United States v. W.F. Brinkley & Son Construction Company, Inc. And William F. Brinkley, Jr.

783 F.2d 1157, 1986 U.S. App. LEXIS 22434, 54 U.S.L.W. 2508
CourtCourt of Appeals for the Fourth Circuit
DecidedFebruary 21, 1986
Docket84-5355
StatusPublished
Cited by33 cases

This text of 783 F.2d 1157 (United States v. W.F. Brinkley & Son Construction Company, Inc. And William F. Brinkley, Jr.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. W.F. Brinkley & Son Construction Company, Inc. And William F. Brinkley, Jr., 783 F.2d 1157, 1986 U.S. App. LEXIS 22434, 54 U.S.L.W. 2508 (4th Cir. 1986).

Opinion

SNEEDEN, Circuit Judge:

The defendants, William F. Brinkley, Jr. and W.F. Brinkley & Son Construction Company (“Brinkley & Son”), appeal their convictions of one count of conspiring to rig bids on a construction project in violation of Section 1 of the Sherman Act, 15 U.S.C. § 1. Brinkley, president of Brinkley & Son was sentenced to 30 days incarceration and fined $25,000. The. company was fined $100,000.

The appellants contend that the trial court erred by denying their motion for judgment of acquittal and by improperly instructing the jury on the definition of bid rigging and on the requisite intent to violate Section 1 of the Sherman Act. Finding no error below, we affirm their convictions.

I.

This case concerns the 1979 bidding process for a portion of the Pasquotank River Supply Project undertaken by Elizabeth City, North Carolina. For several years Elizabeth City considered the need to supplement its raw water supply, finally concluding that obtaining water from the adjacent Pasquotank River was the best alternative. The overall project was divided into several subprojects, each of which was to be awarded through a competitive bidding process. Contract 12, at issue in this case, involved constructing a pumping station at the river and laying a pipeline system to carry the water to a treatment plant.

Contract 12, along with several other subprojects, was first let for bidding in 1977. The city received bids from Brinkley & Son; Dickerson, Inc. (“Dickerson”); Crain & Denbo, Inc. (“Crain & Denbo”); and Dellinger, Inc. 1 Brinkley & Son was the low bidder with a bid of $653,000. Contract 12 was not awarded in 1977, however, because bids on other projects were significantly higher than expected and the city decided not to award any of the contracts.

In the summer of 1979, Elizabeth City again offered Contract 12 for bidding. Brinkley & Son, Dickerson, and Crain & Denbo submitted bids. Brinkley & Son was again the low bidder — this time with a significantly higher bid of $995,000 — and was awarded the contract.

At trial, representatives of both Dickerson and Crain & Denbo testified as immunized witnesses for the government concerning events which preceded the 1979 bidding. Frank Carpenter, the Utility Division manager for Dickerson, testified that he spoke with William Brinkley prior to the bidding and told him that they should try to get the contract together again 2 and that Dickerson would “honor” Brinkley’s low bid from 1977. Joint Appendix at 59-60 and 103. Carpenter stated that Brinkley indicated his agreement with that suggestion. Joint Appendix at 60. While Carpenter could not recall the specific wording of his conversation with Brinkley — a point on which he was vigorously cross-examined by defense counsel — he remembered that the substance of the conversation was that *1159 Dickerson would intentionally submit a high or “complementary” bid to ensure that Brinkley would again be the low bidder. Joint Appendix at 79. Carpenter further testified that, to the best of his recollection, the amount which Dickerson bid in 1979 for Contract 12 was given to him by Brinkley. Joint Appendix at 73.

Harold Crain, Jr., and Edward Denbo, Jr., of Crain & Denbo, the third company to submit a bid in 1979, also testified. Both Crain and Denbo stated that, on the morning of the day that bids were to be submitted, they telephoned William Brinkley and asked that he give them a “safe” number to bid on Contract 12. Joint Appendix at 165. Both further testified that Brinkley agreed to give them an amount to bid on the project. Joint Appendix at 129-130 and 165. Crain and Denbo indicated that they had originally intended to submit a competitive bid but were unable to complete the bid when a subcontractor failed to give them a price for the pipeline work. Joint Appendix at 145 and 167. Thus, their options at that point were to submit no bid, to guess on an amount, or to obtain a safe number from another contractor. Joint Appendix at 156. They testified that they rejected the alternative of failing to submit a bid because they did not want to offend the project engineer. Joint Appendix at 147. Fearing a costly mistake if they simply guessed on a bid amount, they decided to contact William Brinkley for a safe number to bid. 3 Joint Appendix at 149. Both Crain and Denbo stated during cross-examination that they decided not to submit a competitive bid prior to discussions with Brinkley. Joint Appendix at 146 and 181.

Gene Greer, an employee of Crain & Denbo, then testified that he went to Brinkley’s motel shortly before noon on the day of the bidding and was given an amount to bid by Brinkley. Greer stated that he then filled out a bid, placed it in a sealed envelope, and gave it to Brinkley to turn in for him. Joint Appendix at 185-187. Greer further testified that Brinkley appeared to be working on Brinkley & Son’s bid, which was due at 2:00 p.m. that afternoon. Joint Appendix at 185-186.

II.

The appellants first argue that the district court erred in denying their motion for judgment of acquittal, both at the conclusion of the government’s case and at the close of all the evidence, because there was insufficient evidence of an agreement between Crain & Denbo and appellants to rig bids. 4 Pointing out that unilateral action cannot violate Section 1 of the Sherman Act, the appellants argue that there was no agreement to rig bids because Crain and Denbo 5 had decided not to compete for Contract 12 before contacting Brinkley. 6 Appellants maintain that Crain & Denbo’s decision was thus the result of unilateral action and not the result of a conspiracy involving the appellants. Under the appellants’ view, one could never be convicted of bid rigging for simply giving a competitor a safe number to bid once that competitor *1160 had decided for himself not to compete for a particular contract. 7

We agree with appellants’ assertion that unilateral action does not violate Section 1, but that is the extent of our agreement with their position. Contrary to the appellant’s argument that Crain & Denbo acted unilaterally, the facts of this case clearly demonstrate concerted action by Crain & Denbo and Brinkley on the submission of bids to Elizabeth City. While Crain and Denbo might have decided between themselves not to submit a competitive bid on Contract 12, they went beyond unilateral action when they contacted Brinkley requesting a safe number to bid and he consented to give them one. At that point, there was an agreement between two competitors pursuant to which bids would be submitted to Elizabeth City. Such an agreement is clearly bid rigging. As Judge Russell explained in United States v. Portsmouth Paving Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Brent Brewbaker
87 F.4th 563 (Fourth Circuit, 2023)
WILLIAMS v. THE ESTATES LLC
M.D. North Carolina, 2021
Corizon, LLC v. Wainwright
M.D. Tennessee, 2020
Powell v. Shelton
386 F. Supp. 3d 842 (W.D. Kentucky, 2019)
United States v. Katakis
252 F. Supp. 3d 988 (E.D. California, 2017)
In re London Silver Fixing, Ltd.
213 F. Supp. 3d 530 (S.D. New York, 2016)
United States v. Jackson
926 F. Supp. 2d 691 (E.D. North Carolina, 2013)
Amos v. Aspen Alps 123, LLC
2012 CO 46 (Supreme Court of Colorado, 2012)
Isaac v. North Carolina Department of Transportation
192 F. App'x 197 (Fourth Circuit, 2006)
United States v. Gosselin World Wide Moving, N.V.
411 F.3d 502 (Fourth Circuit, 2005)
Shaw v. United States
371 F. Supp. 2d 265 (E.D. New York, 2005)
Gravity Inc v. Microsoft Corp
309 F.3d 193 (Fourth Circuit, 2002)
No. 01-2458
309 F.3d 193 (Fourth Circuit, 2002)
DJ Manufacturing Corp. v. Tex-Shield, Inc.
275 F. Supp. 2d 109 (D. Puerto Rico, 2002)
Zachair, Ltd. v. Driggs
965 F. Supp. 741 (D. Maryland, 1997)
Ehredt Underground, Inc. v. Commonwealth Edison Co.
848 F. Supp. 797 (N.D. Illinois, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
783 F.2d 1157, 1986 U.S. App. LEXIS 22434, 54 U.S.L.W. 2508, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-wf-brinkley-son-construction-company-inc-and-william-ca4-1986.