete the PSA. On July 16, 1990, three months after the enforcement action was initiated, Bethlehem submitted documents to EPA, as part of the PSA, which were taken from existing file information. These documents were compiled in only eleven days. The compilation of existing information could have been submitted to EPA by the permit deadline of February 27,1989. Even if these documents were not complete, Bethlehem could have shown its good faith by attempting to partially comply by the deadlines.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Bethlehem Steel Corp., 829 F. Supp. 1047, 1993 WL 336590 (N.D. Ind. 1993).

829 F. Supp. 1047 (United States v. Bethlehem Steel Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State v. Elementis Chemical, Inc.
922 A.2d 678 (Supreme Court of New Hampshire, 2007)
United States v. Torlaw Realty, Inc.
483 F. Supp. 2d 967 (C.D. California, 2007)
United States v. Jg-24, Inc.
331 F. Supp. 2d 14 (D. Puerto Rico, 2004)
United States v. WCI Steel, Inc.
72 F. Supp. 2d 810 (N.D. Ohio, 1999)
A-C Reorganization Trust v. E.I. DuPont De Nemours & Co.
968 F. Supp. 423 (E.D. Wisconsin, 1997)
United States v. Ekco Housewares, Inc.
62 F.3d 806 (Sixth Circuit, 1995)